CNE Review – September 2022

Published on September 14, 2022 / Leer en español

See all editions of the
CNE Review
SHARE

SPECIAL EDITION

Another Look at the PREPA-LUMA Agreement

For more than 20 years, CNE has stressed that the transformation of Puerto Rico’s energy sector is one of the most important processes for the future of our people and the economy. This work takes time, commitment, and sometimes the courage to say what no one wants to hear.

In August 2020, CNE published an extensive analysis of the operation and maintenance agreement between the Puerto Rico Electric Power Authority & LUMA. We stated then that the complex contract had deficiencies and should be revised. We presented the 14 key areas where we found risks and offered recommendations to address them.

Unfortunately, time has proven us right again. We find ourselves at another frustrating and challenging juncture.

In this edition of the CNE Review, we present several pieces for our readers: a summary of the policy brief by our Policy Director, the policy brief, and a webpage. Click the links below to access them.

Again, we offer our expertise – first to clarify misunderstandings and facilitate the navigation of a complex transaction and also, to provide a route forward for the benefit of Puerto Rico.

The only option is to work through this together.

Insights + Analysis from CNE

Another Look at the PREPA-LUMA Agreement

Our objective with this new analysis is to provide a succinct evaluation of the situation today, analyze some of the options available to the government of Puerto Rico and hopefully clarify some of the confusion surrounding the operation of this public-private partnership agreement.

Beyond PREPA & LUMA

This webpage aims to place the PREPA & LUMA agreement in the broader context of the transformation of Puerto Rico’s energy sector. Many other processes are going on simultaneously, and CNE has been monitoring and analyzing them.

Another Look at the PREPA-LUMA Agreement

By Sergio M. Marxuach, Policy Director

Where are we today?

To understand where we are today, we need to understand the series of events that brought us here and the timeline that was triggered by the execution of two agreements by the Puerto Rico Electric Power Authority (“PREPA”) and LUMA. These are the Operation and Maintenance Agreement (the “O&M Agreement”) and the Supplemental Agreement. This means that:

  • First, LUMA has been operating the Puerto Rico transmission and distribution system (“T&D System”) for approximately 15 months now pursuant to the terms and conditions of the O&M Agreement as amended by the Supplemental Agreement.
  • Second, the Supplemental Agreement established an interim period of operation, which ends on November 30, unless the government of Puerto Rico requests its extension.
  • Third, the clock has not started running on the 15-year term of the O&M Agreement, as Section 2.4 of the Supplemental Agreement clearly states “the occurrence of the Interim Period shall not in any way reduce or be applied against the Initial Term.” Thus, assuming the Title III Exit occurs by December 31, 2022, the first full year of the O&M Agreement 15-year term would be 2023.
  • Fourth, the fixed Service Fee payable to LUMA in accordance with the Supplemental Agreement is significantly higher than the fixed fee it would receive under the O&M Agreement. According to Section 3.3 the “Interim Period Service Fee” shall be $115,000,000 in 2020 dollars, adjusted for inflation in accordance with Annex VIII of the O&M Agreement, in contrast with the Service Fee payable under the O&M Agreement which is $70,000,000 in 2020 dollars, adjusted for inflation in the same manner, for the first year of the contract. Click here for more information on the timeline and its implications.

After 15 months of operation, it is clear that LUMA is not measuring up to expectations. Both the Puerto Rico Energy Bureau and the P3 Authority have been critical of various aspects of LUMA’s performance. So far LUMA: has incurred budget overruns; has failed to meet key performance metrics regarding the duration and frequency of outages; is behind schedule in meeting certain maintenance goals (for example, controlling vegetation growth around important lines); and has shown little evidence that it is achieving the savings it represented it would generate from more efficient management of the T&D System. It is up to the government of Puerto Rico, then, to defend the interests of the Puerto Rican people.

Given the current state of play and the growing dissatisfaction with LUMA’s performance…

…what are some of the most likely scenarios and their consequences?

1. Run Out the Clock

The government of Puerto Rico could just wait until November 30, 2022, and both agreements would terminate. This would have at least two consequences:

  • PREPA would be required to pay LUMA a termination fee of $115,000,000 in 2020 dollars, adjusted for inflation.
  • A transition period would begin, during which LUMA would wind up its operations and transfer them to a successor operator. PREPA would be responsible for paying a transition fee to cover the cost of LUMA’s operations during this period.

The problem with this scenario is that it appears there are no candidates to be a successor operator in the event of termination. That is, there appears to be no Plan B. Click here for details on Scenario 1.

2. Go the Long Way

The government of Puerto Rico could seek to terminate the O&M Agreement by claiming, through a written notification, the occurrence of at least one Event of Default due to LUMA’s failure to perform a material obligation under the O&M Agreement. A notification of this kind will trigger a long and winding dispute resolution process to terminate the O&M Agreement.

But even if the O&M Agreement is successfully terminated, the same problem remains, who would take over the operation and maintenance of the Puerto Rico T&D System?

3. Play Hardball

Under this scenario, the objective would not be to terminate the O&M Agreement but to turn up the heat on LUMA.

The government of Puerto Rico could do this in any number of ways, but the most effective probably would be by withholding a portion of the Interim Period Service Fee payable to LUMA.

In that event, LUMA would probably argue that such withholding constitutes an Owner Event of Default under the O&M Agreement. The government of Puerto Rico could then seek to start the long and complex dispute resolution process described in Scenario 2.

The idea is that the tedious negotiation and mediation process will force the parties to the table and agree on a set of actions to be undertaken by LUMA to improve its performance. Click here for details on Scenario 3.

The Consequences of Having No Plan B

As we have mentioned above, Scenarios 1 and 2 both suffer from the same fatal defect: there is no obvious candidate to take over the operation of the T&D System in the event of a termination.

Returning the operation of the T&D System to PREPA, a criminally corrupt and extremely inefficient corporation, would be a regression, instead of progress towards meeting Puerto Rico’s energy objectives.

In the alternative, seeking a new operator under the law would be cumbersome and could take up to two years and it is not clear there would be much interest in taking over LUMA’s role.

In addition, we have to consider the impact that a termination could have on the disbursement of the FEMA and CDBG-DR funds allocated for the reconstruction of the grid.

In the end, it is just as irresponsible to grant LUMA a blank check as it is to terminate the O&M Agreement without identifying a viable successor operator. Thus, the most practical scenario is Scenario 3 or a variation thereof. Click here for details.

When Can I Expect My Electricity Bill to Decrease Significantly?

Many factors affect the cost per kWh in Puerto Rico, some of which are within our control and some that are not. Yet, the most important in terms of lowering the cost of electricity in Puerto Rico is the transition to large-scale renewable sources of generation.

According to unaudited financial information available from PREPA’s website, during the period between July 2021 and May 2022, PREPA spent $1.85 billion on fuel and $758 million on purchased power, which is equivalent to 73% of total expenditures of $3.568 billion incurred during that period. Thus, our monthly bill will not significantly decrease in the short term unless (1) the world price of oil and natural gas suddenly plunges; or (2) Puerto Rico significantly increases its capacity to generate electricity from large-scale renewable sources. That is why we emphasize and underscore the need to start rolling out large-scale renewable energy projects.

Conclusion

As we have seen, it is possible to terminate the Agreement with LUMA but there will be some severely adverse consequences, especially if there is no Plan B. Under current circumstances, we would counsel against that course of action. That does not mean, however, that there is nothing that the government can do. Scenario 3 described above is one possible alternative. At a minimum, though, we recommend that the P3 Authority hire an independent firm of world-class engineers, with no business or political connections to Puerto Rico, to relentlessly and unwaveringly supervise LUMA’s performance of its obligations under the Agreement.

Finally, we warn our readers against believing those who are already peddling easy fixes and trafficking in false hopes with the expectation of financial or political gains, or both. There are no effortless solutions to Puerto Rico’s energy problems. It will take several years of steadfast hard work to rebuild the system and decrease energy rates. There are no shortcuts, no easy answers, and no straightforward ways out. The only option is to work through it. Otherwise, we face the unpleasant prospect of several more years of economic decline and social stagnation that would entail.

PREPA and LUMA Agreement: Where are we now?

PREPA and LUMA Agreement: Where are we now?

Published on September 13, 2022 / Leer en español

Sergio portrait
Policy Director
SHARE

We live in a complicated and oftentimes confusing world. Faced with that reality, it is only to be expected that people will oversimplify complex problems. We then divide solutions to economic, political, or social problems into two groups and with a heavy sigh of relief we declare ourselves decidedly in favor of this set of solutions and most definitely against that other set of proposals. While that simplicity may help us feel better, this kind of binary thinking is not helpful in advancing real solutions to difficult problems. What usually happens is that the public discourse degrades into a screaming contest between those ferociously in favor of one “solution” and those rabidly against it. As the opposing groups talk past each other little thinking and even less analysis about the underlying problem gets done.

This is precisely the situation with respect to the public-private agreement between the government of Puerto Rico and LUMA. In recent days, the public debate on this issue has devolved into a silly shouting match between those who support LUMA and those who oppose it. But to paraphrase Pope Francis, who knows a thing or two about hard-nosed negotiations, reducing complex reality to simple binaries is the result of mediocre thinking and when faced with such a reductive, partial mental scheme we must try to transcend it and see the world as it really is, in all its wonderful and confusing complexity.

In the case of the agreement between LUMA and the Puerto Rico Electric Power Authority (“PREPA”) after 15 months of operation it is clear that LUMA is not measuring up to expectations. Both the Puerto Rico Energy Bureau (“PREB”) and the Puerto Rico Public-Private Partnerships Authority (“P3 Authority”) have been critical of various aspects of LUMA’s performance. So far LUMA: has incurred in budget overruns; has failed to meet key performance metrics regarding the duration and frequency of outages; is behind schedule in meeting certain maintenance goals (for example, controlling vegetation growth around important lines); and has shown little evidence that it is achieving the savings it represented it would generate from a more efficient management of the transmission and distribution system (“T&D System”). It is up to the government of Puerto Rico, then, to defend the interests of the Puerto Rican people.

However, this is not the whole story. While we fully sympathize with and support the demands for affordable and more reliable electric service in Puerto Rico, the objective reality is that all of our electric power troubles cannot be blamed on LUMA. The T&D System, while functional, has been in a fragile state since the emergency repairs related to the damage caused by Hurricane Maria were finalized in 2018.

In addition, PREPA’s generation fleet, with the exception of a handful of units that have been retrofitted to burn natural gas, has not been modernized. It still relies mostly on oil and diesel fuel for the generation of electricity. This means that Puerto Rico is at the mercy of oil and natural gas markets, which have been roiled recently by the unexpectedly rapid economic recovery from the COVID-19 pandemic, the strong post-pandemic shift towards the consumption of manufactured goods (instead of services), other constraints on energy supply, and the invasion of Ukraine by Russia.

Therefore, a share of the outages, at least those related to the patched-up state of the grid, and the rate increases, which are mostly, if not wholly, a function of increases in fuel costs, cannot be properly charged to LUMA.

Given this complicated reality the government of Puerto Rico has several options, some of which we explore and explain in the accompanying Policy Brief. To make a long story short, the answer to those who ask whether the operation agreement with LUMA can be terminated is yes. The contract provides several ways for doing so.

Perhaps the easiest course of action, in procedural terms, would be not to seek the extension of the interim operation period that ends on November 30. The Supplemental Agreement currently in effect provides for the automatic termination of both agreements (the Operation and Maintenance Agreement (“O&M Agreement”) as well as the Supplemental Agreement) on that date, unless the government of Puerto Rico seeks to extend its effectiveness.

However, each proposed solution carries with it some consequences that must be analyzed beforehand to avoid mistakes or making an already difficult situation even worse. In the case of the scenario we just described, the automatic termination of the agreements would trigger the occurrence of several events.

First, pursuant to Section 7.2(c)(i) of the Supplemental Agreement, PREPA would be required to pay LUMA a termination fee, which in this case would be equal to the Interim Period Service Fee (see Section 4.2(d) of the Supplemental Agreement). This fee would amount to $115,000,000 in 2020 dollars, adjusted for inflation.

