CNE Review – March 2026

Published on March 25, 2026 / Leer en español

See all editions of the
CNE Review
SHARE

In This Issue

In this edition of the CNE Review, our Policy Director Sergio M. Marxuach analyzes the PREPA Title III bankruptcy case as it enters its ninth year: still unresolved, and with enormous consequences for Puerto Rico’s electricity rates, grid investment, and economic future.

We also include a Data Snapshot showing how the size of a potential settlement would translate directly into costs for ratepayers.

Finally, in our On Our Radar section, we share a recent article on technology and the economy that caught our attention this month.

Insights + Analysis from CNE

PREPA Title III: Threading the Needle

By Sergio M. Marxuach, Policy Director

Nine years into PREPA’s Title III bankruptcy proceeding, there is still no agreement between the Financial Oversight and Management Board and the utility’s major creditor groups. The stakes could not be higher: how this case is resolved will shape Puerto Rico’s electricity rates, its capacity to attract private investment in renewable energy, and the long-term viability of the grid itself.

A November 2024 First Circuit ruling changed the landscape. The court affirmed that bondholders hold an $8.5 billion claim secured by a lien on PREPA’s net revenues, but also clarified that their actual recovery depends on what those revenues turn out to be, and that they have no recourse to any other government assets. Both sides, in other words, had something to celebrate.

The single most consequential variable is time. Every year that PREPA remains in bankruptcy is a year in which grid investment is deferred, federal incentives go unused, costly litigation drags on, transition to renewables is delayed, work on the master Integrated Resource Plan stalls, and the island’s population and economic base continue to erode – reducing the very revenue base that is expected to service PREPA’s restructured debt.

The analysis in this brief identifies two bookend scenarios. At the low end, the FOMB’s proposed 23-cent recovery, roughly $2.3 billion in new bonds, would add an estimated 1.6 cents per kWh to customer bills. At the high end, full repayment of $11 to $12 billion would require surcharges of 6 to 9 or more cents per kWh, pushing blended rates to 34 to 37 cents and almost certainly triggering a rate-revenue death spiral that would accelerate grid defection, erode the revenue base, and ultimately make the plan unworkable.

The window for a reasonable settlement is narrow, and every year of delay is itself a cost Puerto Rico cannot afford.

Data Snapshot

Puerto Rico already pays 27.5 cents per kWh (including provisional charges approved by the regulator at the end of 2025), well above the 20-cent affordability threshold recognized by both the Legislature and the Oversight Board. The size of PREPA’s bankruptcy settlement will directly determine how much higher the rates go. These two scenarios illustrate the range of outcomes analyzed in the brief, from the FOMB’s current proposal to full repayment, and what each would cost ratepayers every month. For a full analysis, read the brief.

On Our Radar

The Anthropic Economic Index: AI’s Uneven Footprint on Labor Markets – Anthropic’s January 2026 Economic Index report — the most comprehensive empirical analysis to date of how artificial intelligence (AI) is reshaping labor markets — finds that nearly half of all occupations now see Claude being used for at least a quarter of their tasks, up from 36% when the Index was first introduced. The pattern of use has also shifted: augmentation (52% of interactions) has now overtaken automation (45%), suggesting that workers are increasingly using AI to extend their capabilities rather than simply replacing discrete tasks. Estimated productivity gains, when adjusted for model reliability on complex tasks, are projected at approximately one percentage point of annual labor productivity growth over the next decade.

Critically, the Index also surfaces a structural concern: Claude disproportionately handles higher-skill tasks within any given occupation, meaning that when those tasks are displaced, the remaining work is systematically less complex — a dynamic the report terms net occupational deskilling. AI adoption remains highly uneven, strongly correlated with per capita income across countries, and concentrated within the top decile of task types. For policymakers in Puerto Rico and across the Caribbean, the Index’s findings underscore both the transformative potential and the distributional risks of AI adoption in lower-income, service-dependent economies.

PREPA Title III: Threading the Needle

PREPA Title III: Threading the Needle

Published on March 24, 2026 / Leer en español

Sergio portrait
Policy Director
DOWNLOAD
SHARE

The Puerto Rico Electric Power Authority (PREPA) filed for debt restructuring on July 2, 2017, under Title III of the Puerto Rico Oversight, Management, and Economic Stability Act (PROMESA). The case is administered by the U.S. District Court for the District of Puerto Rico, with Judge Laura Taylor Swain presiding. Title III proceedings are bankruptcy-adjacent but are not governed directly by the U.S. Bankruptcy Code; the judge applies select provisions of federal bankruptcy law, incorporated by reference into PROMESA, to the U.S. territory’s public debtors. Under this structure, Puerto Rico has found that declaring bankruptcy is expensive. Total advisory and professional fees paid to attorneys, financial advisors, and consultants across all parties in all Title III proceedings under PROMESA have now surpassed $1.5 billion, a figure that sets a record for a municipal restructuring of this type.

PREPA’s case is the last major outstanding Title III restructuring. As we enter the ninth year of the never-ending saga known as the PREPA Title III case or bankruptcy process, and sure as winter turns to spring, there is no agreement yet between the Financial Oversight and Management Board (FOMB) and PREPA’s major creditor groups, including its bondholders.

Why a Reasonable Settlement is Important

Rebuilding and modernizing Puerto Rico’s electric power system represents one of the most complex institutional, financial, and technical challenges currently facing any U.S. jurisdiction. Nearly a decade after Hurricane Maria devastated the island’s grid in September 2017, and almost nine years into PREPA’s Title III bankruptcy proceeding, the system remains trapped in a web of mutually reinforcing structural contradictions that no single reform has successfully addressed.

The Puerto Rico electric power system consists of six critical subsystems: (1) the restructuring of PREPA’s financial obligations; (2) the reconstruction of the damage caused to the grid by Hurricane Maria; (3) the transition to 100% renewable generation by 2050, as mandated by Puerto Rico law; (4) the operation of the transmission and distribution (T&D) grid pursuant to the terms and conditions of the LUMA T&D operation and management agreement; (5) the operation of the PREPA legacy generation fleet pursuant to the terms and conditions of the Genera PR operation and management agreement; and (6) the drafting and implementation of the Integrated Resource Plan (IRP) for the entire electric system.

These six subsystems are not independent policy challenges or technical tasks that can each be solved in isolation from the others. Collectively, they form a tightly connected system with reinforcing feedback loops and critical balancing mechanisms, which oftentimes interact in a nonlinear, dynamic way that inevitably produces outcomes at variance with stated policy objectives. In the context of Puerto Rico’s electricity sector policy, these concepts explain why standard policy tools —rate design, capacity expansion, regulatory standards— often fail to produce the intended effects. The Title III case impacts them all.

When analyzing potential settlement deals with bondholders, it is necessary to keep in mind the following:

  • The Puerto Rican economy and the Puerto Rico electric system interact with each other. Affordable, reliable electric power is necessary, but not sufficient, to generate sustainable economic growth. Higher economic growth, in turn, increases employment and demand for electricity, which requires new investment to meet the additional demand, which eventually supports additional economic activity, which further increases employment and economic growth, and so on. This cycle also works in reverse: when power costs are high or electric service is unreliable, economic activity contracts, employment decreases, and demand for electricity declines. A downturn in demand for electricity, if permanent, creates a difficult situation as the operator still has to generate sufficient revenues to operate the system, leading to increases in rates, which in turn put downward pressure on employment and economic activity, further decreasing demand for electricity. Any proposed settlement with PREPA’s bondholders has to take into account this interactive relationship between the island’s economy and the cost of electricity.
  • In addition, Puerto Rico has approximately $13.5 billion available in FEMA Public Assistance obligations for grid reconstruction, with total federal allocations exceeding $16 billion across all programs, most of which remains unspent. A swift and reasonable settlement of PREPA’s bankruptcy would theoretically restore market confidence and allow PREPA to leverage federal funds with private co-investment. A prolonged dispute or full repayment would destroy this leverage.
  • The prolonged bankruptcy has also been a headwind on new investment in renewable energy generation at the utility-scale level. Most private investors seeking to finance a new solar farm with a power purchase and operating agreement (PPOA) with PREPA would be quite reluctant, and reasonably so in our opinion, to execute a long-term agreement with a bankrupt entity. The Title III case, therefore, is effectively a bottleneck slowing down new private sector investment in renewable generation at scale. This is important because if Puerto Rico currently generated, say, 40% of all its electricity using utility-scale solar generation, it would produce materially significant net savings on fuel expenditures that could then be passed on to ratepayers. Replacing current fossil fuel generation, which has a highly variable cost dependent on events affecting the global fuel markets, with lower, fixed cost utility-scale renewable generation would (1) permanently decrease PREPA’s fuel expense and, everything else being equal, (2) significantly improve PREPA’s operating margin, which would provide headroom for significantly lowering customer rates.
  • The long-term planning for the system has also been affected by the long-running bankruptcy procedures. It is difficult to plan large expenditures for fixed investments with a long useful life if the planners do not know how much of PREPA’s outstanding legacy debt would have to be paid and on what terms, and if future access to the capital markets remains uncertain. The IRP is the master planning document for the electric power system, covering a 20-year planning horizon. The 2019 IRP, prepared by Siemens, recommended aggressive renewable deployment, grid decentralization through mini-grids, and phased retirement of fossil fuel assets. The 2025 IRP, currently in development by LUMA with interim filings in November 2024 and February 2025, represents the first comprehensive update since LUMA assumed T&D operations. The IRP’s recommendations regarding capital investment, decommissioning timelines, adoption of new generation technologies, and rate trajectories will all be significantly influenced by the PREPA bankruptcy settlement.
  • Finally, an unreasonable bankruptcy settlement could spark a Rate-Revenue Death Spiral. Elevated electricity rates (driven by high fossil fuel costs and debt service requirements) increase the economic incentive for customers to reduce their consumption through energy efficiency or to exit the grid entirely through distributed renewable generation, particularly rooftop solar. This grid avoidance reduces the load volume that PREPA must serve, eroding its total revenue. To maintain sufficient revenue for debt service and operations, PREPA must increase rates further, which accelerates grid avoidance. The cycle reinforces itself, with rates rising faster than demand falls, eventually reaching a point where the most efficient investment for a customer is to exit the grid entirely.
  • The Rate-Revenue Death Spiral has policy implications that extend beyond financial sustainability. As rates increase, residential customers with capital (typically higher-income households) invest in distributed solar and battery storage, while renters and lower-income homeowners who cannot make the upfront investment bear the burden of rate increases. This creates a regressive distributional outcome: lower-income customers subsidize the energy independence of higher-income customers. Moreover, customers who exit the grid through distributed generation retain backup service from the utility, effectively requiring the remaining customers to finance infrastructure that serves the departed customer’s occasional needs.

State of Play

Last time we checked with our protagonists, the bondholder groups were celebrating a November 2024 ruling from the First Circuit Court of Appeals in Boston which held, among other things, that bondholders held an $8.5 billion claim (plus accrued interest and fees) secured by a properly perfected lien on PREPA’s past, present, and future net revenues, as opposed to being secured only by funds deposited in certain PREPA accounts. According to some analysts, this ruling has fundamentally altered the negotiating dynamic. Yet, as of this writing and to the best of our knowledge, it has not been fully incorporated into a revised Plan of Adjustment.

We note, however, that the phrase “among other things” is carrying a lot of weight in that sentence, because the First Circuit also held that (1) even though bondholders could make a claim in the amount of $8.5 billion, that does not mean they would actually recover that amount in full; their recovery is, instead, contingent on PREPA’s future net revenues, if any; and (2) bondholders had no recourse, other than PREPA’s net revenues, as their source of repayment. This latter holding is extremely important because it means bondholders cannot seek recovery from any other PREPA assets or from any other Puerto Rico government sources, such as the general fund. The FOMB, thus, also had reason to celebrate the ruling.

In early August, President Trump removed six of seven sitting Oversight Board members. Judge Swain then suspended all case deadlines on August 8, 2025, and ordered the Board to report on its operational status. The suspension effectively froze proceedings for several months. Eventually, three of the removed board members were reinstated by a federal court. The Trump administration has announced its intention to appeal this decision, but is waiting for the court system to rule on a similar dispute before taking further action regarding the FOMB (at least for now).

Boundaries of a Potential Settlement with Bondholders

So, given this state of play, what are the boundaries of a potential settlement with bondholders?

PREPA currently charges approximately 27.5 cents per kWh (including active Puerto Rico Energy Bureau -approved temporary surcharges as of late 2025 of 1.92 cents for pension payments and 1.49 cents for operating expenditures), already among the highest utility rates in the United States and significantly above the 20 cents per kWh affordability threshold recognized by both the Puerto Rico Legislature and the FOMB. Puerto Rico’s median household income is approximately $25,000 (2023 ACS) — roughly one-third the U.S. mainland median — and approximately 40% of residents live below the federal poverty line. The island’s economic activity index has contracted or stagnated since 2024, reflecting a difficult environment that severely limits the economy’s capacity to absorb rate increases.

PREPA generates approximately 19–20 billion kWh of electricity annually (EIA/CRS 2023). Given declining population and ongoing customer defection to rooftop solar, this volume is expected to decrease over a 35-year bond amortization period. A $1 billion debt obligation, financed over 35 years at 4.5–5%, generates annual debt service requirements of approximately $57–61 million, which translates to a rate surcharge of roughly 0.29–0.32 cents per kWh based on current consumption levels. This surcharge does not include any other charges that would be necessary to finance an estimated $6 billion in additional capital spending required to modernize the grid and which is not covered by currently available federal funding.

Based on those assumptions, we believe there are two “bookend” scenarios that determine the universe of potential settlement agreements with bondholders.

The low-end scenario is bounded by the Oversight Board’s current proposed range (23 cents recovery under the 5th Amended Plan). The FOMB’s revised plan, which proposed $2.3 billion in new bonds (representing roughly a 23% recovery), was projected by the Institute for Energy Economics and Financial Analysis (IEEFA) to add approximately 1.6 cents per kWh to customer bills over 35 years, costing ratepayers a total of roughly $5.1 billion (Sanzillo, IEEFA, Sept. 7, 2023).  Under this scenario, PREPA would still be required to raise additional capital for grid investment, likely from a market that views any new indebtedness as deeply subordinated to the bonds issued to exit the Title III proceeding because bankruptcy exit bonds would presumably be secured with a first lien on PREPA’s net revenues.

This scenario is perhaps the most realistic and favorable for Puerto Rico ratepayers and the grid investment program, but creditors relying on the First Circuit lien ruling are unlikely to accept it absent further litigation losses.

At the other end of the spectrum, full repayment of the face value of PREPA’s bonded debt — plus post-petition interest, administrative claims, and fees, as the holdout coalition contends — would produce a total obligation of approximately $11–12 billion. This scenario is not considered economically feasible by most parties to the proceeding, including Judge Swain, who has publicly characterized some of the bondholders’ arguments as “likely delusional” (Slavin, Judge pushes PREPA, creditors to negotiate deal in 60 days. Bond Buyer. July 11, 2024).

A recovery in the order of $9–12 billion would require rate surcharges probably in the range from 6.3 to more than 9 cents per kWh, producing a new blended rate of 34–37+ cents per kWh. This plan would almost certainly be non-confirmable under PROMESA’s feasibility standard: at rates this high, customer defection to rooftop solar accelerates, the revenue base erodes faster than debt is serviced, and PREPA’s balance sheet becomes permanently insolvent, making it impossible for PREPA to perform under the plan without re-defaulting. Population flight and eventual system collapse would further hollow out the very revenue base on which any settlement’s long-term sustainability depends.

Conclusion

The PREPA Title III case is approaching a critical decision point. The November 2024 First Circuit ruling has given a second wind to bondholders, and the Oversight Board faces the challenge of crafting a confirmable plan that respects creditor rights while preserving Puerto Rico’s economic viability.

This is admittedly a difficult needle to thread. Pay too little and the economic impact is manageable, but the settlement is likely to be contested for years, and the capacity to issue new debt to fund grid capital investments in the future is, in the best case, constrained. Offer too much and the legal viability of the plan is compromised — and in the unlikely event such a plan is confirmed, its impact on the economy of Puerto Rico could be devastating while eliminating any possibility of future grid investment capacity.

In the end, the single most consequential variable is time. Every year that PREPA remains in bankruptcy is a year in which grid investment is deferred, federal incentives go unused, costly litigation drags on, the transition to renewables is delayed, work on the master IRP stalls, and the island’s population and economic base continue to erode — reducing the very revenue base that is expected to service PREPA’s restructured debt. A swift, pragmatic settlement may ultimately be less costly to Puerto Rico’s economy than the continued damage of delay.

Connecting the Dots of the Puerto Rico Electric Power System

Connecting the Dots of the Puerto Rico Electric Power System

Published on October 9, 2024 / Leer en español

Sergio portrait
Policy Director
DOWNLOAD
SHARE

Introduction

The performance of Puerto Rico’s electric power system has been deficient for many years now. For decades, the electric service provided by the Puerto Rico Electric Power Authority (“PREPA”) was inefficient, unreliable, and expensive, due to serial mismanagement, chronic corruption, rampant partisan politics, and the deferral of required maintenance and capital expenditures. The poor performance of the electric system intensified after PREPA’s bankruptcy and the widespread damage inflicted on the transmission and distribution network by Hurricane Maria, both in 2017.

During the last seven years the government of Puerto Rico has undertaken a massive effort to rebuild and modernize the system; privatize the operation and management of both the transmission and distribution grid and PREPA’s legacy generation assets; begin the twenty-five-year transition to generate 100% of the island’s electricity from renewable sources; and restructure PREPA’s financial obligations. Yet during the summer of 2024, most of these efforts to transform the electric power system appear to have been derailed, as the island was hit by rolling blackouts in the middle of one of the hottest summers in recent memory. Indeed, progress has slowed down almost to a standstill in some areas and, perhaps more worrisome, the government appears to be unable to discern a way to get out of the current quagmire.

Part of the problem is due to the sheer number of actors that have jurisdiction over at least one area of Puerto Rico’s energy system. As shown below, and in further detail in this webpage, we have identified at least 14 entities at the federal and state government levels and from the private sector that have some influence or control over at least a part of the transformation process. The coordination and synchronization of work efforts among and between these entities has proven difficult and continues to be a challenge, even seven years after PREPA’s bankruptcy and Hurricane Maria.

Another factor that has contributed to the slowdown of the system’s transformation is that such transformation consists in reality of several, complex, in many cases multi-billion dollar projects, each with many moving parts and which, in many cases, partially interlock and overlap with the others.

Short-Term Stabilization

First on this complicated agenda is the current effort to stabilize the system in the short term. As the U.S. Department of Energy (“DOE”), and others, have noted, Puerto Rico’s electric system is functional but fragile. On the generation side, Genera PR states that on any given day as much as 57% of the island’s generation capacity could be unavailable due to either forced outages (many due to time use limitations for lack of compliance with environmental rules and regulations) or for scheduled maintenance. In fact, in its PR100 Final Report, the DOE found that “additional generation capacity is needed immediately—on the scale of hundreds of megawatts—to achieve system adequacy and minimize outages.” (PR 100 Final Report, p. xxxvi). On the transmission and distribution side, it is well known that a lot of work remains to be done and that there are significant deficiencies in the lower-voltage (38kv) transmission network and with voltage control in some geographic areas, among other critical issues.

Stabilizing the system is the number one priority in the short term because, as things stand today, a cascading power system failure cannot be ruled out in the immediate future. Just to be clear, we are not saying that such a failure will occur but rather that it cannot be ruled out at this time. Therefore, all efforts should be directed at eliminating or least minimizing that catastrophic risk in the short term.

Permanent Work to Rebuild the System

At the same time that LUMA, Genera, and PREPA are working on stabilizing the system, projects to execute the permanent work to rebuild the damage caused by Hurricane Maria have been funded by FEMA (that is, FEMA has obligated funds for their execution) and according to COR3, at least 352 energy-related reconstruction projects are in some stage of execution. However, according to data provided by Mr. Manuel Laboy, Executive Director of COR3, at a public hearing of the U.S. House of Representatives Committee on Natural Resources, while a total of $16.299 billion has been allocated for permanent system reconstruction, FEMA had “obligated” only $4.834 billion, or 29%, and of that amount only about $1.272 billion, or 26%, had been disbursed (spent) as of mid-September 2024. In other words, seven years after Hurricane Maria, only 7.8% of the total funds allocated for the reconstruction of the electric system have been spent.

Source: Mr. Manuel Laboy Testimony before the U.S. House Committee on Natural Resources, September 26, 2024

The situation is even worse with respect to the $1.9 billion allocated by Congress to HUD’s CDBG-DR program for use in the reconstruction of the transmission and distribution system. According to recent press reports less than 1% of those funds have been spent.

To be fair, nobody expected this process to be finished in one or two years. However, according to most experts who have analyzed the execution of the reconstruction of the system, progress seems to have taken place at an unduly slow pace. We remind readers that this is due to several factors such as unduly burdensome bureaucratic requirements imposed on Puerto Rico by the Trump administration; FEMA’s decision to use an unproven process under section 428 of the Stafford Act to identify and approve funding for reconstruction projects; and the lack of coordination among and between federal and Puerto Rico government agencies, among other factors.

It is estimated that completing the permanent work to reconstruct the grid according to industry standards will take between 8 to 10 years and cost approximately $21 billion. We note that according to the DOE, only $15.4 billion of the $21 billion required have been identified as of March 2024 (PR100 Final Report, p. 408). That $15.4 billion amount includes spending for generation, transmission, and distribution system repairs and replacements, as well as on the Tranche 1 transmission network upgrades required to connect the first group of utility-scale renewable generation providers. The source of financing for the difference of approximately $6 billion is unknown as of the date of this document.

Transition to 100% Renewable Generation

The Puerto Rico Energy Public Policy Act of 2019 (“Act 17 of 2019”) requires that Puerto Rico meet 100% of its electricity needs with renewable energy by 2050. In order to reach that objective, Act 17 set the interim goals of 40% renewable generation by 2025; 60% renewable generation by 2040; the phaseout of coal-fired generation by 2028; and a 30% increase in energy efficiency by 2040.

By mid-2023, notwithstanding a significant increase in distributed solar PV generation (as opposed to utility-scale solar), only approximately 4% of the generation capacity available for the grid was from renewable sources. Furthermore, “achieving the 40% target by 2025 would represent an increase of at least 3 GW of additional renewable energy capacity if met with utility-scale solar” (PR100 Summary, p.1). According to the DOE, “deployment of renewables at a rate to achieve the 40% RPS goal would require a rapid rate of procurement of over 100 MW per month through 2025 from a level of minimal utility-scale build-out in recent years.” (PR 100 Final report, p. 229) This means that Puerto Rico is significantly behind schedule to meet the interim target of 40% renewable generation by 2025 and it is highly likely that Puerto Rico will miss this target.

Achieving this ambitious goal will require significant new investment to expand the transmission system; upgrade the distribution system; and replace all fossil fuel generation capacity with renewable generation during the next 25 years.

Transmission System Expansion to Integrate Renewable Generation

In terms of the transmission system, the interconnection of new renewable resources will require the construction of new tie lines to the bulk power system in Puerto Rico. The DOE assumed different entities would be responsible for funding those costs:

  1. As stated above, the Tranche 1 transmission network upgrade will be paid for with federal funds.
  2. For subsequent tranches “transmission costs were assumed to be financed by third-party renewable development sponsors and thus included in power purchase and operating agreements (PPOAs) until 2028.”
  3. Finally, commencing in 2028 PREPA “was assumed to be in a position to finance these investments due to its exit from bankruptcy and ability to access capital markets.” (PR100 Final Report, p. 408)

This means that private financing will have to be secured either via PPOAs or debt to be issued by PREPA. In both instances, these costs would be passed on to end customers through their bills. We also note that there is significant uncertainty regarding PREPA’s ability to issue new debt in the short to medium term. Right now PREPA does not have access to the capital markets as it is still undergoing a bankruptcy process. Given that situation, the DOE assumes PREPA will exit bankruptcy in 2024 and will have access to the capital markets by 2028 and, thus, the ability to finance upgrades to the transmission and distribution system going forward from 2028.

In our view, this assumption could be overly optimistic for several reasons. First, it is by no means clear that PREPA will exit bankruptcy in 2024. Even if a Plan of Adjustment of PREPA’s debt is certified by the Federal Court this year, several creditors have already indicated they will appeal such certification, potentially adding several years of litigation to this process.