Second, the termination of both agreements would trigger the clock on the Back-End Transition period, which could last up to twelve months and during which LUMA would wind up its operations and transfer them to a successor operator. PREPA would be responsible for paying a Back-End Transition Fee to cover the cost of LUMA’s operations during this period.

The problem with this and any other termination scenario is that it appears there are no candidates to be a successor operator in the event of termination. That is, there appears to be no Plan B. Who will then be in charge of Puerto Rico’s transmission and distribution system?

Devolving the operation of the T&D System to PREPA, a criminally corrupt and extremely inefficient corporation, would be a regression, instead of progress towards meeting Puerto Rico’s energy objectives. In addition, most of PREPA’s employees with experience in transmission and distribution have either retired or moved on to other government agencies. Thus, even if it were desirable to return the operation of the grid to PREPA it may be unable to do so.

In the alternative, seeking a new operator pursuant to the Puerto Rico P3 law would be a cumbersome process that could take up to two years. Given the experience with LUMA, it seems highly unlikely to us that many world-class companies will be lining up to take up its place as operator under the same terms and conditions granted to LUMA. If anything, any such interested company would probably seek even more favorable terms than the ones currently set forth in the agreement with LUMA. There is also the risk that a hastily put together fly-by-night operator with political connections may obtain the new contract, leaving Puerto Rico with the worst of both worlds: a fragile transmission and distribution system and an incompetent, corrupt operator. A scenario that would be absurd in almost any other country, but which cannot be categorically ruled out in Puerto Rico today.

In addition, we have to take into account the impact that terminating the O&M Agreement now could have on the disbursement of the FEMA and CDBG-DR funds allocated for the reconstruction of the grid. The likely scenario is that both agencies would adopt a wait-and-see attitude with respect to such disbursement as legal and operational wrinkles are worked out. This means that the reconstruction of the grid would take even longer than the currently projected 10 years.

Therefore, it appears to us that the best case scenario would be to make the agreement between LUMA and the P3 Authority work. The current public debate is a sideshow because both sides are wrong: it is just as irresponsible to grant LUMA a blank check as it is to terminate the Operation and Maintenance Agreement without identifying a viable successor operator. In our view, the key questions are (1) why has LUMA been unable to meet basic performance objectives during the past 15 months?; (2) what is the government of Puerto Rico willing and able to do about it?; (3) what are the consequences of terminating the current agreement?; and (4) what are the viable alternatives to LUMA, that is what is Plan B? These are the questions we are asking and analyzing.

Going forward, we recommend, at a minimum, that the P3 Authority hire an independent world-class firm of engineers, preferably from the United States or from Europe, with no business or political connections to Puerto Rico, to relentlessly and unwaveringly supervise LUMA’s performance of its obligations pursuant to its agreement with the P3 Authority.

Finally, we warn our readers against believing those who are already peddling easy fixes and trafficking in false hopes with the expectation of financial or political gains, or both. There are no effortless solutions to Puerto Rico’s energy problems. It will take several years of steadfast hard work to rebuild the system and to decrease energy rates. There are no shortcuts, no easy answers, no straightforward ways out. The only option is to work through it. Otherwise, we face the unpleasant prospect of several more years of economic decline and the social stagnation that would entail.

Another Look at the PREPA-LUMA Agreement

Another Look at the PREPA-LUMA Agreement

Published on September 13, 2022 / Leer en español

Sergio portrait
Policy Director
DOWNLOAD
SHARE

Introduction

Puerto Rico’s energy system has been in the news again. Rate increases, widespread outages, and generally unreliable service have combined to generate street protests as well as calls by politicians, artists, and other stakeholders for the government of Puerto Rico to cancel or terminate the public-private partnership agreement with LUMA Energy for the operation of the island’s electric grid.

As of the date of this Policy Brief, it is clear that LUMA has not performed up to expectations. A recent analysis by the Puerto Rico Energy Bureau (the “PREB”) found that both the duration and frequency of outages had increased during the six months between January and June of the current calendar year. This is a particularly disappointing finding because, while we understand that bringing the performance of the system up to world-class standards will take years, so far we have not seen even nominal progress towards achieving that objective. Indeed, according to the PREB’s analysis, the needle is moving in the opposite direction. Instead of seeing modest and continuous progress, say a 3 or 4 percent reduction in the duration of outages, we are, in a sense, in negative territory.

In addition, LUMA has faced difficulties in operating within approved and established budgets, and any savings it may have generated so far from the more efficient operation of the grid appear to be negligible. This is unacceptable.

However, while we fully sympathize with and support the demands for affordable and more reliable electric service in Puerto Rico, the objective reality is that not all of our electric power troubles can be blamed on LUMA. The transmission and distribution system, while functional, has been in a fragile state since the emergency repairs related to the damage caused by Hurricane Maria were finalized in 2018.

In addition, PREPA’s generation fleet, with the exception of a handful of units that have been retrofitted to burn natural gas, has not been modernized. It still relies mostly on oil and diesel fuel for the generation of electricity. This means that Puerto Rico is at the mercy of oil and natural gas markets, which have been roiled recently by the unexpectedly rapid economic recovery from the Covid-19 pandemic, the strong post-pandemic shift towards the consumption of manufactured goods (instead of services), other constraints on energy supply, and the invasion of Ukraine by Russia.

Therefore, a share of the outages, at least those related to the patched-up state of the grid, and the rate increases, which are mostly, if not wholly, a function of increases in fuel costs, cannot be properly charged to LUMA.

CNE already published an extensive analysis of the operation and maintenance agreement, back on August 2o2o. Our objective with this new analysis is to provide a succinct evaluation of the situation today, analyze the options available to the government of Puerto Rico, and hopefully clarify some of the confusion surrounding the operation of this public-private partnership agreement.

Where Are We Today?

In order to understand where we are today, we need to understand the series of events that brought us here and the timeline that was triggered by the execution of the operation and maintenance agreement. This review may be a little tedious but it is absolutely necessary to understand the nature of the transaction Puerto Rico executed in 2020, as well as the options available today. So, let’s take it from the top, as music teachers say.

On June 22, 2020, the Puerto Rico Electric Power Authority (“PREPA” or “Owner”), the Puerto Rico Public-Private Partnerships Authority (the “P3 Authority” or the “Administrator”), and LUMA Energy LLC (“LUMA” or “Operator”), entered into an Operation and Maintenance Agreement (the “O&M Agreement”).

  • The execution of the O&M Agreement started the clock on a transition period (the “Front-End Transition Period”), defined in the O&M Agreement as the period between the Effective Date of the O&M Agreement (June 22, 2020) and the “Service Commencement Date.”
  • The Service Commencement Date, in turn, is defined in Section 4.7(b) of the O&M Agreement as the date on “which a handover to Operator of the O&M Services occurs, which shall be (i) the first (1st) Business Day of a calendar month that is at least three (3) Business Days following the date on which Administrator delivers a certificate to Operator confirming that all Service Commencement Date Conditions have been met or (ii) such other date as the Parties may agree. The satisfaction or waiver of all the Service Commencement Date Conditions is required for the achievement of the Service Commencement Date.”
  • So, in theory, the Service Commencement Date under the O&M Agreement should have been June 1, 2021.
  • But that is not the entire story. The parties also executed on June 22, 2020 a Supplemental Agreement, at the behest of the Fiscal Oversight and Management Board (“FOMB”). The Supplemental Agreement amended parts of the O&M Agreement and entered into effect on June 1, 2021 (the “Supplemental Agreement Effective Date”).
  • Among the most significant of those amendments, we find the following in Section 6.1 of the Supplemental Agreement: “in addition to the Service Commencement Date Conditions set forth in the O&M Agreement, it shall be a Service Commencement Date Condition that the Title III Exit shall have occurred and that the Title III Plan and order of the Title III Court confirming same shall be reasonably acceptable to Operator. The Parties shall follow the process set forth in the O&M Agreement for establishing the Service Commencement Date, upon which date this Supplemental Agreement shall terminate and be null and void.”
  • Thus, the Supplemental Agreement changed the Service Commencement Date under the O&M Agreement, added a key condition to the Service Commencement Date under the O&M Agreement (the Title III Exit,) and partially substituted the timeline set forth in the O&M Agreement by creating an “Interim Period” of operation.
  • Pursuant to Section 2.3 of the Supplemental Agreement the “Interim Period Service Commencement Date” shall be the first (1st) Business Day of a calendar month that is at least three (3) Business Days following the date on which the Administrator delivers a certificate to the Operator” confirming that certain conditions set forth in the Supplemental Agreement have been satisfied. That date was June 1, 2021.
  • In turn, Section 2.4 of the Supplemental Agreement defines the “Interim Period” of operation as the period between the effective date of the Supplemental Agreement and “the earlier of (a) the Service Commencement Date [under the O&M Agreement] and (b) the Interim Period Termination Date [under the Supplemental Agreement].”
  • The “Interim Period Termination Date” occurs automatically in the event that the Service Commencement Date under the O&M Agreement does not occur on or prior to the date that is eighteen (18) months after the Supplemental Agreement Effective Date (June 1, 2021). In that case, “the Supplemental Agreement and the O&M Agreement shall automatically terminate without further action by Operator, and without need for a court decision or arbitral award confirming such termination.”
  • However, “the Interim Period Termination Date may, if requested by Administrator, be extended by the mutual agreement of the Parties prior to the then-current Interim Period Termination Date.”

So, where does that leave us? First, LUMA has been operating the Puerto Rico transmission and distribution system (the “T&D System”) for approximately 15 months now pursuant to the terms and conditions of the O&M Agreement as amended by the Supplemental Agreement.

Second, this means that the clock has not started running on the 15-year term of the O&M Agreement, as Section 2.4 of the Supplemental Agreement clearly states “the occurrence of the Interim Period shall not in any way reduce or be applied against the Initial Term.” Thus, assuming the Title III Exit occurs by December 31, 2022, the first full year of the O&M Agreement’s 15-year term would be 2023.

Third, the fixed Service Fee payable to LUMA in accordance with the Supplemental Agreement is significantly higher than the fixed fee it would receive under the O&M Agreement. According to Section 3.3 the “Interim Period Service Fee” shall be $115,000,000 in 2020 dollars, adjusted for inflation in accordance with Annex VIII of the O&M Agreement, in contrast with the Service Fee payable under the O&M Agreement which is $70,000,000 in 2020 dollars, adjusted for inflation in the same manner, for the first year of the contract. The same pattern prevails during the entire Interim Period.

This higher fee could be interpreted in two ways. First, it could be construed as a pressure mechanism on bondholders to reach a Title III agreement as soon as possible because the Interim Period Service Fee is considered an “administrative expense” that has priority over payments to bondholders. In theory, the sooner the Interim Period ends, the more cash available to bondholders as the obligation to pay the higher Interim Period Fee ends.

The other way to interpret this clause could be as a pressure mechanism on the government of Puerto Rico, specifically PREPA, to exit the Title III process as soon as possible, again to save money on the Service Fee payable to LUMA.

Whichever way it cuts, however, it does not appear to have had much of an effect on the Title III negotiations. It has certainly benefitted LUMA.

Finally, the Supplemental Agreement sets forth additional causes for termination that could be invoked by either the P3 Authority or LUMA.

What Are Some of the Most Likely Scenarios?

Given the current state of play and the growing dissatisfaction with LUMA’s performance, what are some of the most likely scenarios and their consequences?

Scenario 1: Run Out the Clock

Section 7.1(a) of the Supplemental Agreement provides for the automatic termination of both the O&M Agreement and the Supplemental Agreement in the event that the Service Commencement Date under the O&M Agreement does not occur within 18 months of the Supplemental Agreement Effective Date. Given that the Supplemental Agreement Effective Date is June 1, 2021, the Section 7.1(a) term expires on November 30, 2022.