Second, a restructured PREPA probably will be limited in its ability to issue new debt until the bonds issued as part of the current restructuring are paid in full. We don’t know yet what legal and financial conditions PREPA will have to satisfy (in the form of financial covenants limiting new debt issuance and/or legal or structural subordination requirements) in order to issue new debt after 2028. Finally, any announcement regarding the issuance of new debt by PREPA will probably face significant backlash from customers and other stakeholders who remember waste and mismanagement at the old PREPA.

Distribution System Upgrades

With respect to the upgrades to the distribution system, the DOE has stated that as new distributed energy resources (“DERs”) and electric vehicles (“EVs”) are deployed it will become necessary to upgrade parts of the distribution system. The DOE estimates there will be excess capacity and energy that cannot be integrated into the distribution system starting in 2037. For each scenario analyzed by the DOE, it assumed that these integration challenges would be mitigated by increasing the amount of bulk storage (batteries) on an incremental basis as renewable capacity expanded. This investment in incremental storage, which is expensive, was assumed to be procured via PPOAs. (PR100 Final Report, p. 409) This means that these costs will eventually be passed on to end customers through their bills.

Renewable Generation Capacity

Finally, with respect to new generation capacity, utility-scale generation as well as bulk storage resources are expected to be procured via PPOAs. (PR100 Final Report, p. 416) With respect to rooftop systems, the DOE “did not assume how those systems would be paid for or whether any public or federal funds would be allocated to pay for them.” (PR100 Final Report, p. 185)

Furthermore, we note that the DOE did not “examine any futures in which there is no central grid,” even under the scenario that assumes the maximum adoption of DERs. (PR100 Final Report, p. 184) This means that in the world analyzed by the PR100 Study, there will always be fixed and variable costs that will have to be paid or financed by all ratepayers in connection with the operation, maintenance, and future upgrading of a central grid.

This last point is important in the context of deciding how much to compensate net metering customers for the electricity they export to the system. While it may be true that the massive adoption of solar rooftop systems would probably generate significant positive non-cash externalities due to the reduction of fossil fuel emissions, the fact remains that LUMA would have to incur cash expenditures to maintain and operate the grid. Those costs should be allocated reasonably and fairly among all parties connected to the grid.

Rooftop Solar and Utility-Scale Solar Generation

The points regarding rooftop solar systems and the viability of a fully decentralized grid are important because some environmental groups in Puerto Rico have advocated for executing the transition to 100% renewable generation using only rooftop solar systems with no central grid, essentially creating an island-wide network of independently-owned and managed mini-grids. Adopting that model could increase the risks of inducing delays and increasing the cost of the transition to 100% renewable power for at least two reasons.

First, according to Bent Flyvbjerg, Oxford University professor and author of How Big Things Get Done (Macmillan Business, 2023), using proven, reliable off-the-shelf technology is one of the keys to executing big infrastructure projects on time and within budget. Newer unproven technology is not necessarily better. As far as we know, no jurisdiction with Puerto Rico’s population and industrial footprint has successfully accomplished a transition to 100% renewable power generation installing only rooftop solar systems on a decentralized grid (basically a grid made up of many mini-grids). Attempting to do so in Puerto Rico would increase the risk of execution failure significantly, as both delays and costs would probably increase over time and unexpected or unforeseen events occur along the way.

Second, according to Professor Flyvbjerg, modularity is another key to successfully executing large-scale infrastructure projects. Modularity, says Flyvbjerg, “is a clunky word for the elegant idea of big things made from small things. A block of Lego is a small thing, but by assembling more than nine thousand of them, you can build a scale model of the Colosseum in Rome. That’s modularity.” (How Big Things Get Done, p. 162) Modularity allows projects to get to scale fast, getting better, bigger, and cheaper as they do. It also enables experimentation. If something works, you keep it in the plan. If it doesn’t you “fail fast” and adjust the plan. You get smarter, designs improve. It also radically reduces execution risk. (How Big Things Get Done, p. 163 and 187)

The idea, then, is to start with “a small thing, a basic building block. Combine it with another and another until you have what you need. That’s how a single solar cell becomes a solar panel, which becomes a solar array, which becomes a megawatt solar farm.” (How Big Things Get Done, p. 157)

In this context, the idea of building out 700,000 rooftop solar systems to achieve the goal of 100% renewable generation is the opposite of modularity, as each rooftop system has to be custom-designed and built for each roof. Getting to scale will take longer, cost more, and eventually be subject to greater execution risk relative to using a modular approach.

To be clear, we are not advocating for the elimination of rooftop solar systems from the portfolio of technologies to achieve the 100% goal. Rather, we are arguing for finding the right balance between rooftop solar systems and large utility-scale solar generation as Puerto Rico transitions to 100% renewable generation. In this respect, we note that the rollout of large-scale solar projects is currently about two (close to three) years behind schedule. This delay in turn impacts the decommissioning of the PREPA legacy fossil fuel generation as large units cannot be taken offline until their replacement is ready.

Financial Restructuring

In July 2017, at the request of the Government of Puerto Rico, the Oversight Board filed a voluntary petition on behalf of PREPA for protection under Title III of PROMESA with the U.S. District Court. PREPA owes about $9 billion in outstanding bonds, has an unfunded pension liability of $3.8 billion, owes an additional $700 million to fuel line lenders, and several million more to many unsecured creditors.

According to the PREPA 2023 Fiscal Plan, “without restructuring its debt and other liabilities, PREPA would need to repay approximately $2.62 billion of scheduled legacy debt obligations over four years from FY2024 to FY2027 in addition to the roughly $4.83 billion of unpaid past and currently due amounts through the end of FY2023.” (PREPA 2023 Fiscal Plan, p. 140) Bringing PREPA’s unrestructured debt obligations to funded status in the near term would require rate increases of approximately 6 to 7 ¢/kWh in real dollars in the FY24- 27 period.

In the longer term, without any restructuring, PREPA’s estimated annual debt service obligation is approximately $1 billion per year based on amortization of all long-term financial liabilities at a 5.25% interest rate over 20 years.” (PREPA 2023 Fiscal Plan, p. 140) Under that scenario, the average residential customer who consumes 425 kWh per month would see its bill increase by approximately 26%.

In June 2023, the judge presiding over the proceedings determined that (1) bondholders had a lien only on certain PREPA revenues that had been deposited in debt service accounts and (2) there were significant risks associated with other remedies they may seek (for example, the appointment of a receiver). Therefore, she reduced the amount of their claim to $2.38 billion. About 25% of their original claim.

As expected a group of bondholders and other creditors appealed to the U.S. Court of Appeals for the First Circuit in Boston. The Court issued its opinion on June 12, 2024, and held that:

  1. Bondholders have a non-recourse claim on PREPA’s estate for the full principal [face] amount of the bonds, plus matured interest; and
  2. This claim is secured by PREPA’s Net Revenues — as that term is defined by the underlying bond agreement — and by liens on certain funds created by that bond agreement.

The Court did not decide what effect, if any, confirmation of a plan of reorganization will have on the bondholders’ security interest, nor did it attempt to estimate the economic value of that security interest.

Thus, the value of the bondholders’ claim is $8.5 billion plus matured interest. However, the Court went on to state that “this is NOT to say that the Bondholders must be paid $8.5 billion.” “Rather, it is to say that the Bondholders’ allowed claim on PREPA’s estate is in the order of $8.5 billion.” (FOMB v. Cortland Capital, p. 58)

The Court was quite clear that the Bondholders’ claim is secured only to the extent of the value of the Bondholders’ interest in the Net Revenues and the Sinking and Subordinate Funds. They own “Special Revenue Bonds.” This means that when a default occurs the Bondholders have NO claim (recourse) against the municipality’s [Puerto Rico’s] general fund or other non-pledged revenues or assets of the debtor (Section 927 Bankruptcy Code). Thus, if the value of Bondholders’ liens is less than the allowed claim amount, then the Bondholders are undersecured and they assume the risk that the revenues will not be enough to pay the bonds. (FOMB v. Cortland Capital p. 61)

Paying PREPA Bondholders with Money from the General Fund is a Bad Idea

This last point is why the proposal to pay off bondholders using funds from Puerto Rico’s general fund is a bad idea for at least two reasons. First, under that scenario, Bondholders would be paid using funds to which they have no right either under the bond offering documents or Section 927 of the U.S. Bankruptcy Code, which was incorporated by reference into PROMESA through Section 301(a) of that law. Second, such payment would set a dangerous precedent that could be used by other public utility creditors to demand repayment by claiming funds to which they do not have legal rights or recourse.

Operational Restructuring — LUMA

On June 22, 2020, PREPA and the Puerto Rico Public-Private Partnerships Authority (the “P3A” or “Administrator”) entered into an agreement for the Operation and Maintenance (“O&M” Agreement”) of PREPA’s Transmission and Distribution System (“T&D System”) with LUMA Energy, LLC, (“ManagementCo”) and LUMA Energy Servco, LLC (“ServCo”, and together with ManagementCo, the “Operator”).

Pursuant to the terms and conditions of the O&M Agreement, LUMA, among other things, is responsible for all electric transmission, distribution, load serving, and related activities for the safe and reliable operation and maintenance of the T&D system. These include system operator activities, engineering activities, maintenance of technical documentation, energy efficiency activities, planning, environmental and regulatory, legal services, and managing insurance and claims.

In exchange for providing those services, LUMA is entitled to receive certain compensation, depending on the execution phase of the O&M Agreement, as set forth in the chart below:

Source: FOMB, PREPA Certified Fiscal Plan for Fiscal Year 2021, p. 55

Effect of Supplemental Agreement

Right now, LUMA is operating in what is called the “Interim Period”, which will last, essentially, until the Title III case is finished. One of the conditions precedent to the effectiveness of the LUMA O&M Agreement is that PREPA’s debt restructuring be completed in a satisfactory manner. While the parties to the O&M Agreement could have agreed to waive that condition, the FOMB insisted on executing a Supplemental Agreement that provided for such waiver and other relatively technical amendments to the LUMA O&M Agreement.

The execution of the Supplemental Agreement and the creation of an “Interim Period” of operation apparently has caused some confusion among the public, leading some people to believe that the LUMA O&M Agreement is currently not in effect and LUMA is operating solely pursuant to the terms and conditions of the Supplemental Agreement. This is incorrect. Section 2.1 of the Supplemental Agreement states in the relevant part that:

“The O&M Agreement, except as supplemented and amended by this Supplemental Agreement, is in full force and effect and is in all respects hereby ratified and confirmed.”

You will rarely find a clearer sentence written by a corporate lawyer.

Furthermore, Section 3.1 clarifies that “Operator shall perform all services with respect to the T&D System constituting O&M Services under the O&M Agreement (the “Interim Period Services”), notwithstanding the fact that the Service Commencement Date has not yet occurred.”

Finally, another clause in that same Section 3.1 of the Supplemental Agreement, reiterates LUMA’s obligation to perform all the O&M services in accordance with the terms and conditions of the LUMA O&M Agreement: “Operator shall perform the Interim Period Services subject to the terms and conditions of the O&M Agreement, except as the same may be amended or supplemented by this Supplemental Agreement.”

Given the clarity of the language of the Supplemental Agreement, it is simply baffling to us why people keep repeating the falsehood that the LUMA O&M Agreement is not currently in full force and effect.

Second, we note that LUMA’s fixed annual fee is significantly higher under the Supplemental Agreement. For example, during FY21 it was $115 million (see chart above), while under the LUMA O&M Agreement, it would have been $70 million. The reason for this difference has never been made clear to us. In both cases, however, the annual fee is indexed to inflation using the CPI for the United States. Thus, the annual fee for FY25 should be approximately $135 million.

Failure to Define Key Metrics in the O&M Agreement

LUMA also could receive an Incentive Fee payment to the extent it achieves certain key performance metrics, as shown in the chart above. Unfortunately, these key performance metrics were not fully negotiated before the LUMA O&M Agreement was executed and entered into full force and effect. For some unknown reason, this crucial issue was left open and kicked down the road. Well, more than four years after the execution of the LUMA O&M Agreement, LUMA and the Puerto Rico Energy Bureau (“PREB”) have not yet reached an agreement on this important issue. CNE warned about the risks this scenario entailed when we published our initial analysis of the LUMA O&M Agreement back in August 2020.

What is clear is that the parties to the LUMA O&M Agreement entered into that Agreement based on certain premises shared by the parties and to achieve certain objectives that each of the parties wanted to realize. On the side of the Government of Puerto Rico, it is clear that it entered into the Agreement based on the premise that LUMA would be a more efficient operator of the T&D system (when compared to PREPA) and that such increased efficiency would generate significant savings for ratepayers in Puerto Rico. Specifically, the Government of Puerto Rico expected, at a minimum, that LUMA would:

  • Reduce the amount of energy lost during transmission and distribution;
  • Reduce the costs of operating the grid;
  • Reduce the frequency of service interruptions; and
  • Reduce the duration of service interruptions.

With respect to the first two objectives, the P3A estimated significant savings to be achieved by fiscal year 2024, as shown in the chart below:

Source: P3 Presentation, June 2020

According to the P3A, LUMA would generate $293 million in savings by FY27, compared to an annual fee of $141 million, resulting in a net benefit to Puerto Rico of approximately $150 million. As of this writing, more than three years after LUMA took over the management of the T&D system, we are not aware of any analysis confirming or verifying whether LUMA has in effect generated the forecasted savings.

Nor do we know of any statements by either the P3A or LUMA with regard to this issue, which in our view was the principal motivation to enter into the LUMA O&M Agreement, at least from the perspective of the Government of Puerto Rico. In the absence of the relevant information, we cannot reach any conclusions about this issue. But it is important to highlight that it is possible, if not outright probable, that LUMA may have failed to generate the forecasted savings, or any net savings [net of the annual Fixed Fee] for that matter, as of this writing.

With respect to the frequency and duration of outages, the most recent data published by the PREB indicates that both increased during FY23. In other words, the quality of the service, at least as measured by these two indicators, has gotten worse. In our view, this is the reason why there is so much frustration with LUMA at this moment. Just as in the case of the reconstruction after Hurricane Maria, we don’t think any objective observer would have concluded that LUMA would solve Puerto Rico’s transmission and distribution system problems in six months. But three years out (the first year was a transition period) people probably expected to see some progress, even if at a slow pace. Yet, the needle on these basic indicators appears to be moving in the other direction, that is, things are getting worse. Therefore, as of this writing, it appears that the objectives the Government of Puerto Rico wanted to achieve with the LUMA O&M Agreement are not being realized.

Events of Default Under the LUMA O&M Agreement

It is in this context then, when (1) we don’t know if LUMA has been able to operate the system more efficiently, reduce energy losses, and generate savings managing the T&D system; and (2) the quality of the service appears to be worsening, that some elected officials and other stakeholders have called for the cancellation or termination of the LUMA O&M Agreement.

Contracts usually can be terminated upon the occurrence of an event of default. In the case of the LUMA O&M Agreement, Section 14.1 describes each of the following as an Operator (LUMA) Event of Default:

  1. Involuntary Bankruptcy;
  2. Voluntary Bankruptcy;
  3. Failure to Provide or Maintain the Guarantee (if not cured within five days of notification by the Administrator);
  4. Failure to Perform a Material obligation (if not cured within 90 days of notification by the Administrator; but if the failure to perform is not curable then, under certain circumstances, it shall not constitute an event of default);
  5. Failure to Pay (if not cured within 60 days of notification by the Administrator);
  6. False or Inaccurate Representation or Warranty;
  7. Failure to Obtain or Maintain Insurance (if not cured within 10 business days of notification by the Administrator);
  8. Change of Control (not otherwise permitted by the O&M Agreement);
  9. Illegal Transfer (not otherwise in accordance with the O&M Agreement);
  10. Violation of Law (Operator is found or pleads guilty to certain crimes); or
  11. Failure to Meet a Minimum Performance Threshold for three or more consecutive years (unless failure to perform is excused by Force Majeure, an Outage Event, or Owner’s (PREPA’s) fault)

Termination of the O&M Agreement

Section 14.2, in turn, provides for the termination of the LUMA O&M Agreement in the case of a LUMA Event of Default. In general, this Section states that:

  1. Upon the occurrence of an Event of Default due to involuntary bankruptcy, a voluntary bankruptcy, or a violation of law, the O&M Agreement shall immediately terminate without further action by Administrator; and
  2. In the case of the occurrence of any other Event of Default by the Operator, the Administrator [the P3A] “may terminate this Agreement upon not less than one hundred twenty (120) days prior written notice to Operator, subject, to the extent required by Applicable Law, to the prior approval of PREB or the FOMB (if then in existence).”
  3. However, the termination of the O&M Agreement pursuant to Section 14.2 does not limit or impair LUMA’s “right to contest, pursuant to Article 15 (Dispute Resolution), whether an Operator Event of Default has occurred, or any of its other rights.”

In our view,  termination of the LUMA O&M Agreement upon a LUMA Event of Default, except in the case of a voluntary or involuntary bankruptcy or a violation of law by LUMA, would require the prior approval of the FOMB as long as (1) the FOMB is in existence and (2) PREPA continues to be a “Covered Territorial Instrumentality”, as such term is defined in PROMESA, which, in turn, is expressly included in the definition of “Applicable Law” in the LUMA O&M Agreement.

Additional Termination Rights

Section 14.5 provides additional termination rights to each of the P3A and LUMA in the following cases:

  1. The Sale of the T&D System (upon 120-day prior written notice);
  2. The Failure to Satisfy the Service Commencement Date Conditions;
  3. A Force Majeure Event extends for more than 18 consecutive months (upon 120-day prior written notice); or
  4. The Failure to Agree on a Budget during three or more consecutive years (upon 120-day prior written notice).

Finally, (1) PREPA has the right to terminate the O&M Agreement (upon 120-day prior written notice by PREPA) in the event that LUMA exceeds the approved Operating Budget during three or more consecutive years; and (2) LUMA has the right to terminate the O&M Agreement (upon 120-day prior written notice by the Operator) in the event of a change in Regulatory Law.

Termination Fee

The O&M Agreement also provides for the payment of a termination fee by PREPA to LUMA in the event of:

  1. The Commonwealth Puerto Rico enacts a law canceling or terminating the LUMA O&M Agreement;
  2. Termination of the O&M Agreement by either LUMA or the P3A due to the sale of the T&D System; or
  3. LUMA terminates the O&M Agreement due to certain changes in the applicable Regulatory Law.

In each of these cases, the termination fee to be paid would be equal to the sum of (a) the annual Fixed Fee and (b) the maximum Incentive Fee applicable for the Contract Year during which the O&M Agreement is terminated.

Section 14.6(c)(i) is clear, however, that PREPA shall have no obligation to pay the termination fee in any case other than in the three cases described in the prior paragraph. So it is not true that PREPA would have to pay a termination fee to LUMA in any and all cases if the O&M Agreement were to be terminated by the Government of Puerto Rico. Such fee would be payable only in the three limited circumstances described in the immediately preceding paragraph.

Some stakeholders have argued that no termination would be payable to LUMA, even in the cases covered by Section 14.6(c)(i) of the O&M Agreement, because such payment would be subject to PROMESA’s stay of creditor claims against PREPA.

In our view, this argument is incorrect for the following reason. Section 3.5 of the Supplemental Agreement states that:

“All amounts payable by Owner to Operator hereunder and under the O&M Agreement during the Interim Period shall be deemed to be administrative expenses of Owner.”

This is important because claims for administrative expenses, which are necessary to keep PREPA in operation, are not covered by the PROMESA stay. For example, EcoElectrica can charge and has a right to get paid for the electricity it may sell to PREPA on any given month.

Now let’s assume, for argument purposes, that early in 2025 the Puerto Rico Legislative Assembly passes a bill terminating the O&M Agreement and the new governor signs it into law. In that case, if the Title III case is still ongoing and the Interim Period is still in effect, then LUMA’s claim against PREPA for payment of the termination fee would not be covered by the PROMESA stay because (1) it would be an amount payable by the Owner pursuant to the O&M Agreement; (2) the claim would arise during the Interim Period; and (3) it would be deemed an administrative expense of the Owner pursuant to Section 3.5 of the Supplemental Agreement. Therefore, PREPA would have to pay the termination fee.

If on the other hand, PREPA has exited the Title III process by the time the hypothetical law terminating the O&M Agreement comes into effect, then the question regarding the applicability of the PROMESA stay would be moot, and PREPA would have to pay the termination fee as required by the plain text of Section 14.6(c)(i) of the LUMA O&M Agreement.

Dispute Resolution

Finally, it is important to remember that in the case the Government of Puerto Rico claims that LUMA has incurred in an Event of Default, LUMA has the right to contest, pursuant to a Dispute Resolution mechanism set forth in Article 15 of the O&M Agreement, whether an Event of Default has actually occurred. In general:

  • The Article 15 Dispute Resolution Process begins with a Notice of Dispute setting forth the subject of the Dispute Resolution Process. Once the Notice of Dispute is delivered, the Designated Persons of the parties have 30 days to negotiate in good faith a solution to the dispute.
  • If after 30 days of negotiations the dispute is still unresolved, then the parties have two options: (1) if it is a “Technical Dispute”, they must submit it to an independent expert who shall have 60 days to make his determination, which shall be binding upon the parties; or (2) if it is a dispute other than a Technical Dispute, then the dispute could be referred to Mediation by either the Administrator or the Operator.
  • If the parties choose Mediation, then the parties shall appoint a mediator, who shall have 90 days to mediate the dispute. If the dispute is not resolved within 90 days, then the Mediation process shall be terminated.
  • At this point either party may file a civil action seeking relief in the courts of the Commonwealth of Puerto Rico. It is not possible to forecast the duration of any civil litigation case, but it is safe to assume that any litigation regarding the termination of the LUMA O&M Agreement could last anywhere from several months to various years.
  • If the government of Puerto Rico obtains a decision in its favor, subject to any appeals, then it could proceed to terminate the O&M Agreement.

If the government of Puerto Rico successfully terminates the O&M Agreement due to an Operator Event of Default it is entitled, depending on the reason for the termination, to receive payment from LUMA of the Owner Termination Fee, which is equal to $20,000,000 in 2020 dollars, adjusted for inflation, if the termination occurs during the first five years of the term of the contract, or $10,000,000 in 2020 dollars, adjusted for inflation, if the termination occurs on any other year thereafter.

The termination of the LUMA O&M Agreement pursuant to Article 14 would also trigger the clock on the Back-End Transition period, which could last up to twelve months and during which LUMA would wind up its operations and transfer them to a successor operator. PREPA would also be responsible for paying a Back-End Transition Fee to cover the cost of LUMA’s operations during this period.

Operational Restructuring — Genera

On January 24, 2023, the Puerto Rico Power Electric Authority (“PREPA” or the “Owner”), the Puerto Rico Public-Private Partnerships Authority (the “P3 Authority” or the “Administrator”), and Genera PR LLC (the “Operator” or “Genera”), executed the Puerto Rico Thermal Generation Facilities Operation and Maintenance Agreement (the “Generation O&M Agreement”) setting forth the terms and conditions pursuant to which the Operator will operate, maintain, and eventually decommission certain Legacy Generation Assets owned by PREPA.

Genera is a wholly-owned subsidiary of New Fortress Energy (“NFE”). NFE, in turn, is “an integrated gas-to-power energy infrastructure company”, whose “business model spans the entire production and delivery chain from natural gas procurement and liquefaction to shipping, logistics, facilities and conversion or development of natural gas-fired power generation.”

Genera is being hired by PREPA, as owner of the Legacy Generation Assets, to provide (either directly or through subcontractors) four classes of services, namely: (i) the Mobilization Services, (ii) the O&M Services commencing on the Service Commencement Date, (iii) the Decommissioning Services, and (iv) the Demobilization Services. In exchange for providing those services, the Operator is entitled to receive certain compensation, subject to any applicable Incentive Payments or Penalties, during the term of the Generation O&M Agreement, which is initially expected to last ten (10) years.

The Generation O&M Agreement contains a fairly well-developed set of incentives, penalties, and performance metrics to evaluate the performance of the Operator. In this sense, the Generation O&M Agreement is an improvement over the LUMA O&M Agreement.

Indeed, the inclusion of measurable benchmarks, the requirement to engage in good faith negotiations with current PREPA employees, the cap on the fees that the Operator can earn during the Mobilization Period, and other requirements set forth in the Scope of O&M Services, for example, the obligation to develop a fully fleshed out communications plan prior to the handover of operations to the Operator, demonstrates that governments can and indeed do learn from prior experiences, notwithstanding what some critics may say or think to the contrary.