In addition, since it is likely that at least one condition precedent to the Supplemental Agreement Effective Date, namely a Title III Exit ¾ which requires that a Title III Plan be approved by creditors and the issuance of an order of the Title III Court confirming the same ¾ will NOT occur on or prior to November 30, 2022, the government of Puerto Rico will have to make a policy decision regarding the extension of the Interim Period Termination Date under the Supplemental Agreement.

The language of Section 7.1(a) is quite clear:

This Supplemental Agreement and the O&M Agreement shall automatically terminate without further action by Operator, and without need for a court decision or arbitral award confirming such termination, in the event that the Service Commencement Date does not occur on or prior to the date that is eighteen (18) months after the Supplemental Agreement Effective Date (such date, the “Interim Period Termination Date”), which Interim Period Termination Date may, if requested by Administrator, be extended by the mutual agreement of the Parties prior to the then-current Interim Period Termination Date.

From a reading of the plain language of the agreement, we can reach the following conclusions:

  • First, the termination of both agreements is automatic on the Interim Period Termination Date.
  • Second, a close reading of the relevant language shows that it is within the discretion of the government of Puerto Rico to let the clock run out on both agreements. The Supplemental Agreement clearly states that the Interim Period Termination Date may (instead of “shall”), if requested by the P3 Authority (as Administrator of the O&M Agreement), be extended by mutual agreement. If the government of Puerto Rico does not request the extension of the Interim Period, then the automatic termination language becomes effective.
  • Third, contrary to popular belief, there is no requirement to obtain the prior approval of the FOMB to let both contracts expire pursuant to Section 7.1(a) of the Supplemental Agreement.

The termination of both the O&M Agreement and the Supplemental Agreement would have at least two consequences. First, pursuant to Section 7.2(c)(i) of the Supplemental Agreement, PREPA would be required to pay LUMA the Operator Termination Fee, which in this case would be equal to the Interim Period Service Fee (see Section 4.2(d) of the Supplemental Agreement). As we explained above, the Interim Period Service Fee is $115,000,000 in 2020 dollars, adjusted for inflation.

Second, the termination of both agreements would trigger the clock on the Back-End Transition period, which could last up to twelve months and during which LUMA would wind up its operations and transfer them to a successor operator. PREPA would be responsible for paying a Back-End Transition Fee to cover the cost of LUMA’s operations during this period. The problem with this scenario is that it appears there are no candidates to be a successor operator in the event of termination. That is, there appears to be no Plan B.

Scenario 2: Go the Long Way

In the alternative, the government of Puerto Rico could seek to declare the occurrence of an Operator Event of Default under section 14.1 of the O&M Agreement. That section describes several events any one of which would constitute an Event of Default under the O&M Agreement. In all likelihood, the government would probably seek to declare an Event of Default pursuant to Section 14.1(d), for the failure of the Operator to perform a material obligation under the O&M Agreement.

This process would begin with the government of Puerto Rico sending a notification to LUMA describing what it deems to be at least one Operator Event of Default. Delivery of the notification then triggers a long and winding process to terminate the O&M Agreement:

  • First, the Operator would have 60 days to “cure” the default and an additional 30 days if it is “diligently attempting in good faith to cure such failure and it is reasonably expected that such failure is curable”.
  • If the default is not cured within the 90-day period, then the Administrator may terminate the O&M Agreement upon not less than one hundred twenty (120) days prior written notice to Operator, subject, to the extent required by law, to the prior approval of the PREB or the FOMB (if then in existence). Notice that in this scenario, in contrast with termination pursuant to the Supplemental Agreement, obtaining prior approval from the FOMB may be necessary to the extent required by applicable law.
  • At this point, however, LUMA has the right to contest, pursuant to a Dispute Resolution mechanism set forth in Article 15 of the O&M Agreement, whether an Event of Default has actually occurred.
  • The Article 15 Dispute Resolution Process begins with a Notice of Dispute setting forth the subject of the Dispute Resolution Process. Once the Notice of Dispute is delivered, the Designated Persons of the parties have 30 days to negotiate in good faith a solution to the dispute.
  • If after 30 days of negotiations the dispute is still unresolved, then the parties have two options: (1) if it is a “Technical Dispute”, they must submit it to an independent expert who shall have 60 days to make his determination, which shall be binding upon the parties; or (2) if it is a dispute other than a Technical Dispute, then the dispute could be referred to Mediation by either the Administrator or the Operator.
  • If the parties choose Mediation, then the parties shall appoint a mediator, who shall have 90 days to mediate the dispute. If the dispute is not resolved within 90 days, then the Mediation process shall be terminated.
  • At this point, either party may file a civil lawsuit seeking relief in the courts of the Commonwealth of Puerto Rico.
  • If the government of Puerto Rico obtains a decision in its favor, subject to any appeals, then it could proceed to terminate the O&M Agreement.

If the government of Puerto Rico successfully terminates the O&M Agreement due to an Operator Event of Default it is entitled, depending on the reason for the termination, to receive payment from the Operator of the Owner Termination Fee, which is equal to $20,000,000 in 2020 dollars, adjusted for inflation, if the termination occurs during the first five years of the term of the contract, or $10,000,000 in 2020 dollars, adjusted for inflation, if the termination occurs on any other year thereafter.

The termination of the O&M Agreement pursuant to Article 14 would also trigger the clock on the Back-End Transition period, which could last up to twelve months and during which LUMA would wind up its operations and transfer them to a successor operator. PREPA would also be responsible for paying the Back-End Transition Fee to cover the cost of LUMA’s operations during this period.

But the same problem remains, who would take over the operation and maintenance of the Puerto Rico T&D System?

Scenario 3: Play Hardball

Under this scenario, the objective would not be to terminate the O&M Agreement but to turn up the heat on LUMA to get it to improve its performance. The government of Puerto Rico could do this in any number of ways, but the most effective probably would be by withholding a portion of the Interim Period Service Fee payable to LUMA. In that event, LUMA would probably argue that such withholding constitutes an Owner Event of Default under Section 14.3 of the O&M Agreement.

At that point, however, the government of Puerto Rico could invoke the provisions of the Dispute Resolution mechanism pursuant to Article 15, which would set in motion the same dispute resolution process described in Scenario 2. The idea is that the tedious negotiation and mediation process will force the parties to the table and agree on a set of actions to be undertaken by LUMA to improve its performance. It remains to be seen, however, whether the government of Puerto Rico has the backbone and the resolve to execute this Scenario.

The Consequences of Having No Plan B

As we have mentioned above, Scenarios 1 and 2 both suffer from the same fatal defect: there is no obvious candidate to take over the operation of the T&D System in the event the O&M Agreement is terminated.

Devolving the operation of the T&D System to PREPA, a criminally corrupt and extremely inefficient corporation, would be a regression, instead of progress towards meeting Puerto Rico’s energy objectives. In addition, most of PREPA’s employees with experience in T&D have either retired or moved to other government agencies. Thus, even if it were desirable to return the operation of the grid to PREPA it may be unable to do so.

In the alternative, seeking a new operator pursuant to the Puerto Rico P3 law would be a cumbersome process that could take up to two years. Given the experience with LUMA, it seems highly unlikely to us that many world-class companies will be lining up to take up its place as operator under the same terms and conditions granted to LUMA. If anything, any such interested company would probably seek even more favorable terms than the ones currently set forth in the O&M Agreement. There is also the risk that a hastily put together fly-by-night operator with political connections may obtain the new contract, leaving Puerto Rico with the worst of both worlds: a fragile T&D System and an incompetent, corrupt operator. A scenario that would be absurd in almost any other country, but which cannot be categorically ruled out in Puerto Rico today.

In addition, we have to take into account the impact that terminating the O&M Agreement now could have on the disbursement of the FEMA and CDBG-DR funds allocated for the reconstruction of the grid. The likely scenario is that both agencies would adopt a wait-and-see attitude with respect to such disbursement as legal and operational wrinkles are worked out. This means that the reconstruction of the grid would take even longer than the currently projected 10 years.

All of the above leads us to conclude that the most practical scenario is Scenario 3 or a variation thereof. After 15 months of operation, it is clear that LUMA is not measuring up to expectations. Both the PREB and the P3 Authority have been critical of various aspects of LUMA’s performance. So far LUMA: has incurred budget overruns; has failed to meet key performance metrics regarding the duration and frequency of outages; is behind schedule in meeting certain maintenance goals (for example, controlling vegetation growth around important lines); and has shown little evidence that it is achieving the savings it represented it would generate from more efficient management of the T&D System. It is up to the government of Puerto Rico, then, to defend the interests of the Puerto Rican people.

When Can I Expect My Electricity Bill to Decrease Significantly?

This is a difficult question to answer both honestly and with any accuracy due to several reasons. There are many factors that could affect the cost per kWh in Puerto Rico, some of which are within our control and some that are not. Some of these factors are, for example:

  • The restructuring of PREPA’s debts in a court-supervised process pursuant to Title III of PROMESA, the settlement of which may require an increase in rates to pay creditors;
  • The privatization of PREPA’s generation fleet, which probably will require the payment of a service fee to a private operator and thus perhaps result in another rate increase;
  • The modernization and reconstruction of the grid, which is necessary to maximize the interconnection of renewable energy generation resources;
  • The transition to large-scale renewable generation resources, which is taking longer than expected and is being opposed by special interests from the oil and natural gas sector;
  • The war in Ukraine, which has generated a spike in the price of both oil and natural gas;
  • The increased world demand for and high cost of rare earth metals, which are necessary for manufacturing batteries, certain kinds of solar panels, and wind turbines;
  • Puerto Rico’s government lack of capacity to successfully execute complex policies and, unfortunately, complex problems oftentimes, not to say almost always, require complex solutions; and
  • Perhaps related to the prior point, the multiplicity of federal and state agencies with partial jurisdiction over Puerto Rico’s energy sector ¾ among others we can name the DOE, FEMA, HUD, the PREB, PREPA, LUMA, the P3 Authority, COR3, the Puerto Rico Department of Housing, the Puerto Rico Energy Policy Office in the Department of Economic Development and Commerce, a recently appointed Deputy Chief of Staff to the Governor in charge of energy issues, and the FOMB ¾ means that no entity is really in charge, no agency is actually looking at the entire puzzle.

Of all the factors mentioned above, perhaps the most important in terms of lowering the cost of electricity in Puerto Rico is the transition to large-scale renewable sources of generation. According to unaudited financial information available from PREPA’s website, during the period between July 2021 and May 2022, PREPA spent $1.85 billion on fuel and $758 million on purchased power, which is equivalent to 73% of total expenditures of $3.568 billion incurred during that period. This means that your monthly bill will not significantly decrease in the short term unless (1) the world price of oil and natural gas suddenly plunges; or (2) Puerto Rico significantly increases its capacity to generate electricity from large-scale renewable sources.

To put the situation in perspective, even if we assume that terminating the O&M Agreement would immediately generate $115,000,000 in savings, which is not necessarily true because, as we have seen, PREPA would still have to cover LUMA’s costs of operation during the Back-End Transition Period, the savings per client would amount to $6.42 per month, or 21 cents per day, on average.

That is why we emphasize and underscore the need to start rolling out large-scale renewable energy projects. Rooftop solar systems can be a part of the solution but it is unlikely that building an island-wide reliable “grid of grids” consisting solely of interconnected rooftop solar systems can be accomplished in Puerto Rico in a financially feasible manner. Puerto Rico’s relatively large-scale industrial sector calls into question the reliability of such a grid, while its high poverty rates and low wages cast a shadow on its financial viability.

Conclusion

As we stated at the beginning, we empathize with those who are advocating for a more reliable, affordable, and dependable electric power system in Puerto Rico. Unfortunately, the public debate on this issue has devolved into a silly shouting match between those who support LUMA and those who are against it. But to paraphrase Pope Francis, reducing complex reality to simple binaries is the result of mediocre thinking and when faced with such a reductive, partial mental scheme we must try to transcend it.

The current public debate is a circus sideshow because both sides are wrong: it is equally irresponsible to grant LUMA a blank check as it is to terminate the O&M Agreement without identifying a viable successor operator. In our view, the key questions are (1) why has LUMA been unable to meet basic performance objectives during the past 15 months?; (2) what is the government willing and able to do about it?; (3) what are the consequences of terminating the O&M Agreement?; and (4) what are the viable alternatives to LUMA, that is what is Plan B? These are the questions we should be asking and analyzing.

As we have seen, it is possible to terminate the agreement with LUMA but there will be some severely adverse consequences, especially if there is no Plan B. Under current circumstances, we would counsel against that course of action. That does not mean, however, that there is nothing that the government can do. Scenario 3 described above is one possible alternative.

At a minimum, though, we recommend that the P3 Authority hire an independent firm of world-class engineers, preferably from the mainland or from Europe, with no business or political connections to Puerto Rico, to relentlessly and unwaveringly supervise LUMA’s performance of its obligations pursuant to the O&M Agreement.

Finally, we warn our readers against believing those who are already peddling easy fixes and trafficking in false hopes with the expectation of financial or political gains, or both. There are no effortless solutions to Puerto Rico’s energy problems. It will take several years of steadfast hard work to rebuild the system and decrease energy rates. There are no shortcuts, no easy answers, and no straightforward ways out. The only option is to work through it. Otherwise, we face the unpleasant prospect of several more years of economic decline and social stagnation that would entail.

Quo Vadis, Electric System? A Contextual Perspective

Quo Vadis, Electric System? A Contextual Perspective

Published on May 4, 2022 / Leer en español

Director, Madrid Policy Bureau
SHARE

The recent electrical outage in Puerto Rico has again brought to the fore the inordinate delays in modernizing the system, the lack of coordination between public and private entities involved in the task, and the urgent need to reconstruct the electrical grid in the right direction once and for all. To the electrical system’s lack of reliability and the frustrating slowness of the reconstruction process, it is now necessary to add an additional challenge: the instability in the global natural gas markets caused by Russia’s invasion of Ukraine and the uncertainty that now surrounds this energy source.

The planning guidelines driving Puerto Rico’s electric transition anticipate no less than two decades of natural gas in the island’s energy mix; it can thus be expected that the electric bill will continue to be affected by its price swings. It is important to highlight that the price of fossil fuels has already caused the price of electricity in the island to surge from 17¢ Kw/h a 30¢ Kw/h in the past two years.  In this Apuntes desde Madrid I will take a look at what has happened in Europe regarding natural gas in order to reflect on the implications of the new global scenario in the future of Puerto Rico’s electrical system.

At least two more decades tied to natural gas

In January 2022 Puerto Rico produced most of its electricity using fossil fuels (57.8% oil, 25% natural gas), according to the U.S. Energy Information Administration (USEIA). Only 2.2% came from renewable sources produced by large-scale suppliers under contract with PREPA, even though  PR Law 17-2019 establishes a renewable energy generation goal of 40% for 2025 (60% for 2040 and 100% for 2050). It is interesting to note that the capacity of consumers to produce electricity (reflected in net metering statistics) increased from 202,992 MW (20,855 consumers) in 2020 to 315,671 MW (42,199 consumers) in January 2022. This would make distributed generation the third source of electricity in the island.

ELECTRICITY GENERATION (MW) / NET METERING CAPACITY  (MW)
JANUARY 2022

Source U.S. Energy Information Administration, EIA-923 and EIA-861

The future evolution of Puerto Rico’s electrical grid – contained in the Integrated Resource Plan (IRP) that PREPA submitted to the Puerto Rico Energy Bureau (PREB) in June 2019 and the Resolution that the PREB emitted in August 2020 – envisage natural gas as an important part of the island’s electrical infrastructure in the foreseeable future. Oil units will be retired as renewables are integrated into the system during the present decade (several of them do not comply with federal environmental standards) and the system’s transition will be anchored in natural gas. The selected planning scenario (Scenario 3 of the IRP) anticipates a significant penetration of renewable energy by 2038 (90% of installed capacity and 72% of generation) while continuing to rely on natural gas at least until 2040, according to a recent conversation with the PREB. The Bureau says that the transition will be anchored on existing gas facilities, although a new 300MW one could be built if the integration of renewables calendar fails.

This means that natural gas will be an important part of the electric bill in the foreseeable future (the yellow strip in the IRP graph below): consumers in the island will continue to be exposed to the fuel’s volatility in the global markets.

EXPECTED FOSSIL FUEL COSTS

Source: Puerto Rico Integrated Resource Plan 2018-2019

Europe and the “shock” of prices for natural gas

The global spike in the prices of natural gas has been dramatic: in Europe, the juncture has been compared to the 1970s oil crisis (in Puerto Rico we have the remains of the former CORCO refinery as a reminder of the juncture). The signals of the gas crisis started well before Russia’s invasion of Ukraine, at the beginning of 2021, with increased demand due to the rapid post-pandemic economic recovery and a particularly harsh 2020/2021 winter. Geopolitical factors also came into play: during the last quarter of 2021, Russia, the European Union’s principal supplier, reduced by 25% its gas exports to Europe as a way of pressuring Germany to certify the controversial Nord Stream 2 underwater pipeline (the German government had halted approval for security and non-compliance reasons).

EVOLUTION OF THE PRICE OF NATURAL GAS IN EUROPE (DUTCH TTF)

Source: International Energy Agency, Gas Market Report Q4-2021

The marked increase in the price of natural gas provoked in turn a dramatic increase in the price of electricity: in Germany and Spain, for example, prices for the last quarter of 2021 were three and four times those of 2019 and 2020. The European Union  (EU) has a marginalist structure that ties the price of electricity to the costliest source of energy; until now, it served as an incentive for investment in renewables, but it has now provoked an upward spiral in the price of electricity. The upward trend was aggravated by the invasion of Ukraine: in Spain, for example, on March 8 (two weeks after the invasion) residential consumers in the regulated market (those that do not have fixed-rate contracts and pay a daily market price) paid 95 ¢ of euro per kWh during the 7 PM tranche (about $1.03 kWh, more than three times the cost in Puerto Rico).

PRICE OF ELECTRICITY FOR RESIDENTIAL CONSUMERS
WITH NO FIXED RATE CONTRACT, MARCH 8 2022

Source: PrecioLuz March 8, 2022

In Spain, the dramatic increase in the price of electricity provoked production stoppages in electro-intensive industries (steel mills, chemical plants), as well as enormous public pressure.  Social tensions have run high, and the fear of destabilization over the price of energy moved the Spanish government to approve a “crash programme” that included decreases in energy taxes (from 21 to 10%) in September of 2021 and, recently, credits and direct assistance to vulnerable businesses and consumers. The fiscal cost of the programme is € 24,000 million (about $ 25,300 million), a significant gap for the Spanish treasury (the spectre of the gilet jaunes, the French “yellow vests” has been all-too present in Spanish decision-making).  Both the International Energy Agency (IEA) and rating agency Fitch anticipate that the prices for natural and liquified gas will continue high for the remainder of 2022; managing the cost of electricity will continue to require significant political maneuvering.

Economic imperatives have intermingled with geopolitical ones aimed at reducing Europe’s dependency on Russian gas. Germany, for example, is considering the possibility of postponing the retirement of its carbon and nuclear plants and has started to build two liquified natural gas (LNG) terminals in order to receive supplies from alternative suppliers. The European Commission (EC) has launched an initiative to ensure gas supplies for the coming 2022 winter and to reduce demand for Russian gas to 1/3 of present demand by the end of the year (events seem to be overtaking the programme, as Russia has unilaterally stopped gas supplies to Poland and Bulgaria). The European Union (EU) has also started to diversify gas suppliers (the United States and Algeria figure prominently in the plan), increase its natural gas storage capacity, and implant block-purchase mechanisms similar to the one used for COVID-vaccine purchases.

Some think tanks such as the French Jacques De Lors understand that these short-term measures are not enough: the issue is not about finding new gas suppliers but about transitioning out from this energy source. The institute recommends accelerating the green transition: fast-forwarding the deployment of renewable sources; renovating buildings in order to reduce thermal needs (in Europe the need is to provide heat in winter; in Puerto Rico, the imperative is to cool interior environments); substituting grey with green hydrogen (hydrogen produced from green sources instead of gas); and excluding natural gas from sustainable finance taxonomies in order to minimize its attractiveness for investors.

Gonzalo Escribano, analyst at Spanish think tank Real Instituto Elcano understands that this new scenario opens the door for Spain to become a protagonist in Europe’s energy transition, particularly in the development and production of new technologies: green hydrogen (produced from renewable sources), marine eolic capacity (which harnesses wind in high seas), bio-combustibles (which is produced from organic residues or natural resources) and concentrated solar energy (which produces electricity from solar light using mirrors or lenses).

The transition to renewables: an expert’s opinion

Diego Rodríguez Rodríguez, professor at Universidad Complutense in Madrid and research associate at Spanish think tank FEDEA, understands that, even though in the short run the urgency to reduce dependency on Russia will slow the elimination of fossil fuels in Europe, the “shock” will actually accelerate the transition to renewable energy both in the medium and in the long-term. “We are in the process of abandoning natural gas”, Rodriguez recently told CNE, “there will be no more deployment of gas networks, except for hydrogen”.  The EU has recently launched RePowerEU, an initiative that will halve the consumption of natural gas by 2030 and that will accelerate the transition to renewable sources of energy. According to this new norm, all new gas infrastructure must eventually be converted to hydrogen.

Diego Rodríguez Rodríguez,  Universidad Complutense and FEDEA

Rodríguez understands that the biggest challenges to achieving the transition will be administrative and technical since the funding will be readily available through the NextGen EU program (by contrast, in Puerto Rico, federal funding is geared towards reconstructing the grid, not towards new generation).  First, it will be necessary to break the bureaucratic bottlenecks in environmental assessments, which should be completed in five months instead of two years. Second, it will be necessary to deploy a robust electrical grid to integrate and transport new green generation.  As in Puerto Rico, the Spanish grid is operated by a private company, Red Eléctrica, but planning is made by public entities. Spain has recently approved a roadmap to renovate the Electrical Transport Grid which will entail a € 7,000 million investment (about $ 7,600 million) capable to integrate a new contingent of 37MW of renewable energy throughout the country. By 2026, 67% of electric generation should come from renewables, both land and marine-based (a timeline that is a decade and a half shorter than Puerto Rico’s).

Rodríguez highlights the similarities between Puerto Rico and the Canary Islands archipelago: as islands, both have isolated electrical systems. For both, transitioning the electrical systems towards renewables poses a challenge. Most of the electricity generated in the Canary archipelago is fossil-fuel-based (mainly petroleum) – 91% in Lanzarote, 57% in Tenerife. Several decades back, the Canary Islands discussed converting its electric infrastructure to gas, but the endeavor was abandoned for environmental and cost reasons (a local councilperson said last year that renewables had rendered gas obsolete). Rodriguez says that the archipelago seems to have missed the boat on gas: it will not convert existing petroleum-based plants and will instead use these existing thermal units as “back up” in its transition to renewables (in contrast to Puerto Rico, the islands do not register violations to sulfur dioxide air quality norms since 2011). By 2030 the islands must have reduced fossil-based electricity to 50%.

Renewable-based electricity is being integrated into the grid at an increasing pace, but it is still a small share of the archipelago’s mix, below the Spanish median, (17%, well above Puerto Rico). The islands face the environmental challenge of deploying solar panels and wind towers in landmasses of limited territorial extension (El Hierro, for example, is about half of Culebra). For Rodríguez, new technologies like marine eolic floating platforms (which allow deploying wind structures in deep waters) are the archipelago’s big hope and should be an important part of its energy transition: the first Spanish platform was tested and deployed in the archipelago’s waters.  Spain is planning to deploy fifteen floating eolic parks within the next decade and has earmarked € 200 million (about $ 217 million) for research and development of new marine-based new technologies.  Both Scotland and Holland are also betting heavily on marine eolic technologies.

Floating eolic platform

And Puerto Rico?