Expected Savings from the Generation O&M Agreement

That being said, though, the fact remains that executing and entering into the Generation O&M Agreement makes sense only if the expected savings to be generated exceed the expected costs of the agreement. The government of Puerto Rico has stated that it expects to generate “significant savings” from transferring the operation and management of the Legacy Generation Assets to Genera. However, the evidence it offers to back up that assertion is rather thin.

According to a report prepared by FTI Consulting (Exhibit B to the P3 Report), Genera estimates achievable O&M savings of $19 million per year, mostly from labor and more efficient maintenance activities. Genera also estimates fuel savings (without plant conversions or equipment replacement) of approximately $85 million per year, which would come from:

  • “Optimizing existing fuel contracts” ($56 million);
  • “Achieving better risk and credit terms on the existing oil contracts” ($20 million); and
  • “Making operational changes at the Legacy Generation Assets to increase fuel efficiency”
    ($9 million).

Genera also “believes” that, subject to PREB approval, “there are additional fuel savings”, in excess of $100 million, “achievable through fuel conversion of units”…These “conversions would involve commissioning of gas fuel operation for units that are dual fuel capable or conversions of units that are able to be converted.”

The “combined estimated savings from O&M and fuel range from $100 million to $200 million annually (including conversion savings if approved by PREB).” Those “savings would be shared 50%/50% between Genera and the electric ratepayers of Puerto Rico. That would result in $50 million to $100 million per year to Puerto Rico electric system customers.”

In sum, concludes FTI, “Puerto Rico is guaranteed a benefit and Genera’s incentive compensation pays for itself. Given the low fixed fee, high incentive fee component and the 50%/50% sharing of [the savings], Genera is more than motivated to perform and operate the plants well and as fuel-efficiently as possible.”

So, according to FTI’s analysis, this transaction is a clear win-win situation. We note, however, that there is significant uncertainty as to whether those savings would actually be realized given that they depend upon the execution of some rather vaguely defined “efficiencies” and the “optimization” of existing contracts. Furthermore, even if these savings are realized, are they, in fact, significant?

According to an unaudited financial report prepared by PREPA’s management for its governing board, it spent approximately $2.1 billion on fuel during fiscal year 2022, while total expenses for that year added up to $4 billion. Therefore, savings of $100 million are equivalent to 4.7% of fuel expense and 2.5% of total expenses for that period.

Those savings are worth something but they do not by any means represent a paradigm-shattering change.

Expected annual savings of $100 million probably will not be enough to even fully offset the debt service on PREPA’s restructured bonds, which we estimate as follows:

  • $5 billion in new bonds (@50% reduction)
  • 6% interest rate
  • $300 million annual debt service

Inherent Conflict of Interest

Furthermore, the Generation O&M Agreement is problematic for at least two reasons. First, the Agreement clearly allows the conversion of oil burning units to burn natural gas as a cost-saving initiative (subject to PREB approval), which would be contrary to the stated public policy goal of fully transitioning to renewable fuels by 2050 and creates an incentive for Genera to enter into related party transactions with its parent company for the purchase of natural gas. To be fair, the Agreement set forth a process to address conflicts of interest. It remains to be seen whether that mechanism will be implemented effectively.

Second, by allowing the switch to natural gas as a fuel cost-saving measure, the Generation O&M Agreement confronts Genera with a set of potentially incompatible incentives. On one hand, Genera gets to keep 50% of any fuel savings generated by its implementation of any Fuel Cost Savings Initiative. On the other hand, Genera keeps 50% of any savings it generates when the process of decommissioning a legacy asset ends up costing less than originally budgeted. This creates a disincentive for Genera to move quickly on the decommissioning of legacy assets, which at the end of the day will be the principal source of savings from this Agreement over the medium to long term.

However, we note that the Generation O&M Agreement has been in effect for only a little more than 18 months. So we don’t have enough data yet to pass judgment on Genera’s performance. Nonetheless, we need to keep an eye on how it addresses the conflict of interest inherent in the Generation O&M Agreement, under which a subsidiary of a fossil fuel company has been hired to decommission PREPA legacy assets and facilitate the build-out of large-scale renewable energy generation.

Conclusions and Net Assessment

Given all of the above, we reach the following conclusions:

  • First Priority: The stabilization of the electric system should be the number one priority in the short term.
  • Risk of a Cascading Power System Failure: given the current state of the system, the occurrence of a catastrophic event cannot be ruled out in the short term (2-3 years) unless drastic corrective measures are implemented soon.
  • LUMA O&M Agreement: it appears that the objectives the Government of Puerto Rico wanted to achieve with the LUMA O&M Agreement are not being realized.
  • It is Complicated: We are facing a cluster of complex multi-year, multi-billion dollar projects, each with many moving parts. Successful completion is probably beyond the current execution capability of the Puerto Rico government.
  • Who is in Charge?: Coordination and execution problems remain with no real solution in sight.
  • There are Many Tradeoffs: But it is unclear who makes the decisions and the criteria upon which they should be made to address these tradeoffs.
  • Cost: All of these processes are very expensive and we are still missing about $5 billion to finish the reconstruction of the grid and an additional $8 to $10 billion for the transition to 100% renewable generation.
  • Risk of Grid Defection/Death Spiral: Under several of the scenarios modeled by the DOE, the volume of electricity sales declines faster than the total cost required to serve customers. This cycle is called a “utility death spiral” and while a complete utility death spiral has yet to be experienced in the U.S. electricity sector, in the case of Puerto Rico this risk cannot be ruled out.
  • The DOE vaguely hinted as much when it stated that “PR100 analyzed a highly centralized utility in a future that was increasingly comprised of distributed and decentralized electricity resources which were neither owned nor controlled by the utility. Our analysis illustrates the implications of this seemingly dichotomous future: utility costs could not be reduced as quickly as retail sales resulting in higher retail rates.” (PR100 Final Report, p. 446)

The most likely scenario, in our view, is the following:

  • Slow progress on grid reconstruction limits progress on the transition to renewables.
  • Dependency on fossil fuels, mostly natural gas, increases just to keep the lights on.
  • The combination of those factors creates a chain of delays in the transition to 100% renewable generation, followed by failed and expensive efforts to catch up, followed by more delays and more spending on failed efforts to catch up. The transition to renewable generation languishes.
  • PREPA’s debt restructuring results in a rate increase of 3 to 4 cents per kWh to pay legacy debts.
  • Savings from LUMA and Genera O&M Agreements are not realized to the full extent of the original forecast, if at all.
  • Grid defection increases due to higher rates and an unreliable grid.
  • An increase in net metering customers further destabilizes the grid in certain areas of the island and leads to even higher rates.
  • By 2027/28 average rates exceed 35 cents/kWh.
  • Puerto Rico is far behind the milestones to reach the 100% goal by 2050.

CNE Review – May 2024

Published on May 22, 2024 / Leer en español

See all editions of the
CNE Review
SHARE

In This Issue

In late March the U.S. Department of Energy (“DOE”) released the final report of its study of Puerto Rico’s electric grid and its options for implementing a transition to 100% renewable generation by 2050. The final report entitled Puerto Rico Grid Resilience and Transitions to 100% Renewable Energy Study (“PR100 Study”) is (1) the product of a two-year effort carried out by several of the National Laboratories in conjunction with a broad group of Puerto Rican stakeholders; (2) a comprehensive diagnostic of Puerto Rico’s electric system; and (3) a wide-ranging analysis of the challenges to attain the goal of using only renewable energy sources for the generation of electricity in Puerto Rico.

We reviewed a summary of the main findings of the PR100 Study in a prior CNE Review. This time around we want to focus on a handful of issues that we believe merit further public discussion and analysis in Puerto Rico. Specifically, we will highlight (1) the complexity of achieving the 100% goal; (2) the need to make difficult tradeoffs and hard policy decisions to execute the transition; (3) the cost of the investments required to achieve this undertaking; (4) the economic impact of this process; and (5) some risks and uncertainties that remain to be addressed.

Click here to read our full analysis.

Insights + Analysis from CNE

By Sergio M. Marxuach, Policy Director

Five years ago, Puerto Rico enacted legislation setting the ambitious goal of generating 100% of its electricity from renewable sources by 2050 even as it rebuilt its electric grid, which was devastated by Hurricane María in 2017. This is a clear and compelling objective that is worth pursuing. Yet success is not guaranteed because it is also incredibly complicated. The policy questions require analyzing theoretical, technical, and economic constraints as well as making difficult tradeoffs among and between complex economic, technical, and social objectives. In addition, the technology is still evolving. In that sense, there is a tension between the technology that is already available now and the technology that is not yet viable or commercially available.

We also need to note that the transition to 100% renewable generation has a political economy dimension, as the old technology (and those who benefitted from it) is replaced by a still evolving new one (and those who stand to gain from it). Humanity’s natural resistance to change is thus reinforced by powerful economic and financial incentives.

Furthermore, during the last five years, Puerto Rico has fallen behind schedule to meet the interim objective of 40% renewable generation by 2025 due to bureaucratic and coordination failures. We are, therefore, at a critical juncture. We still have time to rebuild our electric grid and to completely switch away from fossil fuel generation by 2050. But achieving those objectives will require strategic thinking, skilled policymaking, competent execution, tactical dexterity, the ability to act collectively over the long term, and inspired leadership—resources that have been in short supply in Puerto Rico for at least a generation. Make no mistake, this endeavor will be challenging, hard, and expensive. There will be setbacks along the way. But it is the right thing for Puerto Rico to do for the generations yet to be born. So, we better get working if we are going to make it.

Before moving on with our analysis, we note that the PR100 Study’s final report is over 800 pages long. Unfortunately, a full analysis of such a comprehensive document is well beyond the scope of this monthly newsletter. We do encourage all interested parties to take a look at the document, which has been translated into Spanish, in case they want to obtain a more detailed analysis of any issue related to the transition to 100% renewable generation.

Section 1: It’s Complicated

Sometimes in the heat of public debate, it is easy to overlook the complexity of the process Puerto Rico is undertaking as it moves towards 100% renewable generation. This is a multi-year, multi-billion dollar process, with many moving parts. Meticulous resource, technical, and economic assessments need to be made, even as the technology itself is evolving. The Puerto Rico Electric Power Authority (“PREPA”), the legacy utility that still owns both the grid and a substantial fleet of fossil fuel generation, is currently undergoing a bankruptcy-like process to restructure its financial obligations. Several old-generation plants need to be decommissioned as renewable generation and large-scale battery storage systems have to be installed and interconnected to the grid. In addition, two new players, LUMA and Genera, are currently managing and operating the electric system, while the regulatory framework is relatively new and the main regulator, the Puerto Rico Energy Bureau, has only been in existence for ten years.

Click here to read more on the following issues:

  • Priority Number One: Stabilize the Grid
  • Too Many Cooks in the Kitchen
  • There is More than One Pathway to 100% Renewable Generation

Section 2: There Are Tradeoffs

As could be expected in a project as complicated as this one, there are multiple tradeoffs involved. Sometimes those tradeoffs are explicit, while others are implicit or ambiguous.

In Chapter 12 of the PR100 Final Report, the DOE compared and contrasted different scenarios to better understand the tradeoffs among and between them.

Click here to learn more about these tradeoffs and:

  • The Impact of Lower Retail Sales
  • The Impact of Different Levels of Distributed Solar PV

Section 3: It’s Expensive

The DOE did not perform an independent analysis of the costs required to bring the electric system “back into a state of good repair, but rather rel[ied] on the FOMB’s 2023 Certified Fiscal Plan for PREPA to identify both the level of investment and the sources of funds to cover that level investment.” (PR100 Final Report, p. 407) According to the DOE analysis, recovery-related investments total $15.441 billion, which includes spending on generation, transmission, and distribution system repairs and replacements, as well as on the Tranche 1 transmission network upgrades.

Notice that the $15.441 billion amount does not include the capital investment necessary to fund new generation as well as the upgrades and extensions of the transmission and distribution (“T&D”) system required to achieve the 100% goal by 2050 (with the exception of the Tranche 1 transmission system upgrade). One independent expert estimated additional T&D capital investments between 2030 and 2035 would add up to an additional $13.6 billion. (London Economics International, Critique of Government Parties’ Assertion that the 9019 Settlement Will Not Affect Non-settling Creditors and Would Avoid a Subsequent Title III Filing by PREPA, October 30, 2019, p. 97, Document #: 1890-1) Keep that in mind as we focus on the resources identified by the DOE to finance the recovery-related investments.

Click here to read more on this topic.

Section 4: Is it Good for the Economy?

The economic impact of the transition to 100% renewable generation, as modeled by the DOE, exhibits several tradeoffs that policymakers will need to take into account: (1) between construction and maintenance jobs; (2) among and between the costs and benefits of the different technologies; and (3) between short-term losses and long-term benefits in terms of employment and household income.

Click here to learn more.

Section 5: Risks and Uncertainties

Any process as complicated as the transition to 100% renewable generation will be full of risks and uncertainties. In this section, we highlight some of the most significant in our opinion.

Click here to read more on:

  • The Challenge of Stabilizing the System
  • Coordination Problems
  • Cost/Resiliency/Reliability Tradeoffs
  • Compensation for Net Energy Metering
  • Policy and Regulatory Constraints Regarding the Contribution of Distributed PV to Achieve the Renewable Portfolio Standards (“RPS”) Goals
  • Reaching 40% RPS by 2025 Appears Unfeasible
  • Obtaining Funding for the Grid Upgrade Remains Challenging
  • PREPA’s Access to Capital Markets
  • Uncertainty Regarding Energy Efficiency Measures and Electric Vehicles
  • Risk of Grid Defection/Death Spiral

On Our Radar…

Click the image above to learn more about our upcoming event in Madrid, Spain.

Let’s Get Going: Next Steps in Puerto Rico’s Energy Transformation

Let's Get Going: Next Steps in Puerto Rico’s Energy Transformation

Published on May 21, 2024 / Leer en español

Sergio portrait
Policy Director
DOWNLOAD
SHARE

Introduction

In late March the U.S. Department of Energy (“DOE”) released the final report of its study of Puerto Rico’s electric grid and its options for implementing a transition to 100% renewable generation by 2050. The final report entitled Puerto Rico Grid Resilience and Transitions to 100% Renewable Energy Study (“PR100 Study”) is (1) the product of a two-year effort carried out by several of the National Laboratories in conjunction with a broad group of Puerto Rican stakeholders; (2) a comprehensive diagnostic of Puerto Rico’s electric system; and (3) a wide-ranging analysis of the challenges to attain the goal of using only renewable energy sources for the generation of electricity in Puerto Rico.

We reviewed a summary of the main findings of the PR100 Study in a prior CNE Review. This time around we want to focus on a handful of issues that we believe merit further public discussion and analysis in Puerto Rico. Specifically, we will highlight (1) the complexity of achieving the 100% goal; (2) the need to make difficult tradeoffs and hard policy decisions to execute the transition; (3) the cost of the investments required to achieve this undertaking; (4) the economic impact of this process; and (5) some risks and uncertainties that remain to be addressed.

Before moving on with our analysis, we note that the final report is over 800 pages long. Unfortunately, a full analysis of such a comprehensive document is well beyond the scope of this policy brief. We do encourage all interested parties to take a look at the document, which has been translated into Spanish, in case they want to obtain a more detailed analysis of any issue related to the transition to 100% renewable generation.

Section 1: It’s Complicated

Sometimes in the heat of public debate, it is easy to overlook the complexity of the process Puerto Rico is undertaking as it moves towards 100% renewable generation. This is a multi-year, multi-billion dollar process, with many moving parts. Meticulous resource, technical, and economic assessments need to be made, even as the technology itself is evolving. The Puerto Rico Electric Power Authority (“PREPA”), the legacy utility that still owns both the grid and a substantial fleet of fossil fuel generation, is currently undergoing a bankruptcy-like process to restructure its financial obligations. Several old-generation plants need to be decommissioned as renewable generation and large-scale battery storage systems have to be installed and interconnected to the grid. In addition, two new players, LUMA and Genera, are currently managing and operating the electric system, while the regulatory framework is relatively new and the main regulator, the Puerto Rico Energy Bureau (“PREB”), has only been in existence for ten years.

Priority Number One: Stabilize the Grid

Furthermore, Puerto Rico is starting the transition to 100% renewable generation with an electric system that is fragile and functioning well below recommended industry standards. The first priority, therefore, should be to stabilize the system and bring it up to 21st-century standards. On the generation side, the DOE found that “the current Puerto Rico grid is not reliable and needs immediate additional capacity to meet an acceptable level of performance.” (PR 100 Final Report, p. 240) With respect to the transmission system, the DOE found that “the lower-voltage (38-kV) transmission network components are insufficient to handle the projected system transitions” and 38-kV network upgrades are necessary to support the projected buildout of renewable generation. (PR 100 Final Report, p. 241) Finally, with respect to the distribution system, the DOE highlights that some “feeders as they exist in Puerto Rico today operate outside” standard voltages and several mitigating actions would have to be implemented to avoid “backfeeding” and voltage violations as significant photovoltaic (“PV”) generation is connected to the system. (PR100 Final Report, p. 347). This means that both LUMA, the grid operator, and Genera, which manages PREPA’s legacy generation fleet, need to undertake substantial remedial actions even as the system is transitioning to renewable sources of energy. It is our understanding that both LUMA and Genera are undertaking remedial measures to stabilize the electric system in the short term.

Too Many Cooks in the Kitchen

A multiplicity of government agencies and entities, at both the federal and state levels, with sometimes overlapping and partially interlocking jurisdictions add a second layer of complexity to this process. Among those agencies and entities, we find the following:

  1. The U.S. Department of Energy (“DOE”) – Carried out the PR100 Study and was also allocated $1 billion by Congress to finance distributed energy projects at the community level in Puerto Rico.
  2. The Federal Emergency Management Agency (“FEMA”) – Administers and oversees the use of $13.7 billion allocated to rebuild the electric grid.
  3. The U.S. Department of Housing and Urban Development (“HUD”) – Is in charge of administering approximately $1.9 billion in CDBG funds to upgrade Puerto Rico’s energy system.
  4. Central Office for Recovery, Reconstruction, and Resiliency (“COR3”) – The main liaison between the government of Puerto Rico and FEMA. The COR3 is technically the grantee for most federal reconstruction funding.
  5. Puerto Rico Department of Housing (“DOH”) – Administers and oversees the use of CDBG funds in Puerto Rico.
  6. Puerto Rico Energy Bureau (“PREB”) – The independent regulator of Puerto Rico’s electric system. It has a statutory mandate to regulate the generation and sale of electricity in the island; to set rates; and to plan for the efficient long-term operation of the electric system, among other important matters.
  7. Puerto Rico Electric Power Authority (“PREPA”) – Puerto Rico’s legacy utility, currently in bankruptcy and the nominal owner of the assets of Puerto Rico’s electric system.
  8. LUMA – Private manager and operator of Puerto Rico’s electric grid. In charge of authorizing interconnections to the grid and dispatching electricity.
  9. Genera – Private manager and operator of PREPA’s legacy generation assets. In charge of decommissioning existing fossil-fuel generation and coordinating the ramp-up of new renewable generation resources.
  10. AES and EcoEléctrica – Independent power producers with an aggregate generation capacity of approximately 900 MW using coal and natural gas, respectively. The AES plant is statutorily required to be shut down in 2028.
  11. Public Private Partnership Administration (“P3A”) – Executes limited oversight functions pursuant to the operation and management agreements executed with each LUMA and Genera, respectively.
  12. Financial Oversight and Management Board (“FOMB”) – Represents PREPA in its bankruptcy process. Has oversight powers over PREPA pursuant to PROMESA. Certifies PREPA’s annual Fiscal Plan and its operating budget. Exercises authority under PROMESA to review certain contracts covered by that law. In the case of PREPA, it has been in charge of reviewing the terms and conditions of the power purchase agreements between developers of utility-scale renewable generation and PREPA.
  13. The United States District Court for the District of Puerto Rico (“Federal Court”) – Has jurisdiction over PREPA’s bankruptcy under Title III of PROMESA. It will eventually determine how much PREPA’s creditors can recover from the bankrupt utility and certify a Plan of Adjustment (“POA”). The POA will affect electricity rates in so far as it provides for the imposition of a special charge to repay bondholders and PREPA is otherwise unable to generate offsetting cost savings.

In addition, there are dozens of consultants, suppliers, rooftop solar systems vendors, developers of utility-scale renewable generation sites, trade organizations, NGOs, community-based organizations, and other stakeholders with a direct interest in the transition to 100% renewable generation.

The problem we see is that there appears to be little or no coordination among and between all these actors. In our view, the PREB, as Puerto Rico’s energy regulator, should be the principal player coordinating the upgrade of the grid, the decommissioning of PREPA’s legacy assets, the ramp-up of renewable generation both on rooftops and at the utility scale, and in general making the key decisions, in consultation with the relevant stakeholders, regarding the long-term transition to 100% renewable generation by 2050.

There is More than One Pathway to 100% Renewable Generation

A third layer of complexity arises from the multiple pathways and combinations of generation technology that are least potentially available to reach the 100% goal. To briefly recapitulate, the DOE analyzed three scenarios, all based on the utilization of “mature” renewable technologies (with the exception of biodiesel to provide firm dispatchable generation towards the end of the transition period) and which vary according to (1) the amount of distributed energy resources; (2) the amount of land available for utility-scale generation (Less Land or More Land); and (3) two load forecasts (a Mid Case and a Stress Case). In addition, the DOE also took into account the level of technological development (Conservative, Moderate, or Advanced) throughout the transition period, a variable that is exogenous to Puerto Rico.

The three scenarios are:

(1) the Economic Adoption of distributed energy resources (“DERs”), which assumes the adoption of DERs is based on financial savings to home and business owners and their deployment is extended to critical infrastructure such as fire stations and hospitals;

(2) the Equitable Adoption of DERs, which assumes the deployment of DERs beyond that of Scenario 1 to include remote areas and very low-income households (defined as households earning 0%–30% of area median income); and

(3) the Maximum Adoption of DERs, which assumes deployment of DERs on all suitable rooftops.

As stated above, each scenario has four variations: Less Land or More Land (regarding land use) and Mid Case or Stress Case (regarding load), for a total of twelve scenarios. Scenarios are labeled by number, land variation, and load variation. Thus, Scenario 1LS means: Scenario 1, Economic Adoption, Less Land, Stress load.

We note that the DOE did not “examine any futures in which there is no central grid,” even under Scenario 3, which assumes the maximum adoption of DERs. (PR100 Final Report, p. 184) This means that in the world analyzed by the PR100 Study, there will always be fixed and variable costs that will have to be paid or financed in connection with the operation, maintenance, and future upgrading of a central grid.

In addition, in Scenarios 2 and 3, the DOE:

…forced in the adoption of significantly higher amounts of rooftop PV to examine the impacts of these levels of adoption. In this analysis, we did not assume how those systems would be paid for or whether any public or federal funds would be allocated to pay for them. By definition, Scenarios 2 and 3 exceed what is likely to be adopted based on bill savings and resilience savings. (PR100 Final Report, p. 185)

This means difficult tradeoffs will have to be made among and between cost, resilience, land use, and economic impact.

Section 2: There Are Tradeoffs

As could be expected in a project as complicated as this one, there are multiple tradeoffs involved. Sometimes those tradeoffs are explicit, while others are implicit or ambiguous. For example, the DOE states that “accelerating the deployment of rooftop PV and storage will therefore accelerate increased resilience. This greater building-level resilience might reduce both the urgency to restore the grid after an outage and the resilience needs for the grid system.” (PR100 Final Report, p. 186)

Now, this statement could be interpreted in one of two ways. An optimistic or positive interpretation would be that increased rooftop solar and storage systems would increase resilience so much so as to render the restoration of the grid to a second order of priority during the recovery period immediately after a natural disaster. That would open up or make funding available to attend to other priorities during the immediate recovery period.

A more pessimistic or negative interpretation would focus on the potential perverse incentives created by additional resilience. Since a large number of people and critical infrastructures would not depend on the grid, government agencies may have less urgency in restoring grid-based service to those who have no choice but to be connected to the grid. Hence, the implicit tradeoff: more resiliency for those with access to DERs may imply longer recovery times for those still connected to the grid because restoring the grid would not be as urgent or important.

In Chapter 12 of the PR100 Final Report, the DOE compared and contrasted different scenarios to better understand the tradeoffs among and between them.

The Impact of Lower Retail Sales

First, the DOE sought to “better understand the impact of differences in demand for electricity.” Combining changes in loads with the impact of DERs on utility costs, allowed the DOE to “better understand the economic implications associated with changes in retail sales.” (PR100 Final Report, p. 435) They did this by comparing the impacts of what they call “the two bookend scenarios”, namely scenario 1MS (Economic Adoption, More Land, Stress Load), which results in the highest level of retail sales by the utility, and scenario 3MM (Maximum Adoption of DERs, More Land, Mid-Case Load), which results in the lowest level of utility retail sales. The results are quite interesting.

First, as shown in the figure below, utility “retail sales [in kWhs] in 2050 drop from 2020 levels by 55% for the lowest forecast (3MM) relative to falling 10% for the highest usage forecast (1MS).” (PR100 Final Report, p. 435) This means that under the Maximum Adoption Scenario, which maximizes rooftop solar systems, electricity sales by PREPA/LUMA/Genera decline significantly, as would be expected. Total system resiliency under this scenario is also expected to be greater.


Source: PR100 Final Report, p. 436

Second, the large reduction in retail sales by the utility between these two scenarios reduces the amount of revenue collected each year by the utility, again as would be expected. However, the sharp decline in retail sales has an adverse impact on the repayment schedule of PREPA’s legacy debt as renegotiated under the POA. According to the DOE analysis, revenues under the 3MM Scenario would decline by so much, that “the repayment date [of the restructured debt] was extended by 4 years for the 3MM scenario.” (PR100 Final report, p. 436) The figure below shows this impact:

Source: PR100 Final Report, p. 436

So, here is one clear tradeoff: more resiliency under Scenario 3MM results in (1) significantly less revenues for the utility and (2) an extension of the repayment term of the legacy debt.

Third, on the positive side, lower retail sales (in kWhs) also mean lower generation costs for the utility, which should translate into lower rates. However, the reduction in costs modeled by the DOE was not equivalent to the 55% reduction in sales in 2050 between the two scenarios under analysis for two reasons.

  • First, “as renewable energy penetration increased, the utility-owned fossil resources produced less energy overall but incurred additional cycling costs to manage the variability of the utility-scale renewable resources and, in conjunction with storage resources, was required to operate in ways that provided grid services that the utility-scale renewable energy resources could not.” (PR100 Final Report, p. 437)
  • Second, “the achievement of 100% [renewable portfolio standards] RPS in 2050 forced investment in a portfolio of new resources to provide the comparable grid services required to integrate distributed PV generation.” (PR100 Final Report, p. 437)

Notice another tradeoff here: maximum deployment of DERs significantly reduces the generation costs for the utility but those savings are partially offset by the need to incur additional investments to maintain system stability and reliability over the long term.

The net impact is that while utility electricity sales decline by approximately 55%, the utility revenue requirement (what the utility must charge to cover its costs) decreases by only 24% in the lower retail sales scenario (3MM) relative to the utility revenue requirement under the scenario with the highest sales (1MS). (PR100 Final Report, p. 437) Thus, lower sales under Scenario 3MM do result in an overall reduction in generation production costs but such a reduction is significantly lower than the decrease in total utility retail sales.

Fourth, this is where things get complicated. According to the DOE:

Because utility retail sales in the 3MM scenario declined so much more than utility costs, those costs had to be spread over a much smaller sales base to keep the utility financially healthy. This resulted in an increase in retail rates between 2025, when the electric system achieved a more reliable state of operation, and 2050: moving from 37¢/kWh to 56¢/kWh for the lowest retail sales level…In contrast, the retail rate level modestly drops between 2025 and 2045 for the highest retail sales level (34¢/kWh to 32¢/kWh) and then increases as the utility achieves 100% renewable energy penetration in 2050 (37¢/kWh). (PR100 Final Report, p. 438)

Thus, as shown in the figure below, the all-in average retail is significantly higher under scenario 3MM when compared to Scenario 1MS.


Source: PR100 Final Report, p. 438

As DERs are increasingly deployed under Scenario 3MM, utility costs decrease but, as stated above, by an amount lower than the decrease in total utility sales. As fewer customers remain totally dependent on the grid, total costs have to be apportioned over a smaller customer base, which results in higher rates relative to Scenario 1MS for all those dependent on the grid.

The Impact of Different Levels of Distributed Solar PV

The decision of how many resources should be dedicated to deploying either rooftop solar systems or utility-scale PV generation is one of the most intensely debated issues in Puerto Rico right now. Advocates for rooftop solar rightly emphasize the resiliency advantages of those systems, while advocates of more investment in utility-scale generation, relative to rooftop solar, emphasize the economies of scale and lower costs associated with larger solar generation facilities. To us, it is obvious that Puerto Rico needs both kinds of systems. So, in a certain sense, this is a false choice. But here we are.

Section 12.1.3.7 of the PR100 Final Report details the result of the DOE’s analysis of three scenarios that maintain constant both land use constraints and the load forecast while allowing for different levels of distributed/utility-scale solar PV generation. Those scenarios are 1LS (Economic Adoption, Less Land, Stress Load); 2LS (Equitable Adoption, Less Land, Stress Load); and 3LS (Maximum Adoption, Less Land, Stress Load). This analysis allows the DOE to assess the economic trade-offs associated with each of these scenarios in terms of the deployment of rooftop systems versus utility-scale generation.

The first thing they notice is that “increasing levels of distributed PV adoption under NEM [Net Energy Metering] resulted in increasing distributed PV production (MWh) that could not be integrated on the distribution system without additional infrastructure investments.” (PR100 Final Study, p. 441) As shown in the figure below, this means that as soon as 2037 “distribution system upgrades in the form of storage procured under [power purchase and operating agreements] PPOAs in addition to the requirements [to meet RPS goals] began to be needed to mitigate the integration challenges by the highest distributed PV adoption scenario under NEM.” (PR100 Final Study, p. 442)


Source: PR100 Final Report, p. 442

In terms of the impact on utility-owned generation costs, the DOE found that electricity from rooftop solar systems reduced the amount of utility-scale generation resources required to meet annual energy demand “but the increased level of variability introduced into the net load profile caused offsetting integration costs.” (PR100 Final Report, p. 442)


Source: PR100 Final Report, p. 443

As shown in the figure above, utility-owned generation costs decline modestly in Scenario 3LS relative to Scenario 1LS starting in 2025. However, the decline is “not as large, in percentage terms, as the reduction in retail sales between the two scenarios.” (PR100 Final Report, p. 442) Furthermore, (1) purchased power costs were “nearly identical” across all three scenarios and (2) starting in 2040, “both utility-owned generation and purchased power cost reductions were much smaller, in percentage terms, than the change in retail sales reductions from distributed PV between the highest and lowest level of distributed PV adoption.” (PR100 Final Report, p. 443)


Source: PR100 Final Report, p. 443

Finally, “at the levels of distributed PV penetration seen in the 3LS scenario, the utility incurred substantially more distributed PV integration costs under NEM that offset nearly all the savings from the lower electricity demand.” (PR100 Final Report, p. 443)

Just like in the previous analysis, the lower generation costs were offset by higher distribution system storage/battery costs required for the highest level of distributed PV under NEM. “As a result the total revenue requirement under the highest penetration level of distributed PV was only 1% lower than it is for the lowest penetration of distributed PV in 2050.” This means that the utility revenue requirement is essentially the same under the three scenarios, as shown in the figure below:


Source: PR100 Final Report, p. 444

 

Finally, “with nearly identical total revenue requirements, the 21% reduction in retail sales (1LS scenario versus 3LS scenario) in 2050 caused rates to be higher by 26” by 2050. See figure below.


Source: PR100 Final Report, p. 444

The tradeoffs, then, are very similar to those in the prior analysis of the “bookend scenarios.” In general, under Scenario 3 relative to Scenario 1 (with both land use constraints and loads held constant): (1) the system is more resilient as there is greater deployment of DERs; (2) retail sales (in kWh) decrease significantly; (3) costs also decrease but by less than the reduction in sales because there is a need to invest more in storage systems; (4) purchased power and operating costs are essentially the same under both scenarios; (5) the total utility revenue requirement remains basically unchanged; (6) lower retail sales under Scenario 3 with essentially the same costs as Scenario 1 translate into higher retail rates for consumers without access to a distributed solar PV system.

To be clear, CNE is not advocating for Scenario 1 over Scenario 3 or any other specific scenario for that matter. Our point is that there are tradeoffs that need to be taken into account by those responsible for managing and planning the electric system. Furthermore, those tradeoffs should be disclosed and clearly explained to the people of Puerto Rico. There are many benefits to having a more resilient system. There are also many costs that need to be incurred to achieve a higher level of resiliency. And those costs would disproportionally fall on those unable (for whatever reason) to install a rooftop solar system. If these facts are disclosed clearly and fairly by decision-makers and the decision is still made to implement Scenario 3, or something close to it, then so be it. But let’s be sure we can pay for it.

Section 3: It’s Expensive

The DOE did not perform an independent analysis of the costs required to bring the electric system “back into a state of good repair, but rather rel[ied] on the FOMB’s 2023 Certified Fiscal Plan for PREPA to identify both the level of investment and the sources of funds to cover that level investment.” (PR100 Final Report, p. 407) According to the DOE analysis, recovery-related investments total $15.441 billion, which includes spending on generation, transmission, and distribution system repairs and replacements, as well as on the Tranche 1 transmission network upgrades.

Notice that the $15.441 billion amount does not include the capital investment necessary to fund new generation as well as the upgrades and extensions of the transmission and distribution (“T&D”) system required to achieve the 100% goal by 2050 (with the exception of the Tranche 1 transmission system upgrade). One independent expert estimated additional T&D capital investments between 2030 and 2035 would add up to an additional $13.6 billion. (London Economics International, Critique of Government Parties’ Assertion that the 9019 Settlement Will Not Affect Non-settling Creditors and Would Avoid a Subsequent Title III Filing by PREPA, October 30, 2019, p. 97, Document #: 1890-1) Keep that in mind as we focus on the resources identified by the DOE to finance the recovery-related investments.

According to the DOE, the following sources of funds are available to cover the $15.441 billion spending on recovery-related investments:

  • $13.723 billion from FEMA
  • $0.500 billion from HUD
  • $0.285 billion dedicated by the Government of Puerto Rico from 2023 to 2025
  • $0.193 billion in insurance proceeds
  • $0.740 billion collected from ratepayers through 2034, financed via headroom in rates from 2020 to 2028, “at which point PREPA is assumed able to access capital markets after its exit from bankruptcy in 2024.” (PR100 Final report, p. 408)


Source: PR100 Final Report, p. 408

As stated above, there is also a need to make additional investments, beyond the recovery-related capital expenditures set forth above, in order to meet the Act 17 RPS requirements:

  • Transmission System Expansion: The interconnection of new renewable resources will require the construction of new tie lines to the bulk power system in Puerto Rico. The DOE assumed different entities would be responsible for covering those costs. First, as stated above, the Tranche 1 transmission network upgrade will be paid for with federal funds. Second, for subsequent tranches “transmission costs were assumed to be financed by third-party renewable development sponsors and thus included in power purchase and operating agreements (PPOAs) until 2028.” Third, commencing in 2028 PREPA “was assumed to be in a position to finance these investments due to its exit from bankruptcy and ability to access capital markets.” (PR100 Final Report, p. 408)
  • Distribution System Upgrades: As new DERs and EVs are deployed it will become necessary to upgrade parts of the distribution system. The DOE estimates there will be excess capacity and energy that cannot be integrated into the distribution system starting in 2037. For each scenario, the DOE assumed that these integration challenges would be mitigated by increasing the amount of bulk storage (batteries) on an incremental basis as renewable capacity expanded. This incremental storage was assumed to be procured via PPOAs. (PR100 Final Report, p. 409)
  • New Generation: Utility-scale generation as well as bulk storage resources are expected to be procured via PPOAs. (PR100 Final Report, p. 416) With respect to rooftop systems, the DOE, as stated above, “did not assume how those systems would be paid for or whether any public or federal funds would be allocated to pay for them.” (PR100 Final Report, p. 185)

In addition to the costs outlined above, operating the electric system requires paying for other costs such as fuel costs, legacy debt charges, Paygo pension payments, LUMA contract fees and fixed operation and maintenance (“O&M”) costs, Genera contract fees and legacy generation fixed O&M costs, PREPA Holdco fees, CILT and subsidies, and energy efficiency programs, among others.

PREPA, just like most utilities, recovers some costs via basic tariff charges, which are set during general rate cases, and other costs via rate riders that are updated on a more frequent basis. According to the DOE, “basic tariff charges differ by customer class while rate riders can be, and often are, universally applied to all customer classes.” (PR100 Final Report, p. 422)

The DOE assumed the following division between basic tariff charges and rate riders to estimate the utility revenue requirements going forward:


Source: PR100 Final Report, p. 423

We assume that the final allocation will be determined by the PREB but we notice that significant changes to PREPA’s current billing practices may be necessary to reconcile tradeoffs between solvency and equity objectives going forward.

Let’s take one issue that has been in the news recently to analyze some of the equity concerns that may arise going forward. Customers who currently participate in the Net Energy Metering program are compensated for their net energy exports to the grid at the same amount (per kWh) they are charged for their imports from the grid. This may result in an overpayment to those customers because, while it is true that every kWh exported by a NEM customer reduces PREPA’s variable costs (that is, PREPA avoids incurring these costs), there are some fixed costs that the utility has to incur to interconnect NEM customers to the grid. So, while fuel and purchased power costs (from AES and EcoElectrica) may be avoided, other costs such as debt service, pension payments, and the LUMA fees and fixed costs, for example, have to be paid regardless of how much electricity NEM customers export to the grid.

Therefore, net metering customers should be compensated at a rate per kWh equal to (x) the utility’s avoided costs (as defined by the PREB) minus (y) the utility’s fixed costs (as defined by the PREB). Some advocates for rooftop solar systems argue that overpaying net metering customers is justified as a matter of public policy because it helps to speed up the adoption of DERs. We don’t have an issue with that policy as long as it is (1) clearly and transparently stated and (2) customers understand that, everything else being equal, it would result in higher rates (even if only marginally) for those customers who do not participate in the net metering program because fixed costs will have to be recovered from a smaller customer base.

The DOE found that the utility revenue requirement, relative to the $3.2 billion collected in 2020, fluctuates across three time periods. First, there is a “rapid and substantial increase” in utility incurred costs in the first five years of the analysis, “ending at a level between $5.0 billion and $5.3 billion.” Then, between 2025 and 2045 the revenue requirement trends downward to between $3.9 billion and $4.7 billion. Finally, substantial costs have to be incurred to meet the 2050 objective, increasing the revenue requirement to between $4.3 billion and $5.4 billion. (PR100 Final report, p. 425)

The fluctuation in the utility revenue requirement, in turn, results in variations in the estimated all-in average retail rates over the next 25 or so years. According to the DOE:

  • Between 2020 and 2025, all-in average retail rates increased between roughly 65% to 80% from their starting level of 19.9 cents per kWh;
  • Then, between 2025 and 2045 rates either decreased by up to 0.4% per year or increased by as much as 1.5% per year, depending on the scenario; and
  • After 2045, rates increase again rising between 11% and 17% by 2050, again depending on the scenario. (PR100 Final report, p. 429)

The large increase in rates over the first five years of the transition is driven largely by the rapid short-term build-out of utility-scale generation. This build-out is driven, in turn, by two factors: (1) “meeting industry accepted [resource adequacy] performance; and (2) meeting the 40% RPS by 2025.” (PR100 Final report, p. 230) In order to assess the relative contribution of each of these factors to the 2025 build-out, the DOE ran a scenario variation that relaxed the 40% RPS requirement under the 1LS Scenario. They found that “this relaxation significantly changed the technologies and total capacity selected in the build-out relative to the 1LS results; however, the relaxed RPS total capital and operating costs results were within 1% of the 1LS results. This similar cost result suggests that the dramatic build-out of utility-scale generation is driven principally by the requirement to achieve system reliability rather than the requirement to meet the 40% RPS.” (PR100 Final report, p. 230)

In other words, the initial large increase in rates, estimated to be between 65% and 80% relative to 2020 rates, is to a large extent the legacy cost we all have to pay for the decades of corruption, mismanagement, negligent administration, political shenanigans, and postponed maintenance and capital expenditures at the old PREPA. Those who are prone to romanticize the old PREPA are well advised to keep this in mind before they wax poetic about the “good old days”.

Section 4: Is it Good for the Economy?

The DOE estimated the net economic impact of the transition by analyzing two sets of countervailing effects or impact channels on the economy. The first channel considers the stimulative or positive effects associated with higher construction (CapEx) investments and ongoing O&M expenditures for both (1) utility-scale generation, transmission, and distribution and (2) the increased adoption of distributed PV and storage. (PR100 Final Report, p. 486) These investments have positive impacts on employment, earnings, output, and total value added.

According to the DOE, construction and installation activities, which are temporary, create more than six times the number of jobs and earn more than the operation and maintenance efforts, on average. “However, O&M efforts create longer-lasting jobs with higher associated labor hours than temporary construction efforts.” (PR100 Final Report, p. 402) In addition, construction/installation jobs are subject to a “dramatic boom/bust cycle,” increasing rapidly at first to meet the 40% RPS requirement by 2025 and later the 100% RPS requirement by 2050. In contrast, there is more stability in O&M jobs as renewable energy assets are deployed over time. Finally, utility-scale solar supports 44% of all O&M jobs, on average, followed by residential solar with 31% of O&M jobs. (PR100 Final Report, p. 475) Notice the tradeoffs associated with each of the solar PV generation options.

The figure below shows the aggregate amounts of expected CapEx and O&M expenditures, adjusted for inflation, between 2025 and 2050:


Source: PR100 Final Report, p. 493

However, as we stated previously, the transition will be expensive and both households and businesses will face higher electricity prices. The second channel considers the contractionary or negative effects of higher electricity prices. In general, there are two important macroeconomic effects associated with higher electricity prices.

  • First, higher prices mean electricity expenditures increase as a share of total spending, reducing the consumption of other goods and services and, thus, overall economic activity decreases.
  • Second, as businesses face higher production costs, due to higher electricity prices, they increase the price of their products. Higher inflation leads to lower levels of consumption, production, and employment. Both effects reduce real household income. (PR100 Final Report, p. 486)

The figure below shows the projected average inflation-adjusted electricity rates between 2020 and 2050:


Source: PR100 Final Report, p. 495

Looking at both figures together we discern the following pattern:

  • A sharp increase in both capital spending and utility rates during the period between 2020 and 2025.
  • During the period between 2025 and 2045, there is less new capital spending relative to period 1, while the adoption of distributed PV increases. Real rates relative to 2025 stay flat or fall for most scenarios during this period, with the notable exception of Scenario 3MM.
  • Finally, during the last period between 2045 and 2050, there is another sharp increase in capital expenditures, accompanied by an increase in real rates under all scenarios.

The DOE then proceeded to “disentangle” the simultaneous positive effects due to higher spending from the negative effects of price increases. The figure below shows the dis-aggregated employment effects of the expenditure and price impacts for Scenarios 1LM and 3LS:


Source: PR100 Final Report, p. 497

Under Scenario 1LM in 2025, the investment needed to meet the 40% goal of Act 17 results in more than 16,000 new jobs (blue column). This positive impact, however, is more than offset by the negative effects of higher electricity prices, which induce a loss of 25,000 jobs. The same pattern is observed under Scenario 3LS in 2025.

By 2028, “the expenditure and price impacts are much smaller in magnitude than in Epoch 1. This is because there is relatively little new CapEx in this time frame, and electricity price changes are quite small relative to 2025.” (PR100 Final Report, p. 497)

The story is similar when analyzing the impact on household income. As shown in the figure below, economic activity and employment growth related to new expenditures lead to an increase in household income in 2025 under both Scenarios 1LM and 3LS. However, higher electricity prices over this period lead to a decline in real household income that more than offsets any income gains due to the increase in employment.


Source: PR100 Final Report, p. 498

In sum, according to the DOE model, “for 2025, although some households do benefit from the new jobs created by the CapEx and O&M expenditures, most households in Puerto Rico do not see much benefit; instead, they are adversely affected by the higher electricity prices in the early years.” (PR100 Final Report, p. 498) The DOE notes, though, that “while these adverse effects are substantial, it is important to remember that the 2025 scenario reflects a vastly improved electric system, with more reliability, capacity, and resiliency.” Once again, tradeoffs are unavoidable in this process.

Looking at the whole term of the transition, the economic impact, both on employment and household income, is expected to turn slightly to moderately positive, with some fluctuation depending on the scenario. In terms of the impact on employment, the figure below shows the employment impact for six scenarios out to 2050:


Source: PR100 Final Report, p. 499

  • During the first period up to 2025, there is a net decline in employment across all six scenarios, with the largest losses in 3LS (minus 15,894), reflecting the scenarios relatively high price increase and slightly lower CapEx expenditures. The smallest losses are in Scenario 1LM (minus 9,178). (PR100 Final Report, Appendix J, p. 743 and p. 728)
  • During the second period (2025-2045) employment “impacts are relatively small relative to 2025, reflecting low levels of new spending and small price changes”. (PR100 Final Report, p. 499) The employment impacts are positive across the entire second period for Scenarios 1LS, 1LM, 1MS, and 2LS. Beginning in 2035, “employment impacts for the scenarios with higher levels of distributed PV adoption (3LS and 3MM) turn slightly negative, reflecting relatively larger electricity price increases.” (PR100 Final Report, p. 500)
  • During the final period, between 2045 and 2050, there are significant positive employment impacts. “This reflects higher expenditures as the final investments are made to meet the 100% renewable goals.” In this period, electricity prices also increase, but by a smaller percentage than in Period 1, which means their effects are less detrimental. (PR100 Final Report, p. 500)

The forecast in terms of the impact on household income is fairly similar, as shown in the figure below:


Source: PR100 Final Report, p. 501

  • During the first period, all six scenarios reflect losses of real household income. The losses range from $580 million in Scenario 1LM to $864 million in Scenario 3LS. (PR100 Final Report, Appendix J, p. 728 and p. 743) In all six scenarios, the adverse impacts of simultaneous electricity price increases more than offset the gains in employment due to the additional CapEx.
  • After 2025 and up to 2045, Scenarios 1LS, 1LM, 1MS, and 2LS show relatively small increases in household income while Scenarios 3LS and 3MM show modest decreases between 2035 and 2045. In general, during this period there are much smaller net effects on real household income, as electricity price changes and CapEx are both much lower than in the first period.
  • During the third period, there are positive impacts on real household income across all six scenarios. “Like employment, these increases are largely due to the stimulative impacts of relatively high aggregate expenditures…which are partially, but not fully offset by the real electricity price increases in that time frame…Across the six scenarios, the average increase in real household income is $764 million.” (PR100 Final Report, p. 500.) During this period Scenario 3LS shows the highest increase in household income by 2050, $1.25 billion or 4.74% relative to 2025, while Scenario 3MM shows the lowest increase with $564 million or 2.14% also relative to 2025. (PR100 Final Report, Appendix J, p. 743 and p. 748)
  • In general, “increasing levels of distributed PV plus storage adoption were slightly more harmful to the economy relative to a higher reliance on utility-scale renewable energy resources.” (PR100 Final Report, p. 476)

In sum, the economic impact of the transition to 100% renewable generation, as modeled by the DOE, exhibits several tradeoffs that policymakers will need to take into account: (1) between construction and maintenance jobs; (2) among and between the costs and benefits of the different technologies; and (3) between short-term losses and long-term benefits in terms of employment and household income.

Section 5: Risks and Uncertainties

Any process as complicated as the transition to 100% renewable generation will be full of risks and uncertainties. In this section, we highlight some of the most significant in our opinion.