Should Puerto Rico continue depending on a natural gas infrastructure for several decades, as is contemplated in the current planning? It will all depend, according to the PREB, on the celerity with which renewables are integrated into the system.  The Bureau recently named an independent coordinator to oversee the process, after determining that PREPA “fails to comply with important directives and milestones” and that it “is not capable of executing the renewables Procurement Plan”. The integration of 5,157.82 MW of renewable and storage resources is foreseen between December 2023 and May 2026; the first units to be retired will be oil-fired ones, several of which are in non-compliance with federal environmental standards. Moreover, would it be possible to incorporate locally-based governance, production, and R + D in new technologies?  Without a doubt, the reconstruction of the electric infrastructure opens the door for such an aspiration, but it will be necessary to leave behind outmoded paradigms, address coordination failures between actors, and bestow the process with a true sense of urgency.

CNE Review – March 2022

Published on March 25, 2022 / Leer en español

See all editions of the
CNE Review
SHARE

In This Issue

The recently terminated PREPA Restructuring Support Agreement (“RSA”) was the third failed attempt to restructure at least a portion of PREPA’s debt. Judge Taylor Swain, in her March 8 Order, expressed her concern that “the termination announcement presents the risk of a major setback in progress toward readjustment of PREPA’s liabilities.” She also imposed a tight deadline for the Financial Oversight and Management Board to commence a mediation process and file a plan of adjustment, or a term sheet thereof; submit a schedule for the litigation of pending issues; or show cause as to why the Court should not dismiss the Title III case. Time, therefore, is of the essence.

However, while we fully understand the desire to expeditiously conclude this process after five years of expensive and drawn-out negotiations, it is just as important to get right both the process and the substance of the debt restructuring.

In this Review, we offer some recommendations that hopefully will provide a useful framework to thoughtfully analyze any new proposal to restructure PREPA’s debt. Click here for the complete analysis which also includes a deeper look at the current state of PREPA’s debt restructuring process.

–Sergio M. Marxuach, Editor-in-Chief

Insights + Analysis from CNE

Five Recommendations for PREPA’s Debt Restructuring

By Sergio M. Marxuach, Policy Director

  1. Any new plan of adjustment for PREPA has to be comprehensive in nature – This means the plan of adjustment must take into account the complicated environment in which PREPA operates, Puerto Rico’s weak economy, the fragility of the island’s transmission and distribution system, PREPA’s aging generation fleet, the politicization of its management, and PREPA’s prior history of mismanaged initiatives to reduce costs.
  1. A restructured PREPA should be a solvent entity – This is more than a mere accounting technicality. If PREPA is still insolvent, even after exiting the negotiation process, then it is questionable whether the plan of adjustment would be confirmable by the Court. While PROMESA does not require that solvency be established to confirm a plan of adjustment, it does require that it be “viable” and certainly solvency is at least one component of any “viability” analysis.
  1. Debt reduction has to be drastic – According to PREPA’s Monthly Report to its Governing Board for the Month of December 2021, PREPA’s liabilities totaled $18.1 billion, while its assets added to $10.1 billion, a difference of $8 billion. In theory, then, that is the minimum amount — $8 billion or 44% of all liabilities — by which all of PREPA’s obligations would have to be reduced in order to keep it as a minimally sustainable going concern post-restructuring. It would be extremely ironic, not to say utterly irrational, to finish this expensive five-year process with an entity that is still technically insolvent.
  1. Eliminate the securitization structure – Securitization would have guaranteed the repayment of the new PREPA bonds regardless of PREPA’s operational situation and would have represented a significant upgrade of the bondholder’s collateral package. The repayment guarantee for any new PREPA bonds, as is the case with the existing PREPA bonds, should be a lien against the net revenues (after payment of the operating costs of the issuer) generated by PREPA. We see no reason for upgrading this security structure or for substantially modifying PREPA’s current relative repayment priorities, unless creditors provide an infusion of new money, something analogous to a debtor in possession financing, or some other similar consideration.
  1. Any rate increase to pay off debt will have negative economic consequences – Electricity prices affect economic activity and economic activity affects electricity prices. Any significant rate increases to pay off debt would reduce economic activity and employment, which, in turn, would reduce demand for electricity. Lower demand for electricity would force PREPA to further increase its rates to cover operating costs and meet its obligations. Failure to do so would result in the deferment of capital investments and/or maintenance costs, which would adversely affect the quality of service. And under that scenario, we could expect an increase in “grid defection.” That is, we could expect an increase in the number of customers switching to their own generation sources or connecting “informally” to the PREPA grid.

CNE's Impact in Transforming PREPA

Click on the image below to explore our recent work on the energy sector.

On Our Radar...

War in Ukraine – The Russian invasion of Ukraine threatens the post-1945 rules-based international order that brought peace and prosperity to the West (and Japan) over the last 75 or so years. Beyond his immediate aims in Ukraine, Putin seeks to overturn the post-Second World War settlement in Europe, to rebuild the greatness, at least in his mind, that was the Russian Empire. Opening that door only leads to dark paths that end in some very scary places. Here are some books to help you understand the larger forces of history at play in Europe right now:

  • Timothy Snyder, Bloodlands: Europe Between Hitler and Stalin, (Basic Books, 2010);
  • Anne Applebaum, Red Famine: Stalin’s War on Ukraine, (Doubleday, 2017);
  • Tony Judt, Postwar: A History of Europe Since 1945, (Penguin, 2006);
  • Anna Reid, Borderland: A Journey Through the History of Ukraine (Basic Books, 2015);
  • Serhii Plokhy, The Gates of Europe: A History of Ukraine, (Basic Books, 2021);
  • Svetlana Alexievich, Secondhand Time: The End of the Soviets (Random House, 2017);
  • Charles Clover, Black Wind, White Snow: The Rise of Russia’s New Nationalism (Yale, 2016); and
  • Timothy Snyder, The Road to Unfreedom: Russia, Europe, America, (Tim Duggan Books, 2018).

Russian Geopolitics – Stephen Kotkin, professor of History and International Affairs at Princeton, wrote this synthesis of the history driving Russia’s geopolitics for Foreign Affairs in 2016. According to Professor Kotkin, “for half a millennium, Russian foreign policy has been characterized by soaring ambitions that have exceeded the country’s capabilities.” Throughout the past five hundred years, “the country has been haunted by its relative backwardness, particularly in the military and industrial spheres. This has led to repeated frenzies of government activity designed to help the country catch up, with a familiar cycle of coercive state-led industrial growth followed by stagnation. Most analysts had assumed that this pattern had ended for good in the 1990s, with the abandonment of Marxism-Leninism and the arrival of competitive elections and a buccaneer capitalist economy. But the impetus behind Russian grand strategy had not changed. And over the last decade, Russian President Vladimir Putin has returned to the trend of relying on the state to manage the gulf between Russia and the more powerful West.”

The European Response – In times of geopolitical crisis, security and sovereignty prevail over everything else. The European Union struggles with the demons of that defensive reflex even as it faces Russia over its invasion of Ukraine: “As a paranoid dictator, Vladimir Putin has survived by eliminating anyone who could pose a threat to him. But now that he has triggered the survival instinct of Europe and the broader West, the world is entering a dangerous new phase of existential conflict”, writes Mark Leonard, Director of the European Council on Foreign Relations, for Project Syndicate.

PREPA’s Debt Restructuring – What’s Next?

PREPA’s Debt Restructuring – What’s Next?

Published on March 24, 2022 / Leer en español

Sergio portrait
Policy Director
DOWNLOAD
SHARE

Introduction

On March 8, 2022, the Puerto Rico Fiscal Agency and Financial Advisory Authority (“AAFAF”), issued a notification stating it was terminating the Definitive Restructuring Support Agreement (the “PREPA RSA”), dated as of May 3, 2019, as amended, by and among (1) the Puerto Rico Electric Power Authority (“PREPA”), (2) AAFAF, (3) the Financial Oversight and Management Board for Puerto Rico (“FOMB”), (4) the members of the Ad Hoc Group of PREPA Bondholders, (5) Assured Guaranty Corp. and Assured Guaranty Municipal Corp., (6) Syncora Guarantee Inc., (7) National Public Finance Guarantee Corporation, and (8) any other persons who had joined the PREPA RSA as of that date.

The purpose of the PREPA RSA was to restructure certain bonds issued by PREPA. In our view, the PREPA RSA was not a good transaction for Puerto Rico. Its terms and conditions were overly generous to creditors; it discouraged the transition to distributed renewable generation; there was uncertainty as to whether it provided the debt relief necessary to maintain PREPA as a going concern, while avoiding another restructuring in the short to medium term; and would have, in all likelihood, resulted in a significant rate increase for Puerto Rican ratepayers for decades to come.

In this policy brief, we take a look at the current state of PREPA’s debt restructuring process and offer some recommendations about what a good PREPA debt restructuring transaction should (and shouldn’t) include.

Procedural Status

Judge Laura Taylor Swain, also on March 8, issued an Order Denying Urgent Motion of the Ad Hoc Group of PREPA Bondholders to Appoint a Mediator and Impose Deadlines for a PREPA Plan of Adjustment and Directing Additional Consultation and Filings,[1] (the “March 8 Order”).

The March 8 Order denied “the Ad Hoc Group’s Motion insofar as it seeks an order requiring the Oversight Board to participate in, and PREPA to provide unlimited financing for, mediation focused on the interests of a particular subset of creditors under the provision of an RSA that AAFAF has purportedly terminated.”[2]

The Court, however, encouraged the relevant parties to “continue discussions and pursue a consensual resolution of the outstanding issues” and stated that it would be willing to consider “a prompt consensual revival of a private mediation proposal” if such proposal is “accompanied by a delineation of scope, a timetable, and evidence of the proposal’s commercial reasonableness, susceptibility to cost controls, and consistency with any relevant requirements of the Puerto Rico Recovery Accuracy in Disclosures Act (“PRRADA”).[3]

To that end, the Court ordered the FOMB to “promptly meet and confer with AAFAF, the Ad Hoc Group of Bondholders, and all other major stakeholders and interested parties whose collaboration it believes is necessary to construct a viable basis for a plan of adjustment, to consider whether a consensual mediation arrangement can be entered into promptly to resolve key plan-related issues.”[4] Any mediation proposal submitted for Court approval must comply with the criteria set forth above. The FOMB and AAFAF have until March 18, 2022 to submit a status report regarding this matter.

In addition, the Court ordered the FOMB to file by May 2, 2022:

  • “A proposed plan of adjustment, disclosure statement, and proposed deadlines in connection with consideration of the disclosure statement, plan-related discovery, solicitation and tabulation of votes, objection period in connection with the confirmation hearing, and proposed confirmation hearing schedule for the PREPA Title III case; or
  • A detailed term sheet for a plan of adjustment, with a proposed timetable for the filing of the plan, consideration and approval of a disclosure statement, voting and confirmation of the plan; or
  • A proposed schedule for the litigation of significant disputed issues in PREPA’s Title III case, including, without limitation, the motion for stay relief to seek appointment of a receiver, the UCC’s claim objection (including, if appropriate, litigation of antecedent questions of standing), and the issues raised in Adv. Proc. Nos. 19-396 and 19-405; or
  • A declaration and memorandum of law showing cause as to why the court should not consider dismissal of PREPA’s Title III case for failure to demonstrate that a confirmable plan of adjustment can be formulated and filed within a time period consistent with the best interests of PREPA, the parties-in-interest and the people of Puerto Rico.”[5]

On March 9, 2022, the Honorable Rafael Hernández, Speaker of the House of Representatives of Puerto Rico, sent a letter to the FOMB “expressing the House’s interest in participating in the mediation process regarding PREPA’s plan of adjustment.”[6]

On March 14, 2022, the FOMB replied that the “Oversight Board does not anticipate developing or negotiating a PREPA plan of adjustment requiring legislation. But, if that changes, the Oversight Board would welcome the Legislature’s participation in mediation if such a restructuring proposal is developed.”[7]

On March 16, 2022, the Court entered another Order (the “March 16 Order”) amending the March 8 Order, indicating “[t]he Court is exploring whether a judicial mediator or mediation team can be made available to facilitate development of a plan of adjustment for PREPA and the resolution of related litigation.”[8]

Analysis of the Procedural Options

In our view, it is clear from the language of the March 8 Order that Judge Taylor Swain favors a consensual resolution of the major pending issues prior to the FOMB submitting a plan of adjustment for PREPA. Hence her order that the FOMB determine the feasibility of setting up a mediation process in consultation with AAFAF, the Ad Hoc Group of Bondholders, and “all other major stakeholders and interested parties whose collaboration it believes is necessary” to develop a plan of adjustment.