  • The Challenge of Stabilizing the System – Puerto Rico’s electric system is functional but fragile. At any given moment more than half of the PREPA’s legacy generation units could be offline either due to unscheduled repairs or because they are subject to time use limitations due to the failure to comply with environmental rules and regulations. On the transmission and distribution side, the PR100 Study has highlighted a significant problem with the lower-voltage (38-kV) transmission network as well as voltage control and backfeeding problems in the distribution system. These issues, by themselves, would present a formidable challenge to any utility to manage. When combined with the transition to full renewable generation the whole system is at risk of becoming unstable. Potentially catastrophic scenarios cannot be fully ruled out if things are not done the right way. Stabilizing the electric system in the short term is of paramount importance and should be the number one priority of policymakers right now.
  • Coordination Problems – Coordination among and between (1) federal agencies; (2) federal and Puerto Rico agencies; and (3) Puerto Rico state agencies and municipalities has been problematic ever since the recovery and reconstruction process started. To be fair, some of the initial coordination problems were the product of unreasonable terms and conditions imposed by the Trump administration to intentionally slow down the disbursement of funds to Puerto Rico. And certainly, administrative processes have improved over the last six or so years. Yet coordination problems still remain and have plagued policymaking regarding the reconstruction of the system, the procurement of utility-scale renewable generation, and the timeline for decommissioning fossil fuel legacy assets. In our view, the PREB should be the agency taking the lead in coordinating the actions of the multiple stakeholders in this process as well as the forum for resolving knotty policy and technical issues.
  • Cost/Resiliency/Reliability Tradeoffs – It is clear from the PR100 Final Report that there is a tradeoff between systemic resiliency and costs, both in terms of the rates paid by customers that remain dependent on the grid and in macroeconomic terms. Customer rates and negative short-term macroeconomic effects (in terms of lower employment and household income) tend to be higher under all variations of Scenario 3. In addition, system reliability could be compromised to the extent that excess PV capacity and energy cannot be integrated into the distribution system starting as soon as 2037. If the decision is made to prioritize and put a premium on resiliency rather than on lower costs, then that decision should be made and explained to customers as transparently and clearly as possible so they can plan accordingly.
  • Compensation for Net Energy Metering – Participants in the net metering program currently receive a full kilowatt-hour credit on their energy bills for every kilowatt hour they export to PREPA. This means that those customers do not pay the fixed costs of maintaining the electric grid. Therefore, PREPA’s operational and maintenance costs are disproportionately borne by customers unwilling or unable to participate in the net metering program. Act 17 required the PREB to undertake a study of the net metering program by April 2024 to determine whether the current system is adequately structured. However, that study has not been done. Unfortunately, this has become a political issue as the Puerto Rico legislative assembly has enacted another law that orders the PREB to postpone any such study until 2030 and the FOMB has taken the position that this constitutes an undue interference with the work of the PREB. Leaving political turf battles aside, we believe the NEM study should be executed as soon as possible and its findings should be made public and widely divulged. Again, if the policy decision is made to overcompensate participants in the net metering program to incentivize the installation of rooftop solar systems, then that decision should be explained clearly to all electric customers, including the disclosure that, everything else being equal, it would result in higher bills (even if only marginally) for customers that do not participate in the program.
  • Policy and Regulatory Constraints Regarding the Contribution of Distributed PV to Achieve the RPS Goals – The DOE configured its model to count generation from distributed PV toward the achievement of renewable generation goals. However, “the utility and operator do not yet have policies, metering, or an accounting method in place to do so. Further guidance and regulations on renewable energy certificates will clarify the contribution of distributed renewable generation toward the RPS.” (PR100 Final Report, p. 214) Additional policy guidance is also required to determine the amount of rooftop solar capacity and utility-scale PV generation that will be deployed to meet the statutory RPS requirements. The disagreement between the proponents of each option has caused undue delays in the deployment of renewable generation and only benefitted fossil fuel suppliers.
  • Reaching 40% RPS by 2025 Appears Unfeasible – According to the DOE analysis, “deployment of renewables at a rate to achieve the 40% RPS goal would require a rapid rate of procurement of over 100 MW per month through 2025 from a level of minimal utility-scale build-out in recent years. This rate of deployment would be challenging to achieve.” (PR100 Final Report, p. 229) While we appreciate the gracious and diplomatic drafting of the authors of the PR100 Final Report, the reality is that PREPA, LUMA, and Genera don’t have in place the operating framework to support this rapid build-out; the T&D system needs to be upgraded before this amount of capacity and energy can be integrated into the grid; and procurement has been slow due to policy disagreements and coordination problems. Therefore, the most likely scenario is that Puerto Rico will miss the 40% goal by 2025. Given that scenario, Puerto Rico will be better off extending the intermediate goals to reach 100% renewable generation by 2050 and doing things right rather than carelessly and unthinkingly rushing to meet the 40% goal.
  • Obtaining Funding for the Grid Upgrade Remains Challenging – The DOE estimates that recovery-related investments total $15.441 billion, including generation, transmission and distribution system repairs and replacements, as well as Tranche 1 transmission network upgrades. As we stated above, at least one independent expert estimated additional T&D capital investments between 2030 and 2035 would add up to an additional $13.6 billion. Even if we cut that estimate by half, given that it was made by a consultant hired for litigation purposes, obtaining $6.8 billion in additional financing will not be an easy task. According to the DOE, “capital costs for energy projects in Puerto Rico were significantly higher than they were in the 50 U.S. states. Local factors that lead to elevated costs include transportation of component parts and materials, persistent industry-wide supply chain issues from the COVID-19 pandemic, inflation, and international conflict.” (PR100 Final Report, p. 72) Furthermore, Puerto Rico regulatory requirements may affect the final cost of any given project. While some of these issues may eventually resolve themselves, currently a high level of uncertainty regarding the financing of capital expenditures remains.
  • PREPA’s Access to Capital Markets – Right now PREPA does not have access to the capital markets as it is still undergoing a bankruptcy process. Given that situation, the DOE assumes PREPA will exit bankruptcy in 2024 and will have access to the capital markets by 2028 and, thus, the ability to finance upgrades to the transmission and distribution system going forward from 2028. In our view, this assumption could be overly optimistic for several reasons. First, it is by no means clear that PREPA will exit bankruptcy in 2024. Even if a POA is certified by the Federal Court this year, several creditors have already indicated they will appeal such certification, potentially adding several years of litigation to this process. Second, a restructured PREPA will be limited in its ability to issue new debt until the bonds issued as part of the current restructuring are paid in full. We don’t know yet what legal and financial conditions PREPA will have to satisfy (in the form of financial covenants limiting new debt issuance and legal subordination requirements) in order to issue new debt after 2028. Finally, any announcement regarding the issuance of new debt by PREPA will probably face significant backlash from customers and other stakeholders who remember waste and mismanagement at the old PREPA.
  • Uncertainty Regarding Energy Efficiency Measures and EVs – There is significant uncertainty regarding the implementation of energy efficiency measures and the adoption of electric vehicles in Puerto Rico. These two factors impact load forecasts in opposite directions: increased energy efficiency reduces demand for electricity while relatively high adoption of EVs increases demand for electricity. In our view, the most likely scenario right now is that Puerto Rico will not meet its energy efficiency objective because it is not making the necessary investments to achieve it, while the adoption of EVs is likely to be at a lower rate than in the U.S. due to Puerto Rico’s lower wages and income.
  • Risk of Grid Defection/Death Spiral – Under several of the scenarios modeled by the DOE, the volume of electricity sales declines faster than the total cost required to serve customers. This means that the rate per kWh increases and adds to the financial burden of existing customers, leading to even more “grid defection” (mostly higher income individuals and industrial/commercial clients), which means the remaining costs of service are spread over an even smaller customer base, leading to even higher electricity rates, and so on. This cycle is called a “utility death spiral” and while a complete utility death spiral has yet to be experienced in the U.S. electricity sector, in the case of Puerto Rico this risk cannot be ruled out. The DOE vaguely hinted as much when it stated that “PR100 analyzed a highly centralized utility in a future that was increasingly comprised of distributed and decentralized electricity resources which were neither owned nor controlled by the utility. Our analysis illustrates the implications of this seemingly dichotomous future: utility costs could not be reduced as quickly as retail sales resulting in higher retail rates.” (PR100 Final Report, p. 446)

Conclusion

Five years ago, Puerto Rico enacted legislation setting the ambitious goal of generating 100% of its electricity from renewable sources by 2050 even as it rebuilt its electric grid, which was devastated by Hurricane María in 2017. This is a clear and compelling objective that is worth pursuing. Yet success is not guaranteed because it is also incredibly complicated. The policy questions require analyzing theoretical, technical, and economic constraints as well as making difficult tradeoffs among and between complex economic, technical, and social objectives. In addition, the technology is still evolving. In that sense, there is a tension between the technology that is already available now and the technology that is not yet viable or commercially available.

We also need to note that the transition to 100% renewable generation has a political economy dimension, as the old technology (and those who benefitted from it) is replaced by a still evolving new one (and those who stand to gain from it). Humanity’s natural resistance to change is thus reinforced by powerful economic and financial incentives. 

Furthermore, during the last five years, Puerto Rico has fallen behind schedule to meet the interim objective of 40% renewable generation by 2025 due to bureaucratic and coordination failures. We are, therefore, at a critical juncture. We still have time to rebuild our electric grid and to completely switch away from fossil fuel generation by 2050. But achieving those objectives will require strategic thinking, skilled policymaking, competent execution, tactical dexterity, the ability to act collectively over the long term, and inspired leadership—resources that have been in short supply in Puerto Rico for at least a generation. Make no mistake, this endeavor will be challenging, hard, and expensive. There will be setbacks along the way. But it is the right thing for Puerto Rico to do for the generations yet to be born. So, we better get working if we are going to make it.

Let’s get going.

CNE Review – March 2024

Published on March 14, 2024 / Leer en español

See all editions of the
CNE Review
SHARE

In This Issue

CNE’s Policy Director analyzed the recently published summary of the Puerto Rico Grid Resilience and Transitions to 100% Renewable Energy Study (“PR100” or the “Study”). Click here to read the full analysis.

While the PR100 Final Report will not be released until late March, in this issue of the CNE Review we highlight some of the findings of the summary due to their importance and their potential policy implications for Puerto Rico’s electricity sector.

In the full analysis, we outline the U.S. Department of Energy’s (“DOE”) scenarios, based on different assumptions, that would enable Puerto Rico to achieve the goal of  100% renewable generation by 2050. While this study provides valuable guidance, difficult decisions will have to be made by Puerto Rico’s government that imply important tradeoffs between affordability, time, and resources.

CNE advocated strongly for Act 17 of 2019 and we believe in the goals set by this law. Puerto Rico needs an electricity system based on renewable energy that is both reliable and affordable. But as the country moves toward this transition, we need to make sure that we don’t lose sight of the well-being of both families and businesses. Our next steps will include analyzing the DOE’s full report which will be made public at the end of March. CNE will continue to monitor, analyze, make recommendations, and advocate for an affordable and sustainable electricity system for Puerto Rico.

Insights + Analysis from CNE

Analysis of the PR100 Summary Report

By Sergio M. Marxuach, Policy Director

Introduction

The Puerto Rico Energy Public Policy Act of 2019 (“Act 17 of 2019”) requires that Puerto Rico meet 100% of its electricity needs with renewable energy by 2050. To reach that objective, Act 17 set the following interim goals:

On February 7, representatives of the DOE, including Secretary Granholm, presented a summary of the findings of the PR100 Study. This Study was the product of a two-year effort led by the DOE, with the collaboration of the University of Puerto Rico Mayaguez and other local stakeholders, to analyze and identify possible pathways for Puerto Rico to achieve its goal of generating 100% of its electricity from renewable energy sources by 2050.

While public discussion has focused on a few of the Study’s main findings indicating that Act 17’s requirement can be met by 2050, we want to highlight the different scenarios presented in the summary, the tradeoffs required, and their potential policy implications.

In this process, it is also crucial for local decision-makers to take into consideration the following unanswered questions and inform all stakeholders on how they will be addressed: 

  • How much will it cost to achieve maximum resilience in Puerto Rico? 
  • How much can consumers afford or are willing to pay to transition to renewables?
  • Which agency or entity will decide on the scenario, if any, to be implemented in Puerto Rico?
  • What is the economic impact of each scenario, with their variants, on GNP, GNP growth, consumption, employment, and income?
  • If the cost of maximizing resilience is too high, who decides which geographic areas will be excluded?
  • What is the total investment required by system segment (transmission, distribution, generation, battery storage, access, and connectivity infrastructure) to achieve the 100% renewable energy objective? How will that investment be financed (again broken down by segment)?
  • How much funding has been identified, committed, and spent for each of the segments?

Scenarios, Tradeoffs & Policy Implications

Scenarios

The DOE, together with several of the national labs and local stakeholders, modeled three scenarios to meet the 100% target by 2050. Each scenario assumes the current dilapidated electric grid is sufficiently repaired to support the reliable operation of the electric system before the full deployment of renewable generation.  Then the scenarios are initially differentiated by varying the adoption level of distributed energy resources (“DERs”) such as rooftop solar, utility-scale solar photovoltaics (“PVs”), and wind generation units, among others. Two variations are added for land use (how much land is needed to develop these new projects), and electric load with 2 variants each, resulting in a total of 12 scenario variations.

Source: PR100 Summary, p. 8.

Scenario 1 assumes the adoption of DERs is driven primarily by “economic factors and is based on financial savings and the value of backup power to building owners”. It also prioritizes the deployment of DERs on “critical infrastructure such as hospitals, fire stations, and grocery stores”.  This is called the “Economic” Scenario. 

Scenario 2 extends the adoption of DER beyond the levels specified in Scenario 1 to include “very low-income households (0%-30% of area median income) and those in remote areas who would not have bought systems solely based on economics”. This is called the “Equitable” Scenario.

Scenario 3 models the “maximum deployment of DERs on all suitable rooftops at a level that meets their critical loads” (PR100 Summary, p. 8). This is called the “Maximum” Scenario.

Regardless of the scenario, the DOE states, increased system capacity is needed immediately to maintain its stability. 

Tradeoffs

We found that the Scenarios modeled by the DOE present significant tradeoffs between resilience (Scenarios 2 and 3) and energy affordability (Scenario 1); between land use and energy affordability (“less land” scenarios tend to be more expensive); between meeting the 40% goal by 2025 and achieving acceptable grid reliability in the short term; and between incurring high short-term costs to obtain long-term benefits, depending on the scenario to be implemented.

The existence of these tradeoffs raises the question of which agency or entity should be in charge of making these decisions. We strongly recommend that the Puerto Rico Energy Bureau (“PREB”) be in charge of making these decisions.

Policy Implications
         To Achieve the 2025 Interim Goal:

By mid-2023, notwithstanding a significant increase in distributed solar PV generation, only between 3% and 5% of the generation capacity available for the grid came from renewable sources.

This means that Puerto Rico is significantly behind schedule to meet the interim target of 40% renewable generation by 2025. Puerto Rico will likely miss it.

Furthermore, according to the DOE, the all-in average retail rate would increase between 66% and 83% between 2020 and 2025, depending on which scenario is implemented.

A rate increase of this magnitude would have severe, material adverse effects on the economy of Puerto Rico in the short term and is simply not economically feasible. It will be necessary to mitigate these negative effects, either through subsidies, an extension of the timeline for achieving the transition, or through other policies.

         Achieving the 2050 Goal

According to the Study, it is feasible to achieve the objective of 100% renewable energy generation in Puerto Rico by 2050 without using agricultural lands for developing utility-scale generation. However, the economic cost of the transition to 100% renewable energy by 2050 is quite significant, regardless of the scenario.

In addition, there appears to be a contradiction in the Study since it states that the 100% objective can be met using “mature” technologies such as utility-scale PV, distributed PV, and land-based wind. Yet, later on in the report, it states that the optimal resource mix to meet the 100% objective includes generation from engines using biodiesel fuel. To our knowledge such technology is not yet mature or commercially viable for the generation of electric power.

The PR100 Study forecasts loads out to 2050 and models capacity expansion to find the lowest-cost system for each scenario while meeting load requirements. In general, the scenarios outlined in the report with higher deployment of DERs using less land tend to be, on average, more expensive than other scenarios. They also result in higher rates for the consumer and induce greater short-term adverse effects on the Puerto Rican economy. How will these adverse effects be minimized if one of these scenarios is chosen?

         The Challenge of Forecasting Demand

Forecasting long-term energy demand trends is one of the most complex issues in this planning exercise. The time horizon is too long, there are too many variables as well as multiple unknown unknowns (for example, the risk of a major hurricane striking the island ten years from now). Therefore, no one knows what the demand for electricity will be in Puerto Rico twenty-five years from now. It is still necessary, however, to take into account potential risks and uncertainties and start the transition to achieve the 100% goal by 2050. This issue is also important in the court-led process to restructure the debt of the Puerto Rico Electric Power Authority (“PREPA”) that is currently ongoing in federal court.

Given this significant uncertainty, we recommend that representatives of the DOE, the Fiscal Oversight and Management Board, Genera, LUMA, PREPA, and the PREB meet and seek agreement on a single set of forecasts out to 2050 and that the same projections be used for both the development of PREPA’s new IRP and in PREPA’s financial Plan of Adjustment that will be eventually certified by the federal court. Using one set of load forecasts for operational planning purposes (the IRP) and another for financial planning purposes (the Plan of Adjustment) does not make sense.

More Information is Needed

The PR100 Summary appears to present a good preview of the findings of the PR100 Study. From the Summary it seems that the PR100 Study is a thorough and thoughtful analysis carried out by a respected group of stakeholders. It is a welcome contribution to the public debate and a valuable resource for those who analyze and study Puerto Rico’s electricity system. We hope that the final report provides more details on the following critical areas:  

  • Load Forecasts: We need more information about the methodology used by the DOE to forecast electricity demand over the long term to reach any conclusion regarding the reasonableness of its estimates. Specifically, we need to know whether the DOE estimated demand functions for commercial, industrial, and residential users; the price elasticities used and how they were calculated; and additional information regarding their energy efficiency estimates.
  • Biodiesel Fuels: We are not familiar with this technology and need more information before reaching any conclusions regarding the feasibility of its future use in Puerto Rico for the generation of electric power.
  • Economic Impact Analysis: We need more information regarding the economic impact of rate increases in the short term on GNP level, GNP growth, employment, income, and consumption expenditures to assess the economic feasibility of the different scenarios.
  • Total Capital Expenditures and Sources of Financing: It would be useful if the final PR100 Study included a breakdown, by scenario and system segment (transmission, distribution, generation, energy storage, access infrastructure, etc.), of (1) all the capital expenditures required to achieve the 100% goal by 2050 and (2) potential financing sources for each of these expenditures.

On Our Radar…

Reconstruction Spending – A recent report from the United States Government Accountability Office (“GAO”) found that “the Federal Emergency Management Agency (FEMA) had awarded about $23.4 billion in Public Assistance to Puerto Rico’s permanent recovery work related to hurricanes Irma and Maria and the 2019 and 2020 earthquakes, as of June 2023. Of that, Puerto Rico has expended about $1.8 billion and a substantial amount of permanent work remains. Further, about $11.3 billion of the awarded funds needs FEMA’s authorization before Puerto Rico can expend it.” In other words, we have made some progress but a lot of work remains to be done.

An Analysis of PR100 Summary Report

Analysis of PR100 Summary Report

Published on March 13, 2024 / Leer en español

Sergio portrait
Policy Director
DOWNLOAD
SHARE

Introduction

On February 7, representatives of the U.S. Department of Energy (“DOE”), including Secretary Granholm, presented a summary of the findings of the PR100 Study. This was a two-year effort led by the DOE, with the collaboration of the University of Puerto Rico Mayaguez and other local stakeholders, to analyze and identify possible pathways for Puerto Rico to achieve its goal of generating 100% of its electricity from renewable energy sources by 2050.

While the PR100 Final Report will not be released until late March, in this policy brief we highlight some of the findings of the PR100 Summary due to their importance and their potential policy implications for Puerto Rico’s electricity sector.

The Objective

The Puerto Rico Energy Public Policy Act of 2019 (“Act 17 of 2019”) requires that Puerto Rico meet 100% of its electricity needs with renewable energy by 2050. In order to reach that objective, Act 17 set the interim goals of 40% renewable generation by 2025; 60% renewable generation by 2040; the phaseout of coal-fired generation by 2028; and a 30% increase in energy efficiency by 2040. By mid-2023, notwithstanding a significant increase in distributed solar PV generation (as opposed to utility-scale solar), only between 3% and 5% of the generation capacity available for the grid was from renewable sources. Furthermore, “achieving the 40% target by 2025 would represent an increase of at least 3 GW of additional renewable energy capacity if met with utility-scale solar” (PR100 Summary, p.1).

In plain English, this means that Puerto Rico is significantly behind schedule to meet the interim target of 40% renewable generation by 2025 and it is highly likely that Puerto Rico will miss it.

The Scenarios and their Variations

The DOE, together with several of the national labs and local stakeholders, defined three scenarios to meet the 100% target by 2050. All three scenarios assume that “the transmission and distribution networks were repaired sufficiently to support reliable operation of the electric system, and that these repairs were completed with federal funding” (PR100 Summary, p. 4). The scenarios are initially differentiated by varying the adoption level of distributed energy resources (“DERs”).

Scenario 1 assumes the adoption of DERs is driven primarily by “economic factors and is based on financial savings and the value of backup power to building owners”. It also prioritizes the deployment of DERs on “critical infrastructure such as hospitals, fire stations, and grocery stores” (PR100 Summary, p.7-8). This is called the “Economic” Scenario throughout the PR100 Study.

Scenario 2 extends the adoption of DER beyond the levels specified in Scenario 1 to include “very low-income households (0%-30% of area median income) and those in remote areas who would not have bought systems solely based on economics” (PR100 Summary, p. 8). This is called the “Equitable” Scenario.

Scenario 3 models the “maximum deployment of DERs on all suitable rooftops [our emphasis] at a level that meets their critical loads” (PR100 Summary, p. 8). This is called the “Maximum” Scenario.

The graphic below shows the three scenarios modeled in the PR100 Study, “distinguished by varying levels of DER adoption. Differences between scenarios are circled in blue.”


Source: PR100 Summary, p. 8.

In addition, the authors also defined two variations regarding (1) land use and (2) electric load (demand) projections to 2050, to apply to each of the three scenarios.

The land use variation, in turn, has two variants: (1) Less Land and (2) More Land. The purpose of modeling this variation was to determine whether the 100% target by 2050 can be “met by developing utility-scale projects only on land not designated for agricultural purposes” or whether the use of agricultural lands would be required (PR100 Summary, p. 9).

In both land use variants, “development of utility-scale solar PV and wind is restricted from areas such as roadways, water bodies, protected habitats, flood risk areas, slopes greater than 10%, and agricultural reserves. In the Less Land variant, development of utility-scale projects is also restricted from areas identified for agricultural use in the 2015 Land Use Plan” (PR100 Summary, p. 9).

This analysis concludes that in the “More Land variant…638 km2 [246.3 square miles] are available for solar development, with technical potential of 44.66 GW” while in the “Less Land [variant] the developable area is 203 km2 [78.4 square miles] with technical potential of 14.22 GW” (PR100 Summary, p. 9).

The electric load variation also has two variants: (1) the Mid case and (2) the Stress case. Each case projects electric load out to 2050 taking into account (1) end-use demand variation due to changes in population, manufacturing employment, economic activity, and other variables; (2) increased demand from the adoption of electric vehicles (“EVs”); and (3) decreasing demand from the implementation of energy efficiency (“EE”) measures.

The Stress case variant was expressly modeled to “help decision makers not to under plan in the event the load does in fact increase and to account for uncertainty in the inputs to the end-use load calculation” (PR100 Summary, pp. 9-10). The development of this variant leads us to think that the DOE believes decision-makers in Puerto Rico could be underestimating the long-term demand for electricity on the island.

The Mid case variant shows “slightly decreased end-use electricity sales over time, primarily due to forecasted long-term declines in population and real gross national product” (PR100 Summary, p. 10). On the other side of the spectrum, the Stress variant “assumes the combination of end-use loads and energy efficiency will result in flat annual electricity sales and electric loads from FY23 to FY51” (PR100 Summary, p. 10). When the adoption of EVs is added in, the electricity load increases moderately over time out to FY51.

In sum, the PR100 team modeled three scenarios with two variations each with two variants, resulting in a total of 12 scenario variations. The scenarios are identified first by number and then by variation. For example, scenario 1LS means Scenario 1 (Economic), Less Land, Stress load. According to the PR100 Summary, there appears to be fairly small variation in the results among and between the scenarios during the next few years.

The key findings here are: (1) the DOE is assuming federal funding in the immediate to near term will be used to finance the repair of the transmission and distribution networks to support the reliable operation of the electric system before the deployment of DERs begins in earnest; (2) decisionmakers in Puerto Rico could be underestimating long-term electricity loads; and (3) “regardless of scenario or source of renewable energy, increased capacity is needed on the system immediately to achieve a robust electricity system for Puerto Rico” (PR100 Summary, p. 10).

Resource Assessment

The DOE executed assessments of the renewable energy sources in Puerto Rico to determine whether the potential of “solar, wind, hydro, and other sources is sufficient to meet Puerto Rico’s goal of 100% renewable energy” (PR100 Summary p. 11). The main findings were (1) that Puerto Rico’s renewable energy potential exceeds the projected loads out to 2050 by a factor of 10; (2) the 100% objective can be met using “mature” technologies such as utility-scale PV, distributed PV, and land-based wind; and (3) “utility-scale solar PV potential capacity on non-agricultural land is sufficient to meet total annual electric load to 2050.” (PR100 Summary, p. 14).

However, the DOE also found that the costs associated with DER deployment under the Less Land variation are higher than the More Land variation, “across all modeled years and technology scenarios” (PR100 Summary, p. 12). This is due to (1) reduced economies of scale; and (2) the increased need for infrastructure (access roads, interconnections, etc.) under the Less Land variation, which would result in a greater number of smaller solar PV and land-based wind plants to be installed—more dispersed across Puerto Rico—when compared with the More Land variation.

In sum, the DOE found that the levelized cost of electricity (“LCOE”) on average would be $79/MWh under the Less Land variant and $75/MWh under the More Land variant. A difference of $4/MWh, or 5.33%, which over some 25-odd years is quite significant.

From a policy perspective, the main finding here is that there appears to be a tradeoff between land use and energy affordability. That tradeoff, in turn, raises the question of which agency or entity should be in charge of deciding to choose one variant over the other.

Electric Load Forecasts

Forecasting long-term energy demand trends is one of the most complex issues in this planning exercise. The time horizon is too long, there are too many variables as well as multiple unknown unknowns (for example, the risk of a major hurricane striking the island ten years from now). Therefore, no one really knows what the demand for electricity will be in Puerto Rico twenty-five years from now. It is still necessary, however, to go through the exercise taking into account potential risks and uncertainties, in order to start the transition to achieve the 100% goal by 2050. This issue is also important in the court-led process to restructure the debt of the Puerto Rico Electric Power Authority (“PREPA”) that is currently ongoing in federal court.

Given the importance of these forecasts, we will take a deeper look into the analysis and projections set forth in the PR100 Summary. As we mentioned above, the DOE executed its load analysis by analyzing three factors: (1) modeling various end-use parameters; (2) modeling the trajectory to achieve the statutorily mandated goal of a 30% increase in energy efficiency by 2040; and (3) projecting the adoption of EVs in Puerto Rico.

With respect to end-use parameters, the DOE took into account “future population size, changes to manufacturing employment, gross domestic product, and climate”. Specifically, they analyzed “existing hourly end-use loads to determine if in the future these profiles would increase or decrease from year to year” (PR100 Summary, p. 15). As noted above, the DOE found that end-use loads are anticipated to decrease across Puerto Rico by 2050 in the Mid case trajectory, based primarily on population and economic forecasts.

In terms of energy efficiency, the DOE carried out two modeling exercises, using different methodologies, to ascertain the feasibility of achieving a 30% increase in energy efficiency (which everything else being equal would result in a reduction in loads) by 2040. Their main finding in this area was that “achieving the 30% goal is ambitious as compared with the bottom-up analysis results which show an 18% increase [in energy efficiency] by 2050” (PR100 Summary, p. 15).

The DOE also projected the adoption of electric vehicles (light as well as medium and heavy-duty) and their contribution to electric load. The key finding here is that the DOE estimates that 25% of light-duty vehicles and 48% of medium- and heavy-duty will be electric by 2050 (PR100 Summary, p. 15).

Finally, the DOE modeled a Stress load forecast “which assumes the combination of end-use loads and energy efficiency will result in flat annual electricity sales and, due to the addition of EV loads, load trajectory increases” (PR100 Summary p. 15).

According to LUMA, total electricity sales in Puerto Rico were 16,282 GWh in FY22. The two variants modeled by the DOE forecast the following paths out to FY2051:

In the Mid case, sales decrease to 14,240 GWh in FY30 and to 13,192 GWh in FY51, a decrease of 1,048 GWh, or 7.4% relative to FY30, with EVs accounting for 2% of electricity sales in FY30 and 16% in FY51. The graph below shows the projected load decline in the Mid case.


Source: PR100 Summary, p. 16.

In the Stress case, sales are projected to increase to 16,537 GWh in FY30 and to 18,422 GWh in FY51, an increase of 1,885 GWh, or 11.4% relative to FY30, with EVs accounting for 2% of sales in FY30 and 12% in FY51. The graph below shows the projected load increase in the Stress case (PR100 Summary, p. 15).


Source: PR100 Summary, p. 16.

Notice that the difference between both trajectories is 5,230 GWh by FY2051, equivalent to 32% of actual total electricity sales in FY22. This is a huge margin of error, which unfortunately is inevitable given the nature of the exercise.

The DOE by modeling a Stress case with increasing load appears to be suggesting that decision-makers in Puerto Rico could be underestimating future loads and should take into account the Stress scenario in their planning. This is an interesting suggestion, given a recent op-ed published in El Nuevo Día by Dr. Ramón Cao, a former professor of econometrics at the University of Puerto Rico, suggesting that the Financial Oversight and Management Board for Puerto Rico (“FOMB”) could be overestimating demand for electricity over the next 25 years in the forecasts it has filed with the federal court in connection with PREPA’s Plan of Adjustment. Just to be clear and for the avoidance of doubt, we are not suggesting one estimate is better or more accurate than the other. We are simply pointing out the radical uncertainty surrounding these long-term forecasts.

Given this level of uncertainty, we recommend that representatives of the DOE, the FOMB, Genera, LUMA, PREPA, and the Puerto Rico Energy Bureau (“PREB”) meet and seek agreement on a single set of forecasts out to 2050 and that the same projections be used for both the development of PREPA’s new Integrated Resource Plan (“IRP”) and in PREPA’s financial Plan of Adjustment that will be eventually certified by the federal court. It would be irrational to use one set of load forecasts for operational planning purposes (the IRP) and another for financial planning purposes (the Plan of Adjustment). 

At this time, though, we do need more information about the methodology used by the DOE to forecast electricity demand over the long term in order to reach any conclusion regarding the reasonableness of its estimates. Specifically, we need to know whether the DOE estimated demand functions for commercial, industrial, and residential users; the price elasticities used and how they were calculated; and additional information regarding their energy efficiency estimates. We hope this additional information will be available in the Final Report of the PR100 Study to be issued in late March.

In sum, the key finding here is that there is significant uncertainty regarding future electric load in Puerto Rico. According to the DOE modeling, final demand by FY2051 could be as low as 13,192 GWh or as high as 18,422 GWh. Further information is needed to analyze the reasonableness of these results.

Renewable Capacity Expansion

After forecasting loads out to 2050, the DOE then proceeded to model capacity expansion to find the lowest-cost system for each scenario while meeting load requirements. The first key finding here is that even if all six tranches of PREPA’s renewable energy generation and storage plan are executed as intended (something that will NOT happen as PREPA is already at least two years behind schedule in executing this plan), significant new investment in additional generation capacity, “on the scale of hundreds of megawatts”, is needed immediately to achieve “acceptable reliability performance” (PR100 Summary, p. 21). It is not clear from the PR100 Summary exactly how much new capacity is needed nor how such investment would be financed in the short term.

In order to achieve the 40% goal of renewable energy by 2025, “the optimal expansion planning results include 2,600—3,500 MW of utility-scale capacity, depending on the scenario, along with approximately 700 MW of 4-hour duration utility-scale batteries, 260—400MW of long-duration storage, and 170—340MW of land-based wind” (PR100 Summary, p. 21). During this phase, much of the existing fossil-fueled generation remains in place.

The chart below sets forth the modeling results by scenario to achieve 40% renewable energy generation by 2025:


Source: PR100 Summary, p. 21.

We note that the DOE asserts that “the current pace of utility-scale deployment is likely too slow to result in 40% renewable energy by the 2025 statutory deadline and a reliable grid in the near term” (PR100 Summary, p. 21). Thus, there appears to be another tradeoff, in this case between meeting the 40% goal by 2025 and achieving acceptable grid reliability in the short-term.

To achieve 100% generation from renewables by 2050, the “optimal mix of resources includes the addition of energy storage and biodiesel engines to serve system energy demands during periods of low wind and solar output” (PR100 Summary, p. 22). According to the DOE, “once all fossil-fueled plants are retired the system requires some biodiesel engine capacity (or a similar alternative resource) that can operate for prolonged periods.” To our knowledge, the requirement to use biodiesel engines by 2050 to meet demand during periods of low wind and solar output is new. We are not familiar with this technology and would need more information before reaching any conclusions regarding the feasibility of its future use in Puerto Rico for the generation of electric power.

The chart below sets forth the total annual electricity generation by scenario to meet 100% renewable generation by 2050:


Source: PR100 Summary, p.22.

Finally, the DOE found that curtailment (reduction) of solar generation capacity in 2050 is “notable.” According to the PR100 Summary, “the expectation is that variable sources of renewable energy are curtailed somewhat regularly to balance the system; this is a common finding in 100% renewable energy studies and is still the least-cost system solution” (PR100 Summary, p. 23).

The main findings with respect to rollout of renewable generation in Puerto Rico are: (1) there is a need for hundreds of MW of new generation capacity in the immediate term to ensure grid reliability; (2) the current pace of utility-scale solar deployment is too slow to meet the 40% goal by 2025; (3) the optimal resource mix suggested by the DOE to meet the 100% objective includes generation from biodiesel engines; and (4) curtailment of significant solar capacity appears to be necessary to balance the system in the long-term.

Transmission and Distribution Issues

It is well-known that Puerto Rico’s transmission and distribution system (“T&D System”) has severe problems. In this section, we highlight two issues that were identified by the DOE.

On the transmission side, the DOE found that the lower-voltage (38-kV) transmission network components are insufficient to handle the projected system transitions because “the number of new generation interconnections and amount of distributed generation capacity significantly alters the flow patterns on the local transmission infrastructure that is predominantly served by 38-kV assets” (PR100 Summary p. 23). Furthermore, several mitigating actions are required to “avoid frequent and debilitating 38-kV network overloads even at 40%-50% renewable energy”, regardless of the scenario (PR100 Summary, p. 24). Therefore, this is an issue that will need to be addressed relatively soon if Puerto Rico is serious about meeting the 100% renewable goal by 2050.

On the distribution side, the DOE found that (1) some feeders in Puerto Rico today operate outside the standards of the American National Standards Institutes Range A voltages, even with no solar PV generation; and (2) “uncontrolled distributed PV capacity under PR100 Scenarios 1, 2, and 3 was found to exceed 65%-95% of the studied distribution feeders’ hosting capacities, due to issues such as backfeeding and PV-caused voltage violations” (PR100 Summary, p. 28).

With respect to the first issue the DOE assumed that those feeders would be corrected to operate within American National Standards Institutes Range A voltages. The PR100 Summary does not include an estimate of the cost of carrying out these repairs nor of any financing sources available to pay for them. To address the second issue, the DOE identified several mitigation strategies that were found to eliminate “nearly all” of the negative impacts of high distributed PV generation.

The main finding here should not be surprising to anyone familiar with Puerto Rico’s power grid. Significant work needs to be done to bring the island’s T&D System up to 21st-century standards even as Puerto Rico begins the transition to achieve 100% renewable generation by 2050.

Economic Impact Analysis

The transition to 100% renewable energy is costly. New investment is needed to improve the T&D System, bring online new generation capacity, acquire and install large-scale battery storage systems, and build out the necessary infrastructure (access roads, new interconnections with the T&D System, etc.) to achieve the statutory objective by 2050. All this new investment needs to be financed in some way.

In this section, we will look at the principal findings set forth in the PR100 Summary regarding the economic impact of making the required investments to achieve full renewable generation. By definition, the findings in the PR 100 Summary are incomplete, as it is only a summary of the full study. It does not include an analysis of the reduction in the social burden and environmental costs associated with the transition to 100% renewables nor does it present the full results of its economic analysis or the methodology for executing that analysis. The PR100 Summary is also remarkably silent as to financing alternatives, a topic we will take up in the next section.

Notwithstanding those limitations in the content of the summary, the DOE is quite clear upfront about the magnitude of the costs involved. The DOE “found that the utility-incurred costs to transform Puerto Rico’s electric grid to one that is reliable will be significant regardless of the mix of generation technologies” (PR100 Summary, p. 28). The PR 100 Summary presents the cost estimates for two scenarios (1) Scenario 1, Less Land, Stress Load (“1LS”) and (2) Scenario 3, Less Land, Stress Load (“3LS”).

In general, the principal finding is that the “utility must charge substantially higher all-in average retail rates in Scenario 3LS than Scenario 1LS because the former has 20% less utility-sold electricity than the latter” (PR100 Summary, p. 28). The charts below show the revenue required by the utility in order to cover its costs under the two scenario variations as well as an estimate of the all-in average residential rate over time in 2021 dollars.


Source: PR100 Summary, p.29

The yellow line shows how the all-in average retail rate evolves over time as new investments are made to achieve the 100% renewable objective. Under both scenarios there is a sharp increase in average retail rates between 2020 and 2025, estimated to be between 66% and 83%, driven by several factors (1) investments in the near term to achieve resource adequacy and grid stability; (2) the procurement of new renewable generation and storage systems; (3) the need to keep using fossil fuel generation while ramping up renewable generation at the same time; (4) the costs of new energy efficiency programs; and (5) the costs of paying PREPA’s legacy debt and pension obligations. We note that under scenario 1LS, the average retail rate per kWh increases from approximately 21 cents in 2020 to about 34 cents by 2025; while under scenario 3LS the average retail rate per kWh increases to approximately 38 cents by 2025 in 2021 dollars.

After this initial period, costs stabilize and utility revenue requirements decline between 9% and 24% during the period between 2025 and 2045, as fossil-fuel generation is retired and replaced by renewable capacity, which lowers fuel and other associated costs over time.

Finally, between 2045 and 2050 “the system experiences notable cost increases that would be incurred by any system moving from already high levels of renewable energy to 100% renewable energy” (PR 100 Summary, p. 29). According to the DOE, this cost increase is due to the retirement of any remaining fossil-fuel generation units and replacing “the firming and balancing function they perform at high levels of renewable energy (i.e., supplying energy only on an as-needed basis when renewable generation is low and storage reserves are exhausted, for example during periods with several cloudy days in a row)” (PR 100 Summary p. 29). The estimated impact on the all-in average retail rate of this cost increase is estimated to be between 11% and 17% (PR100 Summary, p. 30).

Under both scenarios, then, there is a sharp increase in the all-in average retail rate in the short-term, followed by a period of relative rate stability during the medium to long term, and then another significant increase as the final push to 100% renewable generation is made during the 2045-2050 period.

While we don’t have access yet to the full economic analysis carried out by the DOE, we can assert with a high degree of confidence that an increase of 66% to 83% in the average retail rate in the short term would have severe, materially adverse effects on the Puerto Rican economy, in terms of GNP, GNP growth, employment, consumption, and income for several reasons. First, the Puerto Rican economy is just recently finding its legs after a prolonged period of secular stagnation. Second, the post-disaster reconstruction of the island’s infrastructure has been delayed and it is still an ongoing process. Finally, if we focus specifically on residential customers, the electricity cost share of wallet (electricity expenditures as a percentage of household median income) in Puerto Rico is already the highest in the United States and among the highest in the Caribbean region as shown in the chart below:


Source: FOMB, 2023 Certified Fiscal Plan for the Puerto Rico Electric Power Authority, p. 44.

An increase in the retail rate of the magnitude estimated by the DOE is simply not economically feasible given the current state of the Puerto Rican economy. This means that it will be necessary to mitigate this impact, either through subsidies, extending the timeline for achieving the transition to 100% renewables, a different technology mix, or through other policies.  

The DOE also executed an analysis of the net impact of the transition to 100% renewable generation on real household income (“HHI”) in Puerto Rico. Presumably, that analysis takes into account both the costs associated with the transition to renewables as well as any positive income and employment effects associated with the new investment needed to carry it out. The chart below shows the real HHI effects (in millions of dollars) of six scenarios for all years through 2050:


Source: PR100 Summary, p. 30.

As expected, the short-term impact of the transition on HHI is negative, followed by a modest positive impact between 2025 and 2045, and then a significantly positive effect by 2050. Note that if HHI decreases over the short term it is highly probable that consumption expenditures, employment, and real GNP will also decrease over the same period. However, we don’t have information at this point regarding the magnitude of those additional short-term economic effects.

Finally, we note that Scenario 3LS, which maximizes roof-top solar installations, uses less land, and assumes stress load conditions, produces the largest negative impact on HHI in the short term, and has a modest positive effect on HHI between 2025 and 2035, followed by a modest negative impact between 2040 and 2050. By 2050, however, it will have the largest positive effect on HHI. Therefore, there is a clear tradeoff in this scenario between economic costs to be incurred in the short term and economic benefits to be realized in the long term. Policymakers will have to take into account this explicit tradeoff when deciding which scenario to implement.

Financing the Transition

The PR100 Summary provides little information regarding the potential sources for financing the transition to 100% renewables. Footnote 2 on page 1 of the PR100 Summary sets forth the following sources of federal financing (“obligated funds”) for restoring and building a more reliable and resilient energy system for Puerto Rico:

  • FEMA Hazard Mitigation Assistance: $7.8 billion
  • FEMA Public Assistance: $9.5 billion
  • HUD Community Development Block Grant (“CDBG”) funds (Electric Grid): $1.9 billion
  • HUD CDBG Community Energy and Water Resilience Installations Program: $800 million
  • DOE Puerto Rico Energy Resilience Fund: $1 billion

Thus, a total of $21 billion in federal funds has been “obligated” to improve Puerto Rico’s electric system. Most of that money, approximately $19.2 billion, or 91%, has been earmarked for improving the T&D System. The rest has been used so far to finance the installation of rooftop solar systems. The PR100 Summary, however, does not state whether these amounts are sufficient to cover all the repairs needed to upgrade the T&D System. With respect to new generation capacity, it is already known that additional resources are needed to finance rooftop solar and battery systems as well as utility-scale solar PV and wind generation systems.

We note that there is a political risk that arises from depending solely or mostly on federal funding for modernizing the grid and financing DERs for low-income households. It is possible, under certain circumstances, to rescind the obligation of federal funds (sometimes referred to as the “deobligation” of funds). The political risk would arise in the event that Donald Trump wins the next presidential election in November 2024.

The first Trump Administration imposed unduly burdensome requirements on Puerto Rico and significantly delayed the obligation of CDBG funds, as evidenced by a report issued by the Office of the Inspector General of the Department of Housing and Urban Development and other sources. A Trump victory in November could put at risk funding not only for the modernization of the grid but for the entire reconstruction process. Puerto Rico would be well advised to plan for such an eventuality by identifying and designing litigation, public advocacy, and political lobbying strategies in advance of the coming election.

Finally, it would be useful if the final PR100 Study included a breakdown, by scenario and system segment (transmission, distribution, generation, energy storage, access infrastructure, etc.), of (1) all the capital expenditures required to achieve the 100% goal by 2050 and (2) of potential financing sources for each of these expenditures. We also propose that COR3/LUMA or perhaps the DOE publicly disclose all relevant information regarding the allocation of approved federal funding.

Conclusion

The PR100 Summary appears to present a good preview of the findings of the PR100 Study. From the Summary it seems that the PR100 Study is a thorough and thoughtful analysis carried out by a respected group of stakeholders. It is a welcome contribution to the public debate and a valuable resource for those who analyze and study Puerto Rico’s electricity system.

In our view, these are some of the most important findings:

  • It is feasible to achieve the objective of 100% renewable energy generation in Puerto Rico by 2050 without using agricultural lands for developing utility-scale generation.
  • The 100% objective can be met using “mature” technologies such as utility-scale PV, distributed PV, and land-based wind (but see caveat regarding biodiesel fuel below).
  • Regardless of scenario, Puerto Rico needs to make significant investments in the T&D System and new generation capacity just to improve system stability and reliability in the immediate term.
  • There are significant tradeoffs between resilience (Scenario 2 and 3) and energy affordability (Scenario 1); between land use and energy affordability (“less land scenarios” tend to be more expensive); between meeting the 40% goal by 2025 and achieving acceptable grid reliability in the short-term; and between incurring short-term costs to obtain long-term benefits, depending on the scenario to be implemented.
  • In general, scenarios with higher deployment of DERs using less land tend to be, on average, more expensive than other scenarios, result in higher rates for the consumer, and induce greater short-term adverse effects on the Puerto Rican economy.
  • The existence of these tradeoffs raises the question of which agency or entity should be in charge of making these decisions. We strongly recommend that the PREB be in charge of making these decisions.
  • The levelized cost of electricity on average would be $79/MWh under the Less Land variant and $75/MWh under the More Land variant. A difference of $4/MWh, or 5.33%, which over some 25-odd years is quite significant.
  • Decisionmakers could be underestimating long-term electricity loads and should take into account this risk when planning for the long term.
  • The difference between the Mid case and the Stress case variants is quite significant, some 5,230 GWh by FY2051. This is a large margin of error and the uncertainty regarding this forecast should be taken into account when drafting the next IRP and PREPA’s Plan of Adjustment.
  • Given this level of uncertainty, we recommend that representatives of the DOE, the FOMB, Genera, LUMA, PREPA, and the PREB meet and seek agreement on a single set of forecasts out to 2050 and that the same projections be used for both the development of PREPA’s new IRP and in PREPA’s financial Plan of Adjustment that will be eventually certified by the federal court. It would be irrational to use one set of load forecasts for operational planning purposes (the IRP) and another for financial planning purposes (the Plan of Adjustment).
  • The DOE estimates that the current pace of utility-scale solar deployment is too slow to meet the 40% renewable energy goal by 2025.
  • According to the DOE, the optimal resource mix to meet the 100% objective includes generation from biodiesel engines. This appears to contradict the DOE’s prior finding that it is feasible to attain the 100% renewable generation goal using only “mature” technologies. However, we need additional information about the commercial viability of this fuel source, a list of potential suppliers, and a procurement analysis, among other things, to determine whether biodiesel is a good long-term option for Puerto Rico.
  • The economic cost of the transition to 100% renewable energy by 2050 is quite significant, regardless of the scenario.
  • According to the DOE, the all-in average retail rate would increase between 66% and 83% between 2020 and 2025 in 2021 dollars, depending on the scenario.
  • A rate increase of this magnitude would have severe, material adverse effects on the economy of Puerto Rico in the short term and is simply not economically feasible. It will be necessary to mitigate these negative effects, either through subsidies, an extension of the timeline for achieving the transition, a different technology mix, or through other policies.
  • The DOE estimates that the short-term impact of the transition on household income is negative, followed by a modest positive impact between 2025 and 2045, and then a significantly positive effect by 2050. We note that if household income decreases over the short term it is also highly probable that consumption expenditures, employment, and real GNP will decrease over the same period. However, we don’t have any information at this point regarding the magnitude of these additional short-term economic effects.
  • The PR100 Summary provides remarkably little information regarding the sources for financing the full transition to 100% renewable energy by 2050.
  • Finally, a Trump victory in November could put at risk funding not only for the modernization of the grid but for the entire reconstruction process. Puerto Rico would be well advised to plan for such an eventuality by identifying and designing litigation, public advocacy, and political lobbying strategies in advance of the 2024 election.

In addition, we find that more information is needed in the following areas:

  • Load Forecasts: we need more information about the methodology used by the DOE to forecast electricity demand over the long term in order to reach any conclusion regarding the reasonableness of its estimates. Specifically, we need to know whether the DOE estimated demand functions for commercial, industrial, and residential users; the price elasticities used and how they were calculated; and additional information regarding their energy efficiency estimates.
  • Biodiesel Fuels: We are not familiar with this technology and need more information before reaching any conclusions regarding the feasibility of its future use in Puerto Rico for the generation of electric power.
  • Economic Impact Analysis: We need more information regarding the economic impact of rate increases in the short term on GNP level, GNP growth, employment, income, and consumption expenditures in order to assess the economic feasibility of the different scenarios.
  • Total Capital Expenditures and Sources of Financing: it would be useful if the final PR100 Study included a breakdown, by scenario and system segment (transmission, distribution, generation, energy storage, access infrastructure, etc.), of (1) all the capital expenditures required to achieve the 100% goal by 2050 and (2) potential financing sources for each of these expenditures.

Analysis of PREPA Legacy Assets Public-Private Partnership Agreement

Analysis of PREPA Legacy Assets Public-Private Partnership Agreement

Published on March 15, 2023

Sergio portrait
Policy Director
DOWNLOAD
SHARE

Introduction

On January 24, 2023, the Puerto Rico Power Electric Authority (“PREPA” or the “Owner”), the Puerto Rico Public-Private Partnerships Authority (the “P3 Authority” or the “Administrator”), and Genera PR LLC (the “Operator” or “Genera”), executed the Puerto Rico Thermal Generation Facilities Operation and Maintenance Agreement (the “Generation O&M Agreement”) setting forth the terms and conditions pursuant to which the Operator will operate, maintain, and eventually decommission certain Legacy Generation Assets owned by PREPA.