In theory, the group of “major stakeholders and interested parties” would include, at a minimum, the following parties: (1) PREPA; (2) AAFAF; (3) the FOMB; (4) the Ad Hoc Group of PREPA Bondholders; (5) Assured Guaranty Corp. and Assured Guaranty Municipal Corp.; (6) Syncora Guarantee Inc.; (7) National Public Finance Guarantee Corporation; (8) PREPA’s Fuel Line Lenders; (9) a representative of PREPA’s current retirees and future beneficiaries of PREPA’s pension plan; and (10) a representative of PREPA’s unsecured creditors.

Who else might be deemed a “necessary party” seems to be up to the FOMB to decide. Based on its letter to Speaker Hernández it appears the FOMB will apply a narrow definition to determine who is a “necessary” party to the mediation proceedings. That is, it appears the FOMB would be limiting participation in any mediation process only to those parties strictly required to develop a plan of adjustment.

That would be a pity, for while we understand that there is a negative tradeoff between expediency and the number of parties at the negotiating table, there are also some advantages to integrating a broader set of stakeholders and interested parties into the negotiating process. To the extent any proposed plan of adjustment has significant support among civic society organizations, NGOs, and the various trade guilds, the easier it would be to implement. While, on the other hand, presenting PREPA’s clients, essentially everybody in Puerto Rico, with a plan they don’t understand as a fait accompli, on a take it or leave it basis, is likely to generate resistance and opposition.

Mediation is also preferable to the available alternatives to a negotiated settlement. In the instant case, those alternatives are the litigation of complex issues of law and fact, which could take literally years when appeals are factored in, or the dismissal of the Title III case, in which case bondholders and other creditors would seek to exercise their rights pursuant to the terms and conditions of the relevant credit documents. PREPA’s bondholders, for example, would be entitled to request the appointment of a receiver to manage and operate PREPA and to require the enforcement of the rate covenant of the 1974 Trust Agreement, pursuant to which PREPA’s rates would have to be set at a level that generates sufficient revenues to cover all operating expenses plus 120% of annual debt service.

Finally, the FOMB has the option to develop a plan of adjustment with the support of only one class of creditors and seek a court order to “cramdown” all the other creditors, pursuant to section 314(c) of PROMESA. This option, while theoretically possible, is highly unlikely to be endorsed by Judge Taylor Swain, who has demonstrated a clear preference for consensual solutions throughout all Title III proceedings.

In sum, then, an inclusive mediation process would be the best path forward to “construct the basis for a confirmable plan of adjustment for PREPA”. No doubt, it would be a complicated and tough negotiating process and the timeline set by the Judge is rather tight. Nonetheless, if all the parties act in “good faith and in a focused manner”, it should be possible to present the Court with at least a detailed term sheet for a plan of adjustment by May 2, as requested by Judge Taylor Swain.

Substantive Recommendations

The FOMB has usually defended prior proposals for PREPA’s debt restructuring in narrow terms. Perhaps it is legally required to do so. It has stated in the past that its main objective is to ensure any plan of adjustment for PREPA meets the requirements for confirmation set forth in PROMESA. However, any transaction that affects a sector as important as electricity is to the Puerto Rican economy needs to be evaluated in a thorough manner.

Therefore, any plan of adjustment for PREPA has to be comprehensive in nature and take into account the economic and social environment in which PREPA operates. This means that any plan of adjustment must take the following factors into account: (1) PREPA operates in an economy that has shown little or no growth for 15 years; (2) it operates in an island with a declining population and a shrinking industrial base; (3) high fuel costs and general inflationary pressures are expected to prevail in the short to medium term due to the aftermath of the Covid-19 epidemic and the war in Ukraine; (5) interest rates are expected to rise as central banks seek to lower inflation around the globe; (6) Puerto Rico has a fragile transmission and distribution system that needs, essentially, to be entirely rebuilt; (7) PREPA operates an aging fossil fuel generation fleet, with an average age of 40 years and some units approaching 60 years, which is close to the end of their useful life; (8) PREPA is run by a largely ineffective management team, which has been tainted by corruption in the past, and traditionally has been led by political appointees; and (9) PREPA is currently a bankrupt utility without access to the capital markets.

These operational risks translate into financial risks such as the following, which should be taken into account when restructuring PREPA’s debt:

  • Pension liabilities, if not restructured, could result in a 3.4 cent/kWh increase by 2034.[9]
  • Inefficient dispatch of generation could raise rates by 1.08 cents/kWh to 1.28 [10] cents/kWh a year.
  • PREPA has not been fully transparent about the full extent of T&D investment required over the long term to achieve both its resiliency and renewable generation goals. PREPA’s certified 2019 Fiscal Plan states it will need to make capital expenditures on the T&D system of $8.2 billion between 2020 and 2024 plus an additional $8.2 billion between 2025 and 2030. But that is only for resilience, in order to incorporate large amounts of distributed generation it will need to make an additional investment of $13.6 billion between 2030 and 2035. London Economics International (“LEI”), a consulting firm, estimates the federal government will pay 90% of the first $16.4 billion, but that the other $13.6 billion would have to be recuperated through higher customer rates. [11]
  • Finally, according to its FY2019 Fiscal Plan, PREPA needs to make a series of capital investments in order to reduce its dependency on oil and reduce its operating costs, and those investments will have to be financed and repaid in some way. PREPA’s poor financial condition will raise the cost of financing investments in new renewable generation. This means that ratepayers will have to pay for those costs through long-term power purchase and operating agreements (“PPOAs”), which will need to be included in customer rates. According to LEI, it is possible that the costs of the PPOAs may not be completely offset by reduced use of fossil fuels. [12]

Second, a restructured PREPA should be a solvent entity, at least on paper. As Professor Ramón Cao has stated the “restructured debt is sustainable if, and only if, PREPA is able to effectively operate as an electric utility after the implementation” of the plan of adjustment.[13] This issue is more than a mere accounting technicality. If PREPA is still insolvent, even after exiting the negotiation process, then it is questionable whether the plan of adjustment would be confirmable by the Court. While PROMESA does not require that solvency be established to confirm a plan of adjustment, it does require that it be “viable” and certainly solvency is at least one component of any “viability” analysis.

Debt reduction, therefore, has to be drastic. According to PREPA’s Monthly Report to its Governing Board for the Month of December 2021, PREPA’s liabilities totaled $18.1 billion, while its assets added to $10.1 billion, a difference of $8 billion. In theory, then, that is the minimum amount — $8 billion or 44% of all liabilities — by which all of PREPA’s obligations would have to be reduced in order to keep it as a minimally sustainable going concern post-restructuring.

Again, PROMESA does not require that solvency be established in order to confirm a plan of adjustment, but it would be extremely ironic, not to say utterly irrational, to finish this expensive five-year process with an entity that is still technically insolvent. On the other hand, the approach proposed by Professor Cao appears to be reasonable. It seeks the answer to one question: would PREPA be solvent on a balance sheet and cash flow basis after giving effect to the proposed transaction? Doing that analysis for a stand-alone entity such as PREPA is relatively easy, especially in comparison with the complex nature of Puerto Rico’s central government finances.

For the sake of clarity, we are not arguing in favor of reducing every single creditor’s claim against PREPA by 44%. Instead, our point is, based on Professor Cao’s methodology, that PREPA’s total obligations should be reduced on average by 44%. The amount of the actual impairment of each creditor’s claim would be the subject of negotiation or litigation among the parties.

Fourth, eliminate the securitization structure. Under the terms of recently terminated RSA, the parties to the agreement would have exchanged their existing bonds for new bonds (the “New Bonds”) to be issued by a “special purpose public corporation and instrumentality of the Government of Puerto Rico, constituting a corporate and political entity independent and separate from the Government of Puerto Rico, PREPA and any other Government Entity.”[14]

The repayment of the New Bonds would have been secured by a lien on the future cash flow generated by PREPA through the imposition of a Transition Charge. This was a special charge that would have been added to the amount billed to PREPA’s customers and used solely to pay the New Bonds. The Transition Charge was designed to increase over time, from 2.768 c/kWh during the first fiscal year after the issuance of the New Bonds up to a cap of 4.552 c/kWh during fiscal year 2044 and thereafter.

This so-called “securitization structure” would have guaranteed the repayment of the New Bonds regardless of PREPA’s operational situation and would have represented a significant upgrade of the bondholder’s collateral package. PREPA legacy bonds are “special revenue bonds” which are commonly issued by governmental agencies that provide such basic services as transportation, water, sewers, electricity, gas for heating, and so on. The repayment guarantee for these bonds, as is the case with the existing PREPA bonds, is a lien against the net revenues (after payment of the operating costs of the issuer) generated by the issuer. We see no reason for upgrading this security structure or for substantially modifying PREPA’s current relative repayment priorities, unless creditors provide an infusion of new money, something analogous to a debtor in possession financing, or some other similar consideration.

Fifth, keep in mind that any rate increase to pay off debt will have negative economic consequences. Electricity prices affect economic activity and economic activity affects electricity prices. Under the 2019 RSA, PREPA would have started billing the Transition Charge in the near term, while any savings from switching to cheaper fuel sources and other cost-saving measures would probably have taken several years to materialize.

In theory, as some FOMB have representatives have argued, it is possible that the imposition of the Transition Charge or a similar special charge to pay off debt would not necessarily have entailed a rate increase for customers, so long as PREPA reduced its system-wide operating costs by an amount equal to or greater than the Transition Charge. In practice, achieving that amount of cost reduction would be very difficult, given the state of PREPA’s operations, and PREPA’s prior history of mismanaged initiatives to reduce costs certainly casts a shadow on its ability to reduce costs by an amount that would offset any such special charge.

Therefore, it is highly probable that rates would have increased significantly under the old RSA due to the Transition Charge. Professor Cao estimated that increasing rates by the amount of the Transition Charge would have reduced GNP in Puerto Rico by 8.1% in real terms by 2024 relative to actual GNP at constant prices in FY2017 and induced a reduction in total employment of 33,382 jobs by 2024, equivalent to 3.4% of total employment in FY2018.[15]

Lower economic activity and employment would, in turn, reduce the demand for electricity. According to estimates by Professor Cao, demand for electricity by residential, commercial, and industrial consumers would have declined by 21.8%, 7.8%, and 34.2%, respectively by fiscal year 2024 relative to electricity consumption in fiscal year 2017.[16]

Lower demand for electricity would force PREPA to further increase its rates to cover operating costs and meet its obligations. Failure to do so would result in the deferment of capital investments and/or maintenance costs, which would adversely affect the quality of service. And under that scenario, we could expect an increase in “grid defection.” That is, we could expect an increase in the number of customers switching to their own generation sources or connecting “informally” to the PREPA grid, “leaving only the customers that cannot afford to leave the PREPA service franchise; those are the customers that are least likely to be able to afford to pay for the rising electricity rates.”[17]

Conclusion

The recently terminated PREPA RSA was the third failed attempt to restructure at least a portion of PREPA’s debt. Judge Taylor Swain in her March 8 Order expressed her concern that “the termination announcement presents the risk of a major setback in progress toward readjustment of PREPA’s liabilities.”[18] She also imposed a tight deadline for the FOMB to commence a mediation process and file a plan of adjustment, or a term sheet thereof; submit a schedule for the litigation of pending issues; or show cause as to why the Court should not dismiss the Title III case. Time, therefore, is of the essence.

However, while we fully understand the desire to expeditiously conclude this process after five years of expensive and drawn-out negotiations, it is just as important to get right both the process and the substance of the debt restructuring.