The execution of the Generation O&M Agreement is the most recent step in the long-term transformation of the Puerto Rico electricity market. Some of the highlights of that transformation process are:

  • The enactment of Act 57 on May 17, 2014, creating the Puerto Rico Energy Commission (now the Puerto Rico Energy Bureau or the “PREB”) to regulate the electricity market in Puerto Rico, among other things;
  • The filing of a petition to restructure PREPA’s financial liabilities pursuant to Title III of the Puerto Rico Oversight, Management, and Economic Stability Act (“PROMESA”) in July 2017, a proceeding that is still pending resolution before the United States District Court for the District of Puerto Rico;
  • The enactment of Act 120 on June 21, 2018 to “establish a path for a more reliable, efficient, and low-cost electric system”;
  • The enactment of Act 17 of April 11, 2019 setting forth “the Puerto Rico Energy Public Policy”; and
  • The execution of the Transmission and Distribution Operation and Management Agreement (the “T&D O&M Agreement”) entered into on June 22, 2020, by and among PREPA, the Administrator, LUMA Energy LLC and LUMA Energy ServCo, LLC (collectively, the “T&D Operator” or “LUMA”), pursuant to which the T&D Operator “shall operate, maintain, and modernize PREPA’s transmission and distribution system (the “T&D System”).

This ten-year transformation process was prompted by PREPA’s failure to provide affordable, reliable, and efficient electric service to the people of Puerto Rico after decades of mismanagement, corruption, and non-compliance with applicable laws, regulations, and industry standards.

Indeed, according to the P3 Authority PREPA currently faces significant operational challenges, including in the following areas:

  • Safety — Since 2003, “PREPA’s safety performance has been more than five times worse that the industry average. Incident Rates for T&D and generation on an annual basis have ranged from 11.0 to 19.0, and averaged approximately 15.0; this compares to a U.S. average for public power [companies] of approximately 4.92.”[1]
  • Reliability — PREPA’s plants operate with Forced Outage Rates that are up to five times worse than the industry average and at low Equivalent Availability Factors, which increases “the likelihood of forced outages leading to an interruption of the delivery of electricity to customers. Indeed, some of these outages resulted in inadequate generation supply and significant loss of adequate power supply to meet customer demand.”[2]
  • Generation Resource Adequacy — Puerto Rico has inadequate supply resources to meet expected demand. In fact, “the load loss expectation for Puerto Rico for 2023 was calculated at 8.81 days per year, which is 88 times higher than the utility industry benchmark of 1 day in 10 years or 0.10 days per year. This means that there will be 8.81 days per year when demand will not be met by generation supply.”[3]
  • Environmental Compliance — PREPA’s record of environmental compliance has been deficient, not to say outright awful. Throughout its history it has failed to comply with the Clean Air Act, the Clean Water Act, the Mercury and Air Toxics Standards, and with several other air and water environmental rules and regulations. As a result, the “Legacy Generation Assets continue to operate at significantly lower capacity than their nameplate capacity and suffer from long-standing operational deficiencies and disrepair.”[4]
  • Corruption — PREPA has long been a source of private and public corruption in the island. PREPA’s suppliers, in many cases thanks to their political donations and influence, have benefited from contracts to provide goods and services to the public utility, sometimes at inflated, not to say borderline extortionate, prices. See, for example, the nefarious history of PREPA’s fuel and equipment procurement practices.[5]

It has become fashionable in certain circles of the self-described political avant-garde to claim that PREPA was once considered the “crown jewel” of Puerto Rico’s government (a particularly obnoxious figure of speech given our colonial history). A closer look at the historical record, though, reveals that for many years appointment to senior management positions at PREPA depended more on partisan politics than on personal merit. Technical and managerial decisions, in turn, were often subordinated to short-term political interests. PREPA survived for decades largely by postponing capital expenditures, delaying payment to suppliers, using accounting gimmicks to muddle its true financial condition, and by borrowing billions at relatively low, tax-exempt rates in the U.S. municipal bond markets, in many cases just to make the debt service on other maturing debt. That all these shenanigans eventually ended in a bankruptcy filing should not be surprising to anyone that was paying attention. Nonetheless, it is still difficult to think of other monopolies that have managed to bankrupt themselves, with the exception, perhaps, of the state-owned enterprises in the former Soviet Union.

Given all of the above, the incontrovertible conclusion is that PREPA simply cannot continue operating the way it has up until now. It has become a decrepit, some would say half-dead, zombie public utility that stifles economic activity in Puerto Rico. The time has come to take drastic action with respect to PREPA, as it has proven incapable of reforming itself and has been immune to the efforts of several administrations to modernize and improve its operations. Those who would infuse this moribund public corporation with the breath of new life bear the burden of proof to demonstrate by a preponderance of the evidence why that should be the case.

In this Policy Brief, we will present an analysis of the principal components of the Generation O&M Agreement, including the basic structure of the transaction; the compensation of the Operator (including any incentives and penalties provided for therein); the estimated savings to be generated as a result of hiring a private operator to operate and maintain the Legacy Generation Assets; the planned decommission of most of the existing facilities that currently use fossil fuels to generate electricity in Puerto Rico; and the resulting structure of Puerto Rico’s electricity market.

Structure of the Generation O&M Agreement

Genera is a wholly-owned subsidiary of New Fortress Energy (“NFE”). NFE, in turn, is “an integrated gas-to-power energy infrastructure company”, whose “business model spans the entire production and delivery chain from natural gas procurement and liquefaction to shipping, logistics, facilities and conversion or development of natural gas-fired power generation.”[6]

Genera is being hired by PREPA, as owner of the Legacy Generation Assets, to provide (either directly or through subcontractors) four classes of services, namely: (i) the Mobilization Services, (ii) the O&M Services commencing on the Service Commencement Date, (iii) the Decommissioning Services, and (iv) the Demobilization Services. In exchange for providing those services, the Operator is entitled to receive certain compensation, subject to any applicable Incentive Payments or Penalties, during the term of the Generation O&M Agreement, which is initially expected to last ten (10) years.

The Mobilization Services

The Operator is required to provide a specific set of services during the period between the Effective Date of the Generation O&M Agreement and the O&M Services Commencement Date, which is expected to be about 100 days after the Effective Date (the “Target Service Commencement Date”). The Mobilization Services, which are described in the Mobilization Plan outline set forth in Annex VII to the Generation O&M Agreement, are intended to “ensure an orderly transfer of the care, custody and control of the Legacy Generation Assets to Operator”.[7]

Those services include, among others, the evaluation and hiring of personnel; the hiring of subcontractors, if any; executing the tasks set forth in the Handover Checklist included in Annex VII; obtaining the requisite insurance; preparing a Procurement Manual; developing a Communications Plan; preparing a Fuel Optimization Plan, setting forth the Fuel Cost Savings Initiatives; and preparing a Federally Funded Generation Project Plan “listing and describing those projects proposed by Operator for priority in the receipt of any funding for the Legacy Generation Assets, received or to be received by or for the benefit of Owner from any U.S. federal agency.”[8]

During the Mobilization Period the Operator is entitled to be reimbursed for all reasonable costs and expenses (including the compensation of current employees of the Operator and any subcontractors) incurred during the course of providing the Mobilization Services, subject to a cap of $15 million. [9] If the Target Service Commencement Date is delayed by 90 days or more, except in the case of a Force Majeure Event or an event caused by Owner’s fault, then the Operator shall pay damages to PREPA in the amount of $1 million per week for each week the Target Service Commencement Date is further delayed, up to a maximum of $15 million.[10]

The O&M Services

Commencing on the Service Commencement Date, Operator shall (i) provide management, operation, maintenance, repair, restoration, replacement, and other related services for the Legacy Generation Assets, as well as any optimization procedures (including for improving fuel and efficiency) approved by the PREB, and (ii) establish policies, programs and procedures with respect thereto, to the extent not already established.[11]

The scope of the O&M Services is set forth in Annex IX to the Generation O&M Agreement. These services include, but are not limited to, the following:

(1) day-to-day operation and maintenance (including any major maintenance) services, including operation of the Legacy Generation Assets to generate electricity and deliver it into the T&D System;

(2) identifying, justifying and managing any required maintenance capital expenditures;

(3) providing routine inspections of the Legacy Generation Assets;

(4) providing annual operating tests (the Annual Performance Test) of the Legacy Generation Assets in coordination with T&D Operator;

(5) establishing appropriate and customary safety work rules and practices;

(6) developing an operation and maintenance training program;

(7) provisioning, storing and maintaining the inventory of spare and consumable parts, including Capital Spare Parts, for the Legacy Generation Assets;

(8) establishing and maintaining a computerized maintenance management system for the Legacy Generation Assets;

(9) performing scheduled and emergency maintenance, repair and replacement of equipment, including any balance of plant equipment, painting, and cleaning, among others;

(10) managing Planned Outages, Unplanned Outages and Forced Outages and restoration of power supply to the transmission grid;

(11) coordinating business continuity and emergency planning and storm restoration and recovery in coordination with T&D Operator;

(12) procuring and managing water or auxiliary power supply, as applicable;

(13) maintaining and repairing fuel and water systems, including tanks, pumps, filters, and piping, as required;

(14) procuring and managing the delivery and quality testing of fuel;

(15) liaising with the T&D Operator or any of their assignees or successors regarding dispatch, dispatch planning and related T&D system matters and providing required information;

(16) interfacing with and providing reports to regulators including PREB and with environmental compliance agencies such as the EPA, the Puerto Rico Department of Natural and Environmental Resources, the Occupational Safety and Health Administration and others, as may be required;

(17) obtaining, complying with and maintaining licenses, permits, consents and the Consent Decree, as necessary;

(18) providing periodic reports regarding programmed and non-programmed operations, maintenance, repairs, services and modifications performed and to be performed;

(19) preparing for and assisting in, or subcontracting for and overseeing, the decommissioning of the relevant plants as outlined in the Integrated Resource Plan (including any future integrated resource plans) in coordination with PREPA/the T&D Operator, Owner and PREB;

(20) participating in emergency planning and drills led by the T&D Operator, as needed;

(21) conducting emergency planning and drills independent of T&D Operator;

(22) assisting with the transition of the plants to third parties or to new uses (synchronous condensers, etc.) to the extent certain of the plants are removed from the O&M Agreement; and

(23) developing and maintaining a good neighbor program.[12]

Genera has already stated it will make extensive use of subcontractors to perform the O&M Services; specifically it intends to hire the PIC Group, “a global power and energy service provider”, and Black & Veatch, “an engineering, procurement, and consulting construction firm”.

Compensation for the O&M Services

Pass-Through Expenditures — The Operator shall be reimbursed for any reasonable and documented costs and expenses incurred by the Operator in connection with the performance of its obligations pursuant to the Generation O&M Agreement, including employee compensation, the cost of all subcontracted and seconded employees, the cost of professional services, insurance premiums, any taxes owed to the Commonwealth or any municipality, and fuel costs, among other costs and expenditures set forth in Annex XII to the Generation O&M Agreement.

However, Pass Through Expenditures do not include Disallowed Costs, as such term is defined in Section 7.7(a) of the Generation O&M Agreement, including but not limited to, any costs incurred as a consequence of the Operator’s gross negligence or willful misconduct; any fines or penalties imposed on the Operator by a governmental body; any expenditures in excess of the approved Operating Budget then in effect; or Operator Overhead costs which are included in the applicable Service Fee.[13]

O&M Fixed Fee — In addition, in exchange for providing the O&M Services, the Operator is entitled to receive an annual O&M Fixed Fee in the amount of $22.5 million, adjusted for inflation (subject to a 3% annual cap), during the term of the Generation O&M Agreement.[14]

Adjustments to the O&M Fixed Fee Upon Decommissioning of Assets — Commencing in contract year 6, the O&M Fixed Fee shall be gradually reduced to take into account the decommissioning of generation assets, subject to a $5 million floor. The amount of this reduction is calculated pursuant to a formula set forth in Section I.B. of Annex II to the Generation O&M Agreement. Incentive Payments and Penalties are also adjusted on a pro-rata basis as the O&M Fee is gradually adjusted to account for the decommissioning of the Legacy Generation Assets.

O&M Services Incentives and Penalties — During each contract year the Operator is (i) eligible to receive additional financial compensation in the form of an Incentive Payment and (ii) subject to the payment of potential Penalties, in each case based on the Operator’s performance in providing the O&M Services. For each contract year the aggregate amount of any Incentive Payments minus any Penalties shall not exceed $100,000,000, provided, however, that any excess over that amount carries over to the next contract year.[15] An amount equal to the maximum amount of the Incentive Payments available in any given Contract Year shall be included in the Operating Budget for that year. If any Penalties are determined to be due, then in accordance with Section 7.1(c)(v) of the Generation O&M Agreement, PREPA shall deduct the Penalty from the next payment of the applicable Service Fee due to the Operator following such determination.

The Operator’s performance of the O&M Services will be evaluated in six categories: (1) Operation Cost Efficiency, (2) Equivalent Availability Factor (“EAF”), (3) Safety Compliance, (4) Environmental Compliance, (5) Reporting Obligations and (6) Fuel Savings, as set forth in Section III.B of Annex II to the Generation O&M Agreement.

  1. Operation Cost Efficiency — The Operator’s cost efficiency will be measured using the applicable Operating Budget as the benchmark. Operator shall receive an O&M Incentive Payment based on a percentage of the total amount of cost savings achieved by the Operator in the delivery of the O&M Services, if any, as compared to the approved Operating Budget. The measurement parameter for this Incentive Payment consists of actual expenditures incurred as a percentage (%) of the approved Operating Budget, where actual savings equal the Operating Budget minus actual expenditures. The table below sets forth the criteria for payment:


Source: Section III.B.1. of Annex II to the Generation O&M Agreement

  1. Equivalent Availability Factor — In general, the availability factor of a power plant is the amount of time that it is able to produce electricity over a certain period, divided by the amount of the time in the period. For purposes of the Generation O&M Agreement, the term Equivalent Availability Factor (“EAF”) is defined as:

EAF = (AH-EPDH-EUDH) x 100 %
PH

where:

    • AH = Available Hours
    • EPDH= Equivalent Planned Derated Hours
    • EUDH = Equivalent Unplanned Derated Hours
    • PH = Period Hours or number of hours that the Legacy Generation Asset was in active state

For every contract year, the target EAF will be calculated for each baseload and peaking unit pursuant to an annual performance test to be carried out pursuant to Section 5.22 of the Generation O&M Agreement.[16] Incentive Payments or Penalties, as the case may be, will be calculated in accordance with the criteria set forth below.

For Baseload Units:


Source: Section III.B.2. of Annex II to the Generation O&M Agreement

For Peaking Units:


Source: Section III.B.2. of Annex II to the Generation O&M Agreement

The Minimum Performance Threshold for the annual EAF for the applicable Baseload Units and for the Peaking Units shall be established pursuant to Section 5.22 of the Generation O&M Agreement. Failure by the Operator to achieve either Minimum Performance Threshold in two (2) consecutive Contract Years shall trigger a Minimum Performance Threshold Default pursuant to Section 14.1(l) of the Generation O&M Agreement.[17]

  1. Safety Compliance — Operator shall receive an Incentive Payment or be subject to a Penalty based on its performance for each contract year with respect to the safety compliance targets described below.

OSHA Lost Time Incidents (“LTI”):


Source: Section III.B.3. of Annex II to the Generation O&M Agreement

OSHA Recordable Injury or Illness (“I&I”):


Source: Section III.B.3. of Annex II to the Generation O&M Agreement

OSHA Fatality or Severe Injury:


Source: Section III.B.3. of Annex II to the Generation O&M Agreement

For each contract year, the maximum aggregate Penalty that the Operator may incur shall be US$100,000, in each case with respect to the parameters of the Safety Compliance category. The payment of penalties by Operator on any of the safety compliance measurement parameters in two (2) consecutive Contract Years shall trigger a Minimum Performance Threshold Default pursuant to Section 14.1(l) of the Generation O&M Agreement.

  1. Environmental Compliance — The Operator shall receive an Incentive Payment or be subject to a Penalty based on its performance with respect to the environmental targets described below.

Violation of Consent Decrees and/or Notice of Violations (NOVs):


Source: Section III.B.4. of Annex II to the Generation O&M Agreement

For each contract year, the maximum aggregate Penalty that the Operator may incur shall be US$100,000, in each case with respect to the parameters of the Environmental Compliance category. The payment of a Penalty by Operator under the Environmental Compliance category for two (2) consecutive contract years shall trigger a Minimum Performance Threshold Default pursuant to Section 14.1(l) of the Generation O&M Agreement.

  1. Reporting Obligations — Operator shall be subject to a charge based on its timeliness in responding to a reasonable request for information from the Administrator. For every fifteen (15) sequential days during which the Operator fails to provide a response to Administrator, Operator shall pay a penalty of US$100,000, up to a maximum aggregate of $1 million for each contract year.[18]
  2. Fuel Optimization — Operator shall receive a “Fuel Optimization Payment” of fifty percent (50%) of any Actual Fuel Savings achieved during the relevant contract year.[19] For the purpose determining Actual Fuel Savings and the corresponding Fuel Optimization Payment for any contract year that commences after one or more Fuel Cost Savings Initiatives have been implemented or are otherwise already accounted for in the relevant Budget, the Budgets for such contract year(s) shall include an addendum setting forth hypothetical budget allocations for the Fuel Costs that would be incurred in the absence of the Fuel Cost Savings Initiatives.[20] The detailed methodologies to be used to calculate Actual Fuel Savings and any Fuel Optimization Payment shall be included in the Fuel Optimization Plan to be developed during the Mobilization Period.

Decommissioning Services

In general, the Decommissioning Services are services provided pursuant to the Generation O&M Agreement to complete the dismantlement and removal of the structures comprising PREPA’s Legacy Generation Assets, and all other activities indispensable for the retirement, dismantlement, decontamination or storage of the legacy generation assets.

At any point after the Service Commencement Date, the Administrator may deliver to the Operator a decommissioning notice to commence the Decommissioning Services for one or more of the Legacy Generation Assets. In addition, in the event that the Operator determines that all or a portion of a Legacy Generation Asset cannot continue to be safely operated and maintained, the Operator may deliver to the Administrator and the PREB a request to commence Decommissioning Services for the applicable Legacy Generation Asset.[21]

Once the parties agree that a Legacy Generation Asset or Assets will be decommissioned, then the Operator shall prepare a Decommissioning Plan consistent with the Decommissioning Plan outline set forth in Annex XV to the Generation O&M Agreement.

The Decommissioning Plan shall provide for:

  • the permitting, demolition, decontamination, waste disposal and dismantling/or preparation for conversion to such other future use as the Administrator and the PREB may designate, as applicable, of the Legacy Generation Asset, and waste disposal, for achievement of end-state conditions within a prescribed time;
  • the development of the Decommissioning Budget, as set forth in Section 16.2 of the Generation O&M Agreement;
  • reasonably acceptable arrangements to facilitate the transition of the Operator employees, into new jobs or industries, including a training and/or severance plan (to be funded by the Owner) for any Operator Employees not hired into a successor job or industry; and
  • a timeline setting forth when Decommissioning Services shall be provided, including the date on which the Decommissioning Services shall commence and the date on which the Decommissioning Services for such legacy generation asset shall be completed.[22]

Compensation for Decommissioning Services

Once an asset has been selected for decommissioning the parties have to agree on the Decommissioning Budget for that asset. The Decommissioning Budget, subject to the approval of the Administrator and in certain cases the PREB, will include all the Pass-Through Expenditures the Operator expects to incur in connection with the decommissioning process.

The Owner then will pay the Operator all Pass-Through Expenditures required to perform the Decommissioning Services and shall continue to pay the O&M Fixed Fee in full (subject to any applicable adjustments) for the duration of the term of the Generation O&M Agreement.

The Operator could earn an Incentive Payment or incur a Penalty based on the Operator’s performance of the Decommissioning Services.[23]

Decommissioning Services Incentives and Penalties — The Operator’s performance of the Decommissioning Services will be evaluated in the category of Operation Cost Efficiency. Upon completion of the Decommissioning Services with respect to any decommissioned legacy asset:

  • If (i) the Operator’s actual expenditures are consistent with or exceed the estimates included in the applicable Decommissioning Budget and (ii) the Operator successfully completes the applicable Decommissioning Services on or before the relevant Decommissioning Completion Date, no Incentive Payment shall be applicable.
  • If (i) the Operator’s actual expenditures are below the estimates included in the applicable Decommissioning Budget and (ii) the Operator successfully completes the applicable Decommissioning Services on or before the relevant Decommissioning Completion Date, the Operator shall be eligible to receive a Decommissioning Incentive Payment consisting of a percentage of the actual cost reduction as compared to the estimates included in the applicable Decommissioning Budget.[24]

The performance of the Operator in executing the Decommissioning Services will be measured by calculating the actual expenditures as a percentage (%) of the approved Decommissioning Budget, where actual savings equal the Decommissioning Budget minus actual expenditures, as set forth in the table below:


Source: Section III.C.1. of Annex II to the Generation O&M Agreement

  • If the Decommissioning Services with respect to a Legacy Generation Asset are not completed by the applicable Decommissioning Completion Date, then Operator shall be subject to a Decommissioning Penalty consisting of one million dollars ($1,000,000) for each week by which the completion of the Decommissioning Services is delayed past the applicable Decommissioning Completion Date, up to a maximum of fifteen million dollars ($15,000,000) in the aggregate across all Legacy Generation Assets and Generation Sites.[25]
  • In the event the Operator (i) exceeds the costs and expenses included in the applicable Decommissioning Budget and/or (ii) fails to complete the Decommissioning Services before the Decommissioning Completion Date for any two (2) Legacy Generation Assets, the Administrator may, in its sole discretion, engage an independent third party to perform any future Decommissioning Services with respect to any Legacy Generation Assets without either Party incurring, or becoming liable for, the payment of any penalty, premium or termination fee.

Demobilization Services

The Operator shall provide certain Demobilization Services upon the expiration or early termination of the Generation O&M Agreement to ensure the orderly transfer of any remaining Legacy Generation Asset from the Operator to the Owner or to a successor operator. The Operator has agreed to perform the Demobilization Services in accordance with a Demobilization Plan to be developed in accordance with the requirements set forth in Annex XVI to the Generation O&M Agreement.

In general, “the Demobilization Plan shall enable the seamless, safe, and effective transfer of the Legacy Generation Assets to the Owner, the Administrator, or their successor operator. The Operator’s principal objective shall be to complete any demobilization activities in the time frame and on the terms that are most suitable to Owner and Administrator in a way that will achieve an orderly handover or return of the Legacy Generation Assets.”[26]

Compensation for the Demobilization Services

During the Demobilization Period, which is estimated to last about a year, the Operator is entitled to receive a “Demobilization Service Fee”. The Demobilization Service Fee shall be an aggregate amount equal to:

  • the hourly fully allocated cost rate for each category of Operator employee or Affiliate personnel providing Demobilization Services multiplied by
  • the number of hours worked by each Operator employee or Affiliate personnel in such category providing Demobilization Services, plus
  • ten percent (10%) of the product of (i) and (ii), plus
  • all other reasonable and documented costs and expenses incurred by Operator (without markup for Operator profit) that are necessary and reasonable in the course of providing the Demobilization Services and/or implementing the Demobilization Plan, including the cost of any Subcontractors providing Demobilization Services.[27]

Expected Savings

As we have seen above, the Generation O&M Agreement contains a fairly well-developed set of incentives, penalties, and performance metrics to evaluate the performance of the Operator. In this sense, the Generation O&M Agreement is an improvement over the T&D O&M Agreement.

Indeed, the inclusion of measurable benchmarks, the requirement to engage in good faith negotiations with current PREPA employees, the cap on the fees that the Operator can earn during the Mobilization Period, and other requirements set forth in the Scope of O&M Services, for example the obligation to develop a fully fleshed out communications plan prior to the handover of operations to the Operator, demonstrates that governments can and indeed do learn from prior experiences, notwithstanding what anti-government zealots may say or think to the contrary.

Having said that, though, the fact remains that executing and entering into the Generation O&M Agreement makes sense only if the expected savings to be generated exceed the expected costs of the agreement. The government of Puerto Rico has stated that it expects to generate “significant savings” from transferring the operation and management of the Legacy Generation Assets to Genera. However, the evidence it offers to back up that assertion is rather thin, as we will demonstrate below.