In procedural terms, we believe an inclusive mediation process is the best alternative to achieve a viable agreement among the parties, especially in contrast with the alternatives of prolonged litigation or the dismissal of the Title III case.

In terms of the substance of the transaction, our view is that any proposed plan of adjustment to restructure PREPA’s liabilities has to (1) take into account the complicated environment in which PREPA operates; (2) result in a restructured PREPA that is solvent; (3) reduce PREPA’s total obligations by at least 44%; (4) be based on a net revenue lien on PREPA’s revenues, and (5) minimize any rate increases to pay off debt.

Anything less would probably result in a defective debt restructuring, raising the specter of a new bankruptcy within the next five years.

End Notes

[1] PREPA Docket Entry No. 2748.

[2] Id. at p. 10.

[3] Id. at pp. 10-11.

[4] Id. at p. 12.

[5] Id. at p. 13.

[6] FOMB – Letter – Legislative Leaders – PREPA Regarding Mediation – March 14, 2022.

[7] Id.

[8] Docket Entry No. 20357 at p. 2.

[9] London Economics International LLC, Critique of Government Parties’ Assertion that the 9019 Settlement will Not Affect Non-settling Creditors and Will Avoid a Subsequent Tittle III Filing by PREPA, October 30, 2019, (the “LEI Report”), p. 22. The LEI Report was prepared for the Official Committee of Unsecured Creditors of the Puerto Rico Electric Power Authority.

[10] Id.

[11] Id. at p. 97. With respect to the first $16.4 billion we note that as of the date of this Policy Brief, FEMA and HUD have committed to fund only approximately $12 billion of the required T&D capital expenditures.

[12] Id. at p. 4.

[13] Ramón J. Cao García, An Independent Evaluation of PREPA’s Financial Sustainability and its Impact on Proposed Restructuring Support Agreement, PROMESA Proceedings and Funding Scenarios on PREPA Planned Capital Investments, May 19, 2020, (the “Cao Report 2”), p. 4 and p. 7.

[14] Definitive Restructuring Support Agreement, Exhibit C (Recovery Plan Term Sheet), Annex A (Securitization Term Sheet), Schedule I-B (Securitization Protections), p. I-B-1.

[15] Ramón J. Cao García, An Independent Economic Evaluation of the Definitive Restructuring Support Agreement for Outstanding PREPA’s Debt, of PREPA Fiscal Plan and a Modest Proposal, August 30, 2019, (the “Cao Report 1”), p. 20 and p. 24.

[16] Id. at p. 27, p. 28, and p. 30.

[17] LEI Report, p. 65.

[18] March 8 Order at p. 10.

CNE Review – October 2021

Published on October 21, 2021 / Leer en español

See all editions of the
CNE Review
SHARE

In This Issue

In the past few weeks, we have been hearing diverse opinions as to who bears responsibility for the recent rolling blackouts. Some are placing the blame on LUMA, others on the Puerto Rico Electric Power Authority (PREPA). Prompted by these discussions, we find it necessary to, once again, address the current energy crisis.

In this edition of the CNE Review, we will take a look at some of the early events that foretold the demise of Puerto Rico’s energy system, such as PREPA’s operating losses and increased levels of indebtedness, to the shortcomings of the recent agreement with LUMA for the operation and maintenance of the electric grid. We also provide recommendations as to what can be done to tackle the ongoing crisis.

Keep reading for a summary of our analysis. Click here to access the full text.

Insights + Analysis from CNE

The Demise of Puerto Rico’s Electrical System

By Sergio M. Marxuach, Policy Director

We have been hearing some rosy statements about how well the Puerto Rico Electric Power Authority (“PREPA”) used to work. it would be a mistake to romanticize the old PREPA. As we will demonstrate below, things were not all copacetic when PREPA was in charge. Puerto Rico’s energy woes were years in the making and are the direct result of PREPA’s mismanagement, negligence, and corruption.

However, PREPA’s indictment is not LUMA’s vindication. LUMA had about a year to prepare for the takeover of Puerto Rico’s electricity grid and its performance so far has been, in the best case, deficient, and in the worst, dismal. Its management, so far, has utterly failed to deliver on its promises.

Thus, it is important to keep in mind that both PREPA and LUMA bear responsibility for the recent malfunctioning of Puerto Rico’s electricity system. It is in the best interests of both companies to change their ways, for their own benefit and the wellbeing of the Puerto Rican people.

Interpreting PREPA’s last two bond offerings

The Official Statements for PREPA’s last two bond offerings, dated April 12, 2012 (the “2012 OS”) and August 15, 2013 (the “2013 OS”), respectively, contain a wealth of data and information about Puerto Rico’s electricity system.

After close scrutiny of these documents, we found that a combination of (1) low liquidity; (2) funding current spending with long-term debt; and (3) limited access to the capital markets due to increased levels of indebtedness and debt service, resulted in a significant reduction in system maintenance expenditures from $250.6 million during fiscal year 2007 to $213.9 million during fiscal year 2013, a decrease of $36.7 million, or 14.6%. (2012 OS, p. 71 and 2013 OS, p. 58)

The lack of maintenance, in turn, affected overall system performance as demonstrated by several key metrics.

Click here to read more about the three main reasons why system maintenance expenditures were reduced and the particular ways in which the system’s performance was affected.

A Series of Unfortunate Events?

While PREPA officially claimed that it suffered from a series of unfortunate events caused by a menagerie of small animals, the truth is that by the time PREPA filed for bankruptcy in May 2017 the system was already thoroughly fragile, with decreasing available capacity; increasing outage rates; and limited available reserves. And then Hurricane María hit, devastating the transmission and distribution system in September 2017.

Despite the massive effort to restore electric service after Hurricane Maria, it was always understood that it was not a permanent fix — a thorough refurbishing of the grid was necessary to bring it up to 21st century standards. PREPA estimated such refurbishing would cost north of $10 billion. Years of negotiations with FEMA followed, until an agreement was reached in December 2020. In the meantime, the patched-up grid kept acting up. On the generation side not much happened either, as evidenced by the continued dispatch of the Palo Seco generation plant.

The Arrival of LUMA

Such was the neglected state of Puerto Rico’s electricity system — an old, unreliable, fossil fuel-based generation fleet connected to a functional but fragile and unstable transmission and distribution grid — when PREPA and the government of Puerto Rico executed a long-term agreement for the operation and maintenance of the electric grid (the “O&M Agreement”) with LUMA, a Canadian/Texan consortium.

The video below (in Spanish) summarizes what LUMA and PREPA are each in charge of and the extent of coordination needed between the two entities.

That coordination is executed in accordance with the terms and conditions of another agreement among and between PREPA, LUMA, and the Puerto Rico P3 Authority (“P3”): the GridCo – GenCo Power Purchase & Operating Agreement (the “PPOA”). Click here to read some of the key terms and conditions of the PPOA.

In a nutshell, PREPA is responsible for the operation and maintenance of the generation fleet, while LUMA is in charge of funding PREPA’s operations on a monthly basis and dispatching load into the grid. Given the complicated character of this relationship, we suspect that the recent rolling blackouts are as much a function of (1) a decrepit generation fleet and an unstable transmission and distribution grid as of (2) a series of coordination failures between PREPA and LUMA.

What can we expect moving forward and what can we do?

Given this state of affairs, this is what we can expect…

  • It will take about 10 years to upgrade the transmission and distribution system, with or without LUMA. This task is exceedingly complex and expensive. And there are no shortcuts.
  • The modernization of the generation fleet will also take several years, be it with additional natural gas capacity, increased generation from renewable sources, or a combination of both.
  • The above means that in the short term electric service in Puerto Rico will continue to be unreliable and expensive.
  • Rising fossil fuel prices (including natural gas), the unavailability of several low-cost generation units to meet base load due to unforeseen breakdowns, and the obligation to eventually start paying debt service on PREPA’s restructured indebtedness, will be the main drivers of the cost of electricity in Puerto Rico.

…and what we hope can be done:

  • Nonetheless, some remedial measures could be implemented in the short term to stabilize the transmission and distribution system and to reduce the dependence on the use of high-cost peaking units. It is up to both PREPA and LUMA to identify those “quick wins” and execute them.
  • In addition, the transition to renewable generation must continue. The generation of electricity using renewable sources protects both the environment, by lowering emissions of greenhouse gases, and consumers, by stabilizing the price of electricity. It is not true that electricity from renewable sources is always more expensive than electricity generated with traditional fuels. The technology for solar and/or wind generation in combination with battery storage has developed significantly during the last few years, in some cases approaching the costs of natural gas generation.
  • Furthermore, in order to properly compare costs between one kind of generation and another, it is necessary to add the cost of the environmental and health damages caused by fossil fuel generation. Adding in the costs of these negative externalities almost always reveals that fossil generation is costlier than initially thought. The imposition of a carbon tax is one of several policy alternatives to force polluters to internalize the cost of these negative externalities they impose on society at large.
  • Finally, it is imperative that the government agencies in charge of implementing energy policy in Puerto Rico have the necessary resources to execute their respective missions: (1) the PREB to regulate rates and promote long-term planning for the system; (2) the P3 Authority to effectively monitor and robustly enforce the O&M Agreement with LUMA; and (3) PREPA to adequately coordinate the day-to-day operation of the generation system.

Want to learn more?

On Our Radar...

Climate Change – This fall, from October 31 through November 12, the 26th gathering of the Conference of the Parties to the United Nations Framework on Climate Change, or COP26 for short, will take place in Glasgow. According to a recent paper published by Chatham House, if emissions of greenhouse gases follow the current trajectory “there is a less than five per cent chance of keeping temperatures well below 2°C above pre-industrial levels, and less than one per cent chance of reaching the 1.5°C target set by the 2015 Paris Agreement”…and “many of the climate change impacts described in this research paper are likely to be locked in by 2040, and become so severe they go beyond the limits of what nations can adapt to.”

How Democracies Die – The breakdown of democratic regimes has been studied for decades by historians, sociologists, and political scientists. What is different now, is that many of those analyses focus on the United States, including this thought-provoking essay published in The Atlantic by Eliot A. Cohen, where he concludes that if the U.S. “succumbs to its internal divisions, to its preoccupation with partisan feuding and its desire to withdraw from international politics, the world order, such as it is, will crumble.”

The Future of Work – In this interesting op-ed for the New York Times, Jonathan Malesic writes that “work sits at the heart of Americans’ vision of human flourishing. It’s much more than how we earn a living. It’s how we earn dignity: the right to count in society and enjoy its benefits. It’s how we prove our moral character. And it’s where we seek meaning and purpose, which many of us interpret in spiritual terms…But work often doesn’t live up to these ideals. In our dissent from this vision and our creation of a better one, we ought to begin with the idea that each one of us has dignity whether we work or not. Your job, or lack of one, doesn’t define your human worth.”

The Short Memory of the Masters of Disaster

The Short Memory of the Masters of Disaster

Published on October 20, 2021 / Leer en español

Sergio portrait
Policy Director
DOWNLOAD
SHARE

Introduction

Historians, whenever possible, try to work using primary sources — diplomatic cables, a ship captain’s log, a soldier’s diary, ancient pictographs from a scroll— for a reason. Human memory is short and fallible, while written records can faithfully preserve first-hand accounts of human folly, in theory, forever. Of course, interpretations of those sources can and should be challenged, but once a source’s authenticity has been established its evidentiary value is beyond reproof.

Recently, we have been hearing some unreasonably rosy statements about how well the Puerto Rico Electric Power Authority (“PREPA”) used to work. What caught my attention was that these utterances were not made by the usual suspects, by which I mean people who speak in hushed and reverent tones about “Governor Tugwell” and “Mr. Luchetti”, the “glory that was PREPA” and how it was the “crown jewel”. To them I say, well, sic transit and good luck with that — all those things happened a long time ago. Those of us who have lived through PREPA’s implosion should know better.

That is why I looked up the Official Statements for PREPA’s last two bond offerings, dated April 12, 2012 (the “2012 OS”) and August 15, 2013 (the “2013 OS”), respectively. These documents contain a wealth of data and information about Puerto Rico’s electricity system. And they tend to be accurate, as they are prepared in accordance with federal securities laws.

Speak, Memory

So what did we find? First off, we found that as of August 2013, PREPA had been reporting operating losses for several years in a row. According to the 2013 OS: “For each of the last four fiscal years the Authority incurred losses before contributed capital in accordance with GAAP. These losses reflect the continuation of a historical trend of net losses that have resulted in a deficit in the Authority’s consolidated net assets of $515.7 million as of June 30, 2012. This means that, as of June 30, 2012, the Authority’s total liabilities of $10.8 billion exceed its total assets of $10.3 billion.” (2013 OS, p. 21). In other words, PREPA was already insolvent, on a balance sheet basis, as of the end of fiscal year 2012.

Furthermore, during fiscal years 2011, 2012, and 2013 PREPA’s liquidity deteriorated significantly and “due to liquidity constraints the Authority had a need to use lines of credit and Power Revenue Bonds to finance its operational expenses.” (2013 OS, p. 22). This practice raises a red flag for two reasons. First, using long-term debt to finance operating expenses is always first and foremost a clear sign of financial distress. And, second, by diverting debt proceeds to pay for operational expenses, this practice limited the amount of funds available for financing the capital expenditures necessary for system maintenance. This affected the maintenance for the entire system, including the generation component, as “about half of the $787.5 million in capital expenditures for the five fiscal years ended June 30, 2013 for production plant was spent for such scheduled maintenance.” (2013 OS, p.38).

By 2013 it was well known that PREPA relied too much on debt to finance its capital improvement program. Indeed, both the 2012 OS and the 2013 OS state that such reliance “has caused the Authority’s level of indebtedness and related debt service requirements to increase significantly” and “the Authority’s Consulting Engineers have recommended that the Authority increase the amount of its capital improvement program funded from internally-generated sources.” (2012 OS, p. 17 and 2013 OS, p. 21). Alas, PREPA never did comply with that recommendation.

It should not be surprising then that this combination of (1) low liquidity; (2) funding current spending with long-term debt; and (3) limited access to the capital markets due to increased levels of indebtedness and debt service, resulted in a significant reduction in system maintenance expenditures. And that is exactly what the Official Statements demonstrate, a reduction in maintenance spending, from $250.6 million during fiscal year 2007 to $213.9 million during fiscal year 2013, a decrease of $36.7 million, or 14.6%. (2012 OS, p. 71 and 2013 OS, p. 58)

The lack of maintenance, in turn, affected overall system performance. Between 2007 and 2011, the annualized electric generation equivalent availability decreased significantly, from 84% in 2007 to 78.9% in 2011; while the equivalent forced outage rate (an indication of the average percentage of total dependable generating capacity which is unavailable throughout the year due to forced outages or partial generating capacity outages) increased considerably, from 10% to 15.8%, during the same period. (2012 OS, p. 51). Meanwhile, the Dependable Reserve Margin, which is the reserve capacity available as a percentage of peak load, was forecast to decrease from 77% in 2014 to 67% in 2018. (2013 OS, p. 40).

A Series of Unfortunate Events?

So, while PREPA officially claimed that it suffered from a series of unfortunate events caused by a veritable menagerie of small animals, both feral and domestic — wandering cats, leaping lizards, hopping iguanas, and critters of a hitherto unknown genus and species that ostensibly “lived” inside electricity meters — most of which presumably faced a ghastly demise by coming into contact with the wrong end of a 13 kV line, the truth is that by the time PREPA filed for bankruptcy in May 2017 the system was already thoroughly fragile, with decreasing available capacity; increasing outage rates; and limited available reserves. The masters of disaster have a short memory, indeed.

And then Hurricane María hit, devastating the transmission and distribution system in September 2017. According to data from the Federal Emergency Management Agency (“FEMA”), within hours of Hurricane María’s landfall in Puerto Rico, 100 percent of PREPA’s clients were without electric power service and 80 percent of its infrastructure was destroyed. After a slow start, tainted by some unbecoming shenanigans involving two fly-by-night corporations based in the mainland, it took several billion dollars and the better part of a year to restore electric service throughout the island.

However, as important and massive as that job was, it was always understood that it was not a permanent fix — a thorough refurbishing of the grid was necessary to bring it up to 21st century standards. PREPA estimated such refurbishing would cost north of $10 billion. Years of negotiations with FEMA followed, until an agreement was reached in December 2020. In the meantime, the patched-up grid kept acting up.

On the generation side not much happened either, as evidenced by the continued dispatch of the Palo Seco generation plant, a fantastically aged contraption, described by a former Assistant Secretary of the U.S. Department of Energy in a 2019 Congressional hearing as a “defunct facility.” To be fair, two generation units of the San Juan plant were recently “upgraded” to burn natural gas, but through a suspicious transaction that is currently under scrutiny by the Federal Energy Regulatory Commission.

The Plot Thickens

Such was the neglected state of Puerto Rico’s electricity system — an old, unreliable, fossil fuel-based generation fleet connected to a functional but fragile and unstable transmission and distribution grid — when PREPA and the government of Puerto Rico executed a long-term agreement for the operation and maintenance of the electric grid (the “O&M Agreement”) with LUMA, a Canadian/Texan consortium.

Under the O&M Agreement, PREPA is in charge of the generation (along with a couple of private generators) and LUMA is in charge of the transmission grid. In practice, though, things are seldom so clear cut; because if electricity is to be delivered to the final customers, then PREPA and LUMA have to interconnect and closely coordinate the amount of energy loaded into the system at any given time.

In general, the demand and supply of electricity have to be balanced at all times. If the transmission lines are congested because the load exceeds the demand then the grid will not accept additional load and some generation will shut down. Conversely, if demand exceeds the capacity of the grid to deliver electricity at any given time, then parts of the transmission and distribution system will go offline. So, keeping the lights on requires a kind of hand-in-glove coordination between PREPA and LUMA, as PREPA runs the generation fleet but LUMA determines which generation resources interconnect with the grid, at what time, and in which order.

That coordination is ostensibly executed in accordance with the terms and conditions of another agreement among and between PREPA, LUMA, and the Puerto Rico P3 Authority: the GridCo – GenCo Power Purchase & Operating Agreement (the “PPOA”). To the best of our knowledge, the PPOA has not been made public, but Exhibit H to the O&M Agreement sets forth a term sheet for the PPOA. According to the term sheet, these are some of the key terms and conditions of the PPOA:

  • Pursuant to the PPOA, GenCo agrees to sell and GridCo agrees to accept delivery of and purchase the Energy and/or Dependable Capacity of the Generating Facilities, which shall not be reduced except as provided by the PPOA.
  • Each Generating Facility will be assigned a “Dependable Capacity” which is the net electric generating capacity (gross electric generating capacity less station use) in kW, as determined by testing to be performed from time to time pursuant to the PPOA, which shall also determine the optimal output to meet system load requirements at the lowest possible cost to reliably service customers while recognizing the operational limits of the generation facilities…
  • For any contract year…GenCo shall prepare and deliver to the T&D Operator (with copy to GridCo)…its proposed operations and maintenance budget (the “Operating Budget”) and proposed capital budget (the “Capital Budget”, together with the Operating Budget, the “Budgets”) for such year, together with financial forecasting for the following two (2) contract years.
  • The Operating Budget for any contract year shall include a month-by-month estimate of (i) the working capital reasonably determined by GenCo to be needed for the day-to-day operation of GenCo, (ii) fixed and variable operations and maintenance costs, and (iii) costs and expenses associated with fuel purchases (including a two percent (2%) in excess of the total amount for excess expenditures that may arise in any contract year), in each case for the following contract year.
  • GridCo shall pay GenCo a monthly amount based on the approved budgets, including any costs and expenses for approved capital improvements relating to the Generating Facilities and related supplemental working capital and all costs and expenses associated with the operation and maintenance of a ramped down unit and/or Generating Facility (the “Monthly Generation O&M Charge”).
  • The T&D Operator, as agent of GridCo and dispatch manager, shall at its sole discretion have the right to dispatch the units at the Generating Facilities within their operational limits and in accordance with the principles related to the dispatch of power and electricity set forth in Schedule 1 to Annex I (Scope of Services) of the T&D O&M Agreement.

So there you have it. PREPA is required to provide “dependable generation capacity” in exchange for a monthly payment from LUMA to cover operating and maintenance expenses, as well as approved capital expenditures; while LUMA has absolute control to dispatch generation and manage system load at any given time.

Notice the complex nature of the current arrangement: PREPA is responsible for the operation and maintenance of the generation fleet, while LUMA is in charge of funding PREPA’s operations on a monthly basis and dispatching load into the grid. Given the complicated character of this relationship, we suspect that the recent rolling blackouts are as much a function of (1) a decrepit generation fleet and an unstable transmission and distribution grid as of (2) a series of coordination failures between PREPA and LUMA.

Given this state of affairs, this is what we can expect and what we hope can be done:

  • It will take about 10 years to upgrade the transmission and distribution system, with or without LUMA. This task is exceedingly complex and expensive. And there are no shortcuts.
  • The modernization of the generation fleet will also take several years, be it with additional natural gas capacity, increased generation from renewable sources, or a combination of both.
  • The above means that in the short term electric service in Puerto Rico will continue to be unreliable and expensive.
  • Rising fossil fuel prices (including natural gas), the unavailability of several low-cost generation units to meet base load due to unforeseen breakdowns, and the obligation to eventually start paying debt service on PREPA’s restructured indebtedness, will be the main drivers of the cost of electricity in Puerto Rico.
  • Nonetheless, some remedial measures could be implemented in the short term to stabilize the transmission and distribution system and to reduce the dependence on the use of high-cost peaking units. It is up to both PREPA and LUMA to identify those “quick wins” and execute them.
  • In addition, the transition to renewable generation must continue. The generation of electricity using renewable sources protects both the environment, by lowering emissions of greenhouse gases, and consumers, by stabilizing the price of electricity. It is not true that electricity from renewable sources is always more expensive than electricity generated with traditional fuels. The technology for solar and/or wind generation in combination with battery storage has developed significantly during the last few years, in some cases approaching the costs of natural gas generation.
  • Furthermore, in order to properly compare costs between one kind of generation and another, it is necessary to add the cost of the environmental and health damages caused by fossil fuel generation. Adding in the costs of these negative externalities almost always reveals that fossil generation is costlier than initially thought. The imposition of a carbon tax is one of several policy alternatives to force polluters to internalize the cost of these negative externalities they impose on society at large.
  • Finally, it is imperative that the government agencies in charge of implementing energy policy in Puerto Rico have the necessary resources to execute their respective missions: (1) the PREB to regulate rates and promote long-term planning for the system; (2) the P3 Authority to effectively monitor and robustly enforce the O&M Agreement with LUMA; and (3) PREPA to adequately coordinate the day to day operation of the generation system.

Conclusion

While we understand and sympathize with the feelings of frustration expressed by many Puerto Ricans in connection with recent rolling blackouts, it would be a mistake to romanticize the old PREPA. As we have demonstrated above, things were not all copacetic when PREPA was in charge, Puerto Rico’s energy woes were years in the making and are the direct result of PREPA’s mismanagement, negligence, and corruption. Handing control back to the masters of disaster is not an option.

However, PREPA’s indictment is not LUMA’s vindication. LUMA had about a year to prepare for the takeover of Puerto Rico’s electricity grid and its performance so far has been, in the best case, deficient, and in the worst, dismal. Its management, so far, has utterly failed to deliver on its promises.

Finally, it is important to keep in mind that both PREPA and LUMA bear some responsibility for the recent malfunctioning of Puerto Rico’s electricity system. The process negotiated under the aegis of the Puerto Rico P3 Authority requires good faith efforts from both companies to run the system successfully. We suspect, though, that PREPA is desperately clinging to its old ways of doing things, while LUMA has probably not internalized the fact that it needs to modify its standard playbook to account for an old, unstable, and unreliable electric system. It is in the best interests of both companies to change their ways, for their own benefit and the wellbeing of the Puerto Rican people.