The P3 Authority hired FTI Consulting (“FTI”) to carry out an analysis of the expected benefits of selecting a third party operator for the Legacy Generation Assets. FTI set forth its findings in a report (the “FTI Report”) that is included as Exhibit B to the P3 Report, which the P3 Authority is statutorily required to prepare and publish in connection with the execution of any public-private partnership transaction.

According to the FTI Report:

  • Genera estimates achievable O&M savings of $19 million per year, mostly from labor and more efficient maintenance activities.
  • Genera also estimates fuel savings (without plant conversions or equipment replacement) of approximately $85 million per year, “which would come from optimizing existing fuel contracts” ($56 million), “achieving better risk and credit terms on the existing oil contracts” ($20 million), and “making operational changes at the Legacy Generation Assets to increase fuel efficiency” ($9 million).
  • Genera also “believes” that, subject to PREB approval, “there are additional fuel savings”, in excess of $100 million, “achievable through fuel conversion of units”…These “conversions would involve commissioning of gas fuel operation for units that are dual fuel capable or conversions of units that are able to be converted.”
  • The “combined estimated savings from O&M and fuel range from $100 million to $200 million annually (including conversion savings if approved by PREB).” Under the terms of the Generation O&M Agreement those “savings would be shared 50%/50% between Genera and the electric ratepayers of Puerto Rico. That would result in $50 million to $100 million per year to Puerto Rico electric system customers.”
  • In sum, concludes FTI, “Puerto Rico is guaranteed a benefit and Genera’s incentive compensation pays for itself. Given the low fixed fee, high incentive fee component and the 50%/50% sharing of [the savings], Genera is more than motivated to perform and operate the plants well and as fuel-efficiently as possible.”[28]

So, according to FTI’s analysis this transaction is a clear win-win situation and everybody will live happily ever after the Effective Date. Pardon our skepticism, but it seems to us that FTI is being too clever by half, as the British would say.

First, FTI relies on representations made by Genera to the Partnership Committee and the P3 Authority and their advisors. There is no indication, at least in the text of the FTI Report, that FTI carried out an independent evaluation or executed any standalone due diligence to validate or verify Genera’s claims of expected savings.

Second, even if it is arguably reasonable to take Genera’s representations at face value, FTI should have requested that Genera provide the documentation of the methodology it used to calculate those expected savings. However, the FTI Report includes no explanation of the assumptions, the methodology used, or the variables analyzed by Genera to estimate expected savings. The people of Puerto Rico, in essence, are being asked to believe these ostensible savings on faith alone.

Third, Puerto Rico is a “price taker” in the global oil and natural gas markets due to the relatively small volume of fuel it buys. And while we don’t doubt the negotiating acumen of NFE’s traders, there are limits to how much savings can be generated from obtaining “better risk credit and credit terms”. Even NFE’s most perspicacious traders are subject to the capricious ebbs and flows of the global oil and natural gas markets.

In this context, it is relevant to point out that Section 9.2(b) of the Generation O&M Agreement politely prohibits Genera, NFE, and their affiliates from engaging in business with any person located, organized, or resident in a Sanctioned Country, which is defined in Section 20.2(g)(iv) of the Generation O&M Agreement as “the Crimea (sic), Cuba, Iran, North Korea and Syria.” We note, though, that Russia is conspicuously absent from this list. This omission, we assume, is probably nothing more than just a harmless drafting lapse that obviously will be remedied by counsel in due course.

Fourth, Genera insists on pointing to potential savings to be extracted from the conversion of existing oil-burning plants to facilities that burn natural gas. In fact, according to the FTI report, such conversions would generate approximately 50% of total expected savings from the Generation O&M Agreement. Genera and FTI, however, are silent as to who would pay for the capital expenditures necessary to convert existing oil-burning units to burn natural gas.

To be sure, pursuant to Section 5.6(b) of the Generation O&M Agreement Genera may “propose to PREB certain capital improvements, taking into account the Integrated Resource Plan and the Federally Funded Generation Project Plan, that would be (x) federally funded and owned by Owner, (y) made, owned and funded by Owner or (z) made, owned and funded by Operator or its designated Affiliate.” However, Genera and FTI fail to disclose, in the case of capital improvements not financed by the federal government, (i) how the profile of expected savings is affected once the expected cost of capital is taken into account and (ii) how the expected useful life of a legacy asset converted to burn natural gas would be extended in order to amortize the capital expenditure over time — an extension that, presumably, would be in contravention of the stated objective of decommissioning most of the Legacy Generation Assets as soon as possible.

Furthermore, Genera, as we stated above, is a wholly-owned subsidiary of NFE, which is a “full service” natural gas company that operates along the entire supply chain, from procurement, to shipping, to the development of natural gas-fired power generation. This presents at least two conflicts of interest.

First, it would be only natural for Genera to seek to do business with its parent company or its affiliates and there will be pressure to accept whatever terms are imposed by the “friends of the house.”

To be fair, the Generation O&M Agreement sets forth in Annex VI a fully developed policy to address organizational conflicts of interest arising from or in connection with affiliate or related-party transactions, including the requirement to hire a third party to execute the procurement process in certain cases (yet more evidence that governments do learn). It remains to be seen, though, whether this process will be thoroughly and consistently implemented and enforced throughout the term of the Generation O&M Agreement.

The other conflict arises from the fact that Fuel Cost Savings Initiatives is defined in the Generation O&M Agreement to mean any initiatives undertaken by the Operator, its Affiliates or Subcontractors in connection with the Generation O&M Agreement, that reduce Fuel Costs, including by:

  • improving the fuel efficiency of any Legacy Generation Assets;
  • converting any Legacy Generation Assets to be able to operate on any new alternative fuel(s) (including natural gas and hydrogen);
  • supplementing Legacy Generation Assets with power generation equipment at or in the vicinity of the relevant Generation Site that is more fuel efficient and/or operates on any new alternative fuel(s) (including natural gas and hydrogen);
  • reducing transportation, testing, delivery or storage (including tank maintenance) costs; or
  • pursuing savings opportunities related to credit and portfolio optimization, in each case whether such initiatives are implemented as Pass-Through Expenditures, at the Operator’s cost as the Operator’s own capital improvements pursuant to Section 5.6(b), by replacement or renegotiation of Fuel Contracts or Facility Contracts, or otherwise.

This definition poses several problems. First, it clearly allows the conversion of oil burning units to burn natural gas as a cost-saving initiative (subject to PREB approval), which would be contrary to the stated public policy goal of fully transitioning to renewable fuels by 2050.

Second, by allowing the switch to natural gas as a fuel cost saving measure, the Generation O&M Agreement confronts Genera with a set of potentially incompatible incentives. On one hand, Genera gets to keep 50% of any fuel savings generated by its implementation of any Fuel Cost Savings Initiative. On the other hand, Genera keeps 50% of any savings it generates when the process for decommissioning a legacy asset ends up costing less than originally budgeted.

In most, if not all instances, the amount of money represented by the right to get paid 50% of any realized fuel cost savings will exceed the amount of money represented by the right to get paid 50% of the savings generated from successfully decommissioning a legacy asset 10 or 15% under budget. Thus, Genera probably will have a strong preference for projects that switch generation units to burning natural gas, especially if the fuel is provided by NFE or any of its affiliates , and against decommissioning assets that could be converted to burn natural gas. It will be up to the P3 Authority and the PREB to prevent this risk from becoming a reality.

Third, the definition of Fuel Cost Savings Initiatives also includes any savings generated by switching to the burning of hydrogen. Now, this is interesting because NFE stated in its annual report for the year ended December 31, 2021 “that low-cost hydrogen will play an increasingly significant role as a carbon-free fuel to support renewables and displace fossil fuels across power, transportation and industrial markets.”

To that end, NFE has formed a new division, which it calls Zero, “to evaluate promising technologies and pursue initiatives that will position us to capitalize on this emerging industry.” In addition, it has signed an agreement “to transition a power plant to be capable of burning 100% green hydrogen over the next decade”, and it has made its “first hydrogen-related investment in H2Pro, an Israel-based company developing a novel, efficient, and low-cost green hydrogen production technology.”[29]


Source: Michael Kobina and Stephanie Gil, Green Hydrogen: A key investment for the energy transition, World Bank Blogs, June 23, 2022

However, true green hydrogen production, which consists of using renewably generated electricity to split water molecules into hydrogen and oxygen (see chart above), is not yet a commercially viable technology. Most of the current hydrogen production in the world consists of so-called “gray hydrogen”, which is produced by splitting natural gas into carbon dioxide and hydrogen. This process is energy intensive and emits a significant amount of CO2. “Blue” hydrogen is sometimes presented as an alternative. The process for making blue hydrogen is the same as the one for making gray hydrogen, with the difference that the resultant CO2 is “captured” and stored underground and thus is not released into the atmosphere. Most environmental groups, however, are skeptical about the alleged benefits of producing gray or blue hydrogen.

The risk for Puerto Rico here is twofold. First, we have to be vigilant that the island is not used once again as a “laboratory” for testing some half-baked harebrained idea, the brainchild of some demented trafficker of high-tech scams out on the prowl to make a quick buck in the crumbling colonial backwaters of the American Empire, and which imposes high costs and produces little or no benefits for Puerto Rico’s residents — as has happened so often in our history.[30]

And, second, if the production of green hydrogen eventually becomes commercially feasible, we have to ensure that both the technology and the know-how is transferred to Puerto Rican firms and engineers so the island does not end depending yet again on a resource we do not produce and do not control to generate our energy.

Finally, even if it is true that the implementation of the Generation O&M Agreement generates savings of $200 million per year and half of that amount is passed on to Puerto Rican ratepayers, is that amount “significant”? According to an unaudited financial report prepared by PREPA’s management for its governing board, it spent approximately $2.1 billion on fuel during fiscal year 2022, while total expenses for that year added up to $4 billion.[31] Therefore, savings of $100 million are equivalent to 4.7% of fuel expense and 2.5% of total expenses for that period.

Those savings are worth something but they do not by any means represent a paradigm-shattering change. To put this issue in perspective, the amount of expected savings ($100 million) probably will not be enough to fully offset the debt service on PREPA’s restructured bonds, which is estimated will be around $300 million per year, depending on the details of the final deal to be entered into with bondholders under the aegis of the Title III court.[32]

The objective truth is that Puerto Rico’s electricity costs will not decrease significantly until most of PREPA’s Legacy Generation Assets are decommissioned and replaced with new generation capacity using renewable sources. According to PREPA’s Certified Fiscal Plan for Fiscal Year 2022 generation “expenses are projected to decline over the Certified Fiscal Plan period as PREPA-owned generation units are retired, and the mix shifts to third-party owned generation, specifically renewable generation, which will be contracted through PPAs”.[33] Interestingly, neither the P3 Report nor the FTI Report provide an estimate of those savings.

Numerous factors have contributed to delaying the transition to and deployment of renewable generation in Puerto Rico: PREPA’s bankruptcy; lack of access to capital; federal and state bureaucratic requirements; the loss of state capacity to perform complex tasks due to years of austerity policies; the political influence of groups with fossil fuel interests; disagreements among advocates for renewable power who favor building utility-scale capacity and those who propose rooftop-based solar systems (we need both); and a general lack of coordination among and between government agencies, private sector stakeholders, local and community leaders, representatives of NGOs, and other non-profit entities which promote their own projects in a zero-sum fashion.

To be fair, we should not underestimate the difficulty and complexity of decommissioning fossil fuel generation while simultaneously deploying large scale renewable generation. As shown in the chart below, which is from PREPA’s Management Presentation to participants in the RFP process for awarding the Generation O&M Agreement, the scale of the transition to renewable generation is enormous. And while the timeline needs to be updated, it does makes us wonder whether the government of Puerto Rico has the requisite state capacity to execute this mega-project on time, on budget, and delivering the estimated benefits.


Source: Exhibit E to the P3 Report, p. 19.

Finally, we note that this “potential transition road map” prepared by PREPA includes the addition of up to 400 MW of new combined cycle capacity using natural gas in the San Juan plant, presumably to be paid by the federal government, and forecasts the continued used of legacy assets in Cambalache, Mayaguez, and Palo Seco beyond 2028.

Market Structure

Act 17-2019 calls for “transitioning from the current, vertically integrated monopoly comprising PREPA, to an energy system with multiple players as well as changes to the roles and responsibilities that have historically been concentrated within PREPA, and their reallocation across multiple entities.” According to that Act, one of the objectives of unbundling PREPA’s vertically integrated monopoly is to introduce an element of competition into Puerto Rico’s electricity market. To that end, according to the P3 Report, the Legacy Generation Assets Project is “intended to ‘promote market competition’ by harnessing private sector creativity and resources to help fully deliver on economic, infrastructure, and societal goals identified by the Government.”[34]

At first glance it appears that the execution of the T&D O&M Agreement and the Generation O&M Agreement satisfies the basic requirements of Act 17. While PREPA retains the naked title to the transmission and distribution system and to the legacy generation assets (for purposes of qualifying for federal funding), their respective day to day operation and management have been unbundled and legally transferred to two private operators.


Source: Exhibit E to the P3 Report, p. 8.

However, a closer look at the structure of Puerto Rico’s electric power market after the execution of the T&D and the Generation agreement makes us wonder whether it achieves the policy objectives set forth in Act 17.

First, as shown in the chart above, after the Service Commencement Date of the Generation O&M Agreement, Puerto Rico would have an oligopoly of utility-scale generation companies: Genera, AES, EcoEléctrica, various renewable generators, and whatever new renewable generation is eventually deployed. On oligopoly can be defined as “an economic condition where only a few companies sell substantially similar or standardized products” and “oligopoly markets often exhibit the lack of competition, high prices and low output of monopoly markets.”[35]In oligopolistic markets, prices tend to be set by the firm with the largest market share. In the instant case, the generation market in Puerto Rico will be dominated, at least during the next five years, by Genera which will be operating the most inefficient, and hence the most costly, generation fleet in the island. Thus, we can expect the transfer of the operation and management of PREPA’s generation assets to have only a marginal, if any, effect on prices and reliability, at least in the medium-term.

Second, those oligopoly producers can sell their product (electricity) only to LUMA. Therefore, LUMA will have a monopsony with respect to independent power producers in Puerto Rico. A monopsony can be defined as “a market condition in which there is but one buyer for a particular commodity.”[36]Monopsonies can result in lower wages for workers, lower quality products, and higher prices for the consumer. Now, LUMA would probably argue that these risks are mitigated because they are required to buy power from independent power producers that have long-standing power purchase agreements (“PPAs”) with PREPA, in the case of AES and EcoElectrica, or that will be negotiated in the future, in the case of new entrants to the market. In any event, LUMA would argue, everything is subject to regulation by the PREB. That is true up to a point and good as far as it goes, but the situation could still lead to any number of market failures. For example, if a corporate affiliate of LUMA or Genera, or of their respective parent companies, wins the bid to build and operate the new combined cycle units (up to 400 MW) that will be located in the San Juan plant, what’s to stop LUMA or Genera from granting priority to their affiliate in connecting and dispatching electricity to T&D System?

Third, to complicate matters even further, LUMA has a monopoly on the other side of the market, namely the sale of electricity to retail, commercial, and industrial clients. Consumers in Puerto Rico can only buy electricity from LUMA, unless they set up their own generation capacity (in which case they can sell any excess generation, if they have net metering capabilities, only to LUMA).

While it is true that Puerto Rico has developed regulations to allow “wheeling” (the direct sale of excess electricity generated by say a manufacturing firm with in-house industrial scale generation to another industrial client), to our knowledge there has been little no wheeling sales executed in Puerto Rico. A single company, therefore, exercises de facto control of both sides of the electricity market in Puerto Rico: generators can sell and buyers can buy electricity only from LUMA. We question whether that result was intended by the drafters of Act 17.

Given this complicated market structure, any element of market competition will be promoted only indirectly if and when the time comes to renegotiate existing, or to negotiate any prospective, power purchase agreements between LUMA and independent power producers. We note that neither the P3 Report nor the FTI Report analyze whether competition prompted by the new market structure for the electricity sector in Puerto Rico would generate lower prices for ratepayers in the island.

In sum, the resulting market structure is fertile ground for any number of anticompetitive practices, such as collusion, price fixing, exclusive dealing, and price discrimination, among others, to arise. To prevent LUMA from unduly exercising its market power it will be necessary (1) to closely supervise the implementation of the T&D O&M Agreement; (2) for the PREB to conduct robust regulatory oversight of LUMA; (3) to establish a well-regulated and orderly wheeling market in Puerto Rico; and (4) to consider creating an independent system operator that would be in charge of managing the economic dispatch of generation units and supervising interconnections with the T&D System.

Buy Local Provisions

A novel feature (for Puerto Rico) of the Generation O&M Agreement is that it requires Genera to use “commercially reasonable” efforts to ensure that local companies, or foreign companies with a significant presence in Puerto Rico, are included in the procurement process for materials and services under the agreement.[37] In addition, the Generation O&M Agreement requires Genera to use “commercially reasonable” efforts to select companies established under the Commonwealth of Puerto Rico or companies that have “a significant presence in the Commonwealth of Puerto Rico” as material subcontractors.[38] These provisions, if implemented, have the potential to generate local economic activity and allow local firms and workers to obtain valuable experience working on a complex multi-year project.

Conclusion

Shakespeare’s words to the effect that “the web of our life is of a mingled yarn, good and ill together”, are perhaps an apt description of the Generation O&M Agreement.[39]

Several elements of the new agreement are clearly superior to the LUMA T&D O&M Agreement. Among these we can mention a well-developed system of incentives and penalties to motivate the Operator; the inclusion of clear benchmarks to measure Genera’s performance; stronger filters to analyze transactions with affiliates and related-parties, including a fully fleshed-out policy to address organizational conflicts of interest; the requirement to engage in good faith negotiations with current PREPA employees so as to minimize the learning curve of the new operator; and setting a cap on the fees that the Operator can earn during the Mobilization Period; all point to the conclusion that this is an agreement that offers better protections to the people of Puerto Rico from some of the foreseeable risks associated with this transaction.

Other aspects of the agreement are not as good. For example, most of the services will be provided by subcontractors (wouldn’t it be more efficient just to contract directly with them?); the analysis of the expected savings is clearly deficient and we would like to see a more rigorous examination of those professed savings; and it is not clear to us that the resultant market structure will lead to lower prices, generate allocative efficiencies, and/or produce significant increases in consumer welfare.

So, relative to the status quo, is the post-Genera electricity market in better shape in Puerto Rico? Probably yes, but that is an awfully low bar. Everybody who has objectively analyzed PREPA’s performance over the last 30 or 40 years has concluded that it is mess, the financial and operational equivalent of a long-smoldering dumpster fire. By that standard, trying anything new, no matter how outlandish it may seem, would probably constitute progress.

However, if we set a higher bar, if we ask whether this transaction will really help Puerto Rico achieve its long-standing goals of generating affordable, cleaner, and reliable electricity, then the answer is not quite as clear, for the good is indeed mingled with the ill. The fact is that there is a lot uncertainty surrounding this transaction and it is hard to avoid the unsettling feeling we are being presented with a fait-accompli on a take it or leave it basis.

Maintaining the status quo, though, is not an option. The real question is whether there is a better alternative to a negotiated agreement in this instance. The answer, when taking into account the totality of the circumstances, appears to be no. The available alternatives seem to be (1) worse, for example, resuscitating PREPA; (2) unrealistic, entailing, for instance, the creation of a new Tennessee Valley Authority-like entity to provide electricity in Puerto Rico; or (3) downright utopian, involving extremist schemes reminiscent of Mao’s Great Leap Forward.[40]

After assessing the risks and benefits of the Generation O&M Agreement we face a dilemma in the classical sense of making a decision with no good options. But in a situation with no objectively good options, taking a calculated risk may, perhaps, be the best option. Again, in the words of the Bard of Avon: “there is a tide in the affairs of men which, taken at the flood, leads on to fortune; omitted, all the voyage of their life is bound in shallows and in miseries. On such a full sea are we now afloat, and we must take the current when it serves, or lose our ventures.”[41]

Endnotes

[1] Puerto Rico Public-Private Partnerships Authority, Partnership Committee Report regarding the Puerto Rico Public-Private Partnership for the Puerto Rico Electric Power Thermal Generation Facilities, October 17, 2022, amended January 18, 2023 (the “P3 Report”), p. 16.

[2] P3 Report, p. 17-18.

[3] P3 Report, p. 18.

[4] P3 Report, p. 19.

[5]See Beatriz de la Torre, “AEE pasa con fichas”, El Vocero, 21 de marzo de 2013; “Nebuloso financiamiento de ‘mareducto’”, El Vocero, 23 de mayo de 2013; and “Denuncian ‘chanchullo’ en AEE”, El Vocero, 22 de julio de 2013; and  Mary Williams Walsh, “At Puerto Rico’s Power Company, A Recipe for Toxic Air, and Debt”, New York Times, February 15, 2016; and “In Scandal at Puerto Rico Utility, Ex-Fuel Buyer Insists He Took No Bribes”, New York Times, March 2, 2016.

[6] New Fortress Energy, Inc., Annual Report for the Year Ended December 31, 2021, filed with the United States Securities and Exchange Commission on Form 10-K, p. 3.

[7] Generation O&M Agreement, Section 4.1(a).

[8] Generation O&M Agreement, Section 4.2(u).

[9] Generation O&M Agreement, Section 4.6(b).

[10] Generation O&M Agreement, Section 4.8(a).

[11] Generation O&M Agreement, Section 5.1.

[12] Section 1.A. of Annex IX to the Generation O&M Agreement.

[13] Generation O&M Agreement, Section 7.7(a).

[14] Section 1.A. of Annex II to the Generation O&M Agreement.

[15] Section III.B of Annex II to the Generation O&M Agreement.

[16] Generation O&M Agreement, Section 5.22.

[17] Section III.B.2. of Annex II to the Generation O&M Agreement.

[18] Section III.B.5. of Annex II to the Generation O&M Agreement.

[19] Section III.B.6.(a) of Annex II to the Generation O&M Agreement.

[20] Section III.B.6.(c) of Annex II to the Generation O&M Agreement.

[21] Generation O&M Agreement, Section 16.1(a).

[22] Generation O&M Agreement, Section 16.1(b).

[23] Generation O&M Agreement, Section 16.2(d).

[24] Section III.C.1. of Annex II to the Generation O&M Agreement.

[25] Section III.C.1. of Annex II to the Generation O&M Agreement.

[26] Section 1 of Annex XVI to the Generation O&M Agreement.

[27] Generation O&M Agreement, Section 17.3(b).

[28] FTI Consulting, Benefits of a Third-Party Generation Operator of the Puerto Rico Legacy Generation Assets, September 22, 2022, p. 18-19, included as Exhibit B to the Partnership Committee Report regarding the Puerto Rico Public-Private Partnership for the Puerto Rico Electric Power Thermal Generation Facilities, October 17, 2022, amended January 18, 2023.

[29] New Fortress Energy, Inc, Annual Report for the Year Ended December 31, 2021, filed with the United States Securities and Exchange Commission on Form 10-K, p. 16.

[30] See Juan R. Torruella, “Why Puerto Rico Does Not Need Further Experimentation with its Future: A Reply to the Notion of Territorial Federalism”, Harvard Law Review Forum, Vol. 131, No. 3, (January, 2018).

[31] Puerto Rico Electric Power Authority, Monthly Report to the Governing Board: June 2022, p. 7, available at https://aeepr.com/es-pr/investors/FinancialInformation/Monthly%20Reports/2022/June%202022.pdf

[32] Assuming PREPA’s bonded debt is cut approximately by 50% to $5 billion and a 6% coupon.

[33] 2022 Certified Fiscal Plan for the Puerto Rico Electric Power Authority As certified by the Financial Oversight and Management Board for Puerto Rico on June 28, 2022, p. 164.

[34] P3 Report, p. 29.

[35] Black’s Law Dictionary, Sixth Edition, (St. Paul, MN; West Publishing Co., 1990), p. 1086.

[36] Black’s Law Dictionary, Sixth Edition, (St. Paul, MN; West Publishing Co., 1990), p. 1007.

[37] Generation O&M Agreement, Section 21.19(c).

[38] Generation O&M Agreement, Section 21.19 (d).

[39] William Shakespeare, All’s Well that Ends Well, Act IV, Sc. 3, (1603-1604).

[40] Julia Lovell, Maoism: A Global History, (London: The Bodley Head, 2019), pp. 133-168.

[41] William Shakespeare, Julius Caesar, Act IV, Sc. 2 (1599